Estoppel and related concepts
Estoppel and related concepts
The next stage of Medpro’s case was that if the Contract, on its true construction, did require more than was delivered, DHSC nonetheless was estopped from relying on the relevant clauses which imposed those obligations. In other words it said that DHSC was not entitled to rely on the relevant contractual terms because some combination of what was said or done or believed rendered it unfair to do so. Medpro’s case was pithily summarised in its written closing thus: “[Medpro] provided the documents it had. DHSC approved the Contract based on those documents. That was a clear representation that PPEM’s offer met the applicable requirements; DHSC cannot now assert that they did not.”
This case went primarily to the EN 556 and CE marking aspects of the contractual case, and those are considered first.
Estoppel, of course, is not a generalised “mop up” concept to be applied in any case of perceived unfairness. It is the umbrella concept which links a number of distinct doctrines or rules – each with their own requirements. It is therefore necessary to be clear, in any given case, exactly which doctrine is relied upon, what the requirements of that doctrine are and how the distinct requirements are satisfied.
Medpro relied generally on contractual estoppel, estoppel by representation, estoppel by convention, estoppel by acquiescence. Although contractual estoppel was less in focus by closing, it continued to rely on the others somewhat globally, with the applicable doctrine depending on how the court interpreted the evidence which had emerged.
That being the case, it is worth commencing with an overview of what is involved in each of these concepts.
Contractual estoppel is conceptually distinct (as both parties really agreed – Medpro by its location within the skeletons). Contractual estoppel is all about holding a party to the terms of its contract (see Foxton J inRolls-Royce Holdings plc v Goodrich Corporation[2023] EWHC 1637 (Comm) at [47]). Therefore if Medpro is wrong on contractual construction, contractual estoppel offers no life line.
Estoppel by representation has the following elements (see Chitty on Contracts 35th ed. paragraphs 7-006-7-011):
Clear and unambiguous representation;
At least objective intention by representor that the representee will rely and that reliance should be reasonable (Footnote: 1);
Actual reliance in fact;
Prejudice/detriment if the representor is allowed to rely on the representation.
Estoppel by convention has the following elements (see Chitty paragraphs 7-016-7-028):
Both parties are involved in an assumed state of the facts or law;
That assumed state is unambiguous or clear;
The assumption must be shared and there must be words or conduct which crosses the line between the parties from which the necessary sharing may be inferred;
Both parties act on that assumed state of facts or law and specifically the party asserting it must in fact have relied upon the common assumption, to a sufficient extent, rather than merely upon his own independent view of the matter;
Prejudice/detriment if one party is allowed to rely on the real (non-assumed) facts/law.
Estoppel by acquiescence (in the sense relied upon by Medpro (Footnote: 2)) has the following elements:
One party to a transaction has made an assumption as to the state of facts or law;
That assumed state is unambiguous or clear;
The party estopped knew of the understanding adopted by the other and acquiesces in that assumption;
The party asserting it must in fact have relied upon the common assumption, to a sufficient extent, rather than merely upon his own independent view of the matter.
It can therefore be seen that there are certain elements which are common to most of the concepts prayed in aid by Medpro. In particular all of the estoppels cited require (i) some form of clear representation or assumption and (ii) the party invoking the estoppel to prove reliance in fact, and its correlate prejudice/detriment.
These two elements require some consideration.
- Heading
- This judgment was handed down by the court in person and by circulation to the parties’ representatives by email and released to The National Archives. The date and time for hand-down is deemed to be
- Sterility 101: An Introduction to sterility and Medical Device Law
- ISO 11137: Requirements of a Sterilisation Process
- Sterility level: EN 556
- Medical devices: MD Directive and MDR 2002
- Other relevant standards
- Summary
- Factual Background
- The PPE Cell
- The Recommendation
- The Essential Technical Requirements Document (“ETRD”)
- Precontractual Negotiations
- Closing
- Final Approval and Contract
- Manufacturing, delivery and inspection
- Rejection of the Gowns
- Testing of Gowns
- The Trial and issues
- The Contractual Claim
- The parties’ cases on construction
- The significance of the accepted obligation to deliver gowns with an SAL of 10 -6
- Was there breach of a requirement for a formally validated process in this case?
- Did the Contract require EN 556 or an Equivalent Technical Solution?
- Did the Contract require CE marking?
- The original case: Statistics, Physical Testing and Sterility
- Estoppel and related concepts
- Representation/assumption: clear?
- Approval of an ETS in place of EN 556
- Meeting the technical requirements/ No requirement to have a CE mark with an NB number
- Reliance
- Estoppel and validated process/SAL
- Non-Reliance and Entire Understanding Clauses
- Remedies
- Was the right to reject lost?
- Damages: The value of the Gowns and Mitigation
- Damages: The Claim for Storage Costs and Gown Disposal
- The Counterclaim
- Common mistake and rectification
- Negligent misstatement
- Conclusion
- Annex 1: Statistics, Physical testing and Sterility
- The testing
- Statistics
- The evidence and its implications
- The evidence gap
- Conclusion
- Annex 2: Relevant provisions of the Contract The Contract between DHSC and Medpro consists of a front page and several documents
- Order Form Section 5 of the Order Form “ The Supplier shall supply the deliverable described below on the terms set out in this Order Form and the Schedules and Annex A. Unless the Contract otherwise requires, c
- Section 7 of the Order Form is headed “Specification” and states: “The specification of the Deliverables is as set out in Annex A.1 – A.9 [26.06.2020]. Not as embedded/attached documents. Please confi
- Schedule 1
- Clause 2.2 of Schedule 1 states that the Order Form is to “ include, without limitation, the Authority’s requirements in the form of its specification and other statements and requirements, the Suppli
- Clause 3 of Schedule 1 is headed “ Quality assurance standards ” and states: “The following quality assurance standards shall apply, as appropriate, to the manufacture, supply, and/or installation of
- Conclusions
![CL-2022-000676 - [2025] EWHC 2486 (Comm)](https://backend.juristeca.com/files/emisores/logo_WAai98v.png)