(Case C-212/18 Request for a preliminary ruling from the Tribunale Amministrativo Regionale per il Piemonte (Italy) lodged on 26March 2018— Prato Nevoso Termo Energy Srl v Province of Cuneo, ARPA Piemonte
Fecha: 06-Abr-2006
Request for a preliminary ruling from the Tribunale Amministrativo Regionale per il Piemonte (Italy) lodged on 26March 2018— Prato Nevoso Termo Energy Srl v Province of Cuneo, ARPA Piemonte
(Case C-212/18)
Language of the case: Italian
Referring court
Tribunale Amministrativo Regionale per il Piemonte
Parties to the main proceedings
Applicant: Prato Nevoso Termo Energy Srl
Defendants: Province of Cuneo, ARPA Piemonte
Questions referred
Do Article6 of Directive 2008/98/EC1 and, in any case, the principle of proportionality, preclude provisions of national law, such as Article293 of Legislative Decree No152/2006 and Article268 paragraph eee-bis) of Legislative Decree No152/2006, which provide that, even in the ambit of a procedure for authorisation of a biomass-powered plant, a bioliquid that fulfils the technical requirements in that respect and is requested for production purposes as fuel must be considered waste if and so long as it is not included in Annex X part II, section 4, par.1 in Part V of Legislative Decree of 3April 2006, No152, irrespective of any adverse environmental impact assessments, or of any dispute as to the technical characteristics of the product, arising in the context of the authorisation procedure?
Do Article13 of Directive 2009/28/EC2 and, in any case, the principles of proportionality, transparency and simplification preclude a provision of national law such as Article5 of Legislative Decree No28/2011 insofar as it does not provide, when the applicant requests authorisation to use biomass as fuel in a plant producing emissions into the atmosphere, for any coordination with the procedure for authorisation of that use as fuel under Legislative Decree No152/2006, Annex X Part V, or provide for the possibility of specifically assessing the solution proposed in the context of the single authorisation procedure and having regard to pre-defined technical specifications?