VIII: EuroChem NW2’s demands on the Bonds [38]-[40]
VIII: EuroChem NW2’s demands on the Bonds [38]-[40]
EuroChem NW2’s initial demands under the Bonds were made on 4 August 2022. All except the demand made to SocGen Milan were rejected on the basis that they were technically non-compliant with the terms of the Bonds.
In respect of all the Bonds except that issued by SocGen Milan, EuroChem NW2 served fresh demands on 10 and 11 August 2022. They were all in similar form and all notifying the respective Bank that “… a Contractor has defaulted in its obligations under a Contract…” In ING’s case, the demand then went on by giving some details about the nature of the alleged defaults, including the contractual provisions which were said to have been breached by Tecnimont and/or MT Russia.
In each instance, EuroChem NW2 instructed that payment be made to its Euro account with Gazprombank in Moscow, via a correspondent bank in Luxembourg.
- Heading
- PART A: INTRODUCTION AND PARTIES [1]-[22]
- II: The Claimants [11]-[17]
- III: The Banks and Tecnimont [18]-[20]
- IV: The new Kingisepp plant [21]-[22]
- PART B: THE BONDS AND EUROCHEM NW2’S DEMANDS [23]-[45]
- VI: Designation under Regulation 269 [29]-[33]
- VII: Termination of the Contracts [34]-[37]
- VIII: EuroChem NW2’s demands on the Bonds [38]-[40]
- IX: Rejection of the demands [41]-[45]
- PART C: THE ISSUES AND THE WITNESSES [46]-[98]
- XI: The Claimants’ EuroChem AG witnesses [59]-[66]
- Mr Valters and Mr Solzhenitsyn
- Mr Hechler
- Mr Collishe
- Ms Basyrova
- XII: The Claimants’ EuroChem NW2 witness [67]-[73]
- XIII: The Claimants’ Trust witnesses [74]-[94]
- Mr Fokin
- Mr Noble
- XIV: The Banks’ witnesses [95]-[98]
- PART D: THE FACTS RE OWNERSHIP AND CONTROL [99]-[211]
- The Trusts above EuroChem AG
- The structure from EuroChem AG downwards
- XVI: The ownership structure after sanctions [110]-[123]
- Changes at the level of EuroChem AG
- Changes in directorships
- XVII: Other group structural changes [124]-[144]
- The “Future of EuroChem” memorandum
- The transfers to MCC EuroChem
- The UAE trading cluster
- Changes within EuroChem AG and the EU subsidiaries
- XVIII: Mr Melnichenko’s involvement before March 2022 [145]-[151]
- XIX: The Claimants’ first pleading point [152]-[154]
- XX: The date of the Deed of Retirement [155]-[165]
- XXI: The role of Mrs Melnichenko [166]-[175]
- XXII: Mr Melnichenko’s involvement after March 2022 (1) [176]-[187]
- XXIII: The Claimants’ second pleading point [188]-[197]
- XXIV: Mr Melnichenko’s involvement after March 2022 (2) [198]-[204]
- XXV: The Assignment [205]-[211]
- PART E: REGULATION 269 [212]-[305]
- XXVII: The supplementary EU materials [220]-[225]
- XXVIII: Decisions of the CJEU [226]-[229]
- XXIX: How to interpret Regulation 269 [230]-[240]
- XXX: Article 2(1) [241]-[248]
- XXXI: Article 2(2) [249]-[259]
- XXXII: “Ownership” [260]-[278]
- XXXIII: The Claimants’ third pleading point [279]-[282]
- XXXIV: The MP Bank v Pugachev point [283]-[293]
- XXXV: “Control” [294]-[305]
- PART F: THE NCAS [306]-[347]
- XXXVII: Firewalls and the NCAs [312]-[313]
- XXXVIII: The French NCA: the DGT [314]-[326]
- XXXIX: The Italian NCA: the CSF [327]-[332]
- XL: The Swiss NCA: the SECO [333]-[337]
- XLI: The Cypriot NCA: the SEOK [338]-[341]
- XLII: The Dutch NCA: the BTI [342]-[347]
- PART G: APPLYING REGULATION 269 [348]-[411]
- XLIV: Inferences [360]-[369]
- XLV: Article 2(1) and the Bonds [370]-[378]
- XLVI: The LIA v Maud point [379]-[399]
- XLVII: Article 2(1) and the Assignment [400]
- XLVIII: Article 2(2) and payment to EuroChem NW2 [401]-[403]
- XLIX: Article 2(2) and payment to EuroChem AG [404]-[408]
- L: The pending applications to the DGT and the CSF [409]-[411]
- PART H: REGULATION 833 [412]-[473]
- LII: Are the claims “in connection with” the Contracts? [416]-[429]
- LIII: Are the claims by or on behalf of a Russian entity? [430]-[433]
- LIV: Conclusion on Regulation 833 [434]-[435]
- PART I: THE RULE IN RALLI BROTHERS [436]-[473]
- LVI: The rule in Ralli Brothers [438]-[440]
- LVII: The place of performance under the Bonds [441]-[461]
- LVIII: Licence applications and Article 7 [462]-[465]
- LIX: Public policy [466]-[470]
- LX: Implied term [471]-[472]
- LXI: Conclusion on the rule in Ralli Brothers [473]
- PART J: OTHER ARGUMENTS [474]-[494]
- LXIII: The Bonds’ expiry dates [476]-[478]
- LXIV: Validity of the Assignment [479]-[482]
- LXV: The Assignment and Article 9 [483]-[486]
- LXVI: The sanctioned Russian banks [487]-[491]
- LXVII: ING’s Part 20 claim against Tecnimont [492]-[494]
- Conclusions
![CL-2022-000456 - [2025] EWHC 1938 (Comm)](https://backend.juristeca.com/files/emisores/logo_WAai98v.png)