The effect of the Spin-Off plan as a matter of Korean law
The effect of the Spin-Off plan as a matter of Korean law
Should I decide this issue?
Mr Dunning KC submitted that I need not and should not decide the effect of the Spin-Off plan, but should leave this to the arbitrators in any future arbitration. However, I accept Ms Morgan’s submission that understanding the effect of the Spin-Off is an issue which arises as part of the s.67 challenge, and one, therefore, which the court has jurisdiction to determine de novo:
It provides important context to the issues which arise as to who commenced the arbitration, and to how the RFA was to be understood by a reasonable reader in the position of Energyen. I note that in decisions such as Internaut Shipping GmbH v Fercometal SARL [2003] EWCA Civ 812, SEB Trygg Holding AB v Manches [2005] EWHC 35 (Comm), [2005] EWCA Civ 1237 and Eurosteel Ltd v Stinnes AG[2000] CLC 470, in which the court has faced similar issues to those which arise in this case, the court has itself sought to identify the parties to the arbitration agreement for the purposes of resolving disputes as to whether an arbitration had been validly commenced and/or continued, and who the parties to the reference are.
Energyen has itself squarely raised this issue as one of its jurisdictional challenges (paragraphs 9 and 10 of the Re-Amended Claim Form, being the first jurisdictional points taken) and it is a jurisdictional issue which directly arises if I conclude that the HHI 2019 Company is the arbitral claimant.
The jurisdictional challenge based on the effect of the Spin-Off plan was the primary basis of Energyen’s challenge at all times until the service of Mr Dunning KC’s skeleton argument.
In any event, I should state that the effect of the Spin-Off plan so far as the Supply Contract is concerned seems obvious.
- Heading
- This is the hearing of challenges under ss.67 and 68 of the Arbitration Act 1996 (“ the 1996 Act ”) in relation to the Final Award in ICC Case 26615/XZG (“ the Award ”)
- The issues in summary
- The facts
- The Spin-Off plan
- The effect of the Spin-Off plan as a matter of Korean law
- The rival cases
- The translation issue
- The position as a matter of Korean law
- The effect of the Spin-Off plan as a matter of English law
- The dispute emerges and is referred to arbitration
- Energyen’s jurisdiction challenges
- Who commenced the arbitration?
- Did the HHI 2019 Company validly commence the arbitration?
- The notice issue
- The position if the Original HHI Signatory had been the arbitral claimant?
- The section 73 argument
- Conclusions
![Claim No: CL-2024-000563 - [2025] EWHC 1586 (Comm)](https://backend.juristeca.com/files/emisores/logo_WAai98v.png)