Order of the President of the Court of First Instance of 23 January 2009 – UnityOSGFZE v Council and EUPOL Afghanistan
(Case T-511/08 R)
Application for interim measures – Public procurement – Rejection of a tender – Application for suspension of operation of a measure – Loss of opportunity – No urgency
1.Application for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Prima facie case – Urgency – Cumulative nature – Order of examination and method of verification – Discretion of the judge dealing with the application for interim relief (Arts 225 EC, 242 EC and 243 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see paras 11-12)
2.Application for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Urgency – Serious and irreparable damage – Burden of proof (Arts 242 EC and 243 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see paras 22-23)
3.Application for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Urgency – Serious and irreparable damage (Arts 242 EC and 243 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see paras 27-28)
4.Application for interim measures – Conditions of admissibility – Application – Formal requirements – Statement of the pleas in law establishing a prima facie case for granting the measures sought (Arts 242 EC and 243 EC; Rules of Procedure of the Court of First Instance, Art. 104(2) and (3)) (see para. 29)
5.Application for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Serious and irreparable damage – Financial loss (Arts 242 EC, 243 EC and 288 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see paras 31, 33-34)
6.Application for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Serious and irreparable damage – Financial loss (Arts 242 EC and 243 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see paras 35-37)
7.Application for interim measures – Suspension of operation of a measure – Conditions for granting – Urgency – Serious and irreparable damage – Burden of proof (Art. 242 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see para. 38)
8.Application for interim measures – Suspension of operation of a measure – Conditions for granting – Serious and irreparable damage (Art. 242 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see para. 39)
Re:
APPLICATION for suspension of the operation of the decision, taken by EUPOL Afghanistan in the context of a call for tenders, to reject the applicant’s tender and to award the contract for the provision of guarding and close protection services in Afghanistan to another tenderer. |
Operative part
The Court:
1. |
| Dismisses the application for interim measures; |
2. |
| Reserves the costs. |