Readie Construction & CE Energy
Readie Construction & CE Energy
For the reasons set out below, I have concluded that:
the ratio of Readie Construction is that (a) the contract price in that case was payable ‘irrespective of delivery’ within the meaning of s.49(2) of the Act, on the ground that that required the payment date not to be the contractual delivery date, not that the obligation to pay be not conditional upon delivery, and (b) the payment clause in the contract precluded the defence of abatement asserted by the defendant;
as regards (a), Readie Construction is wrongly decided and should not be followed;
Readie Construction does not decide anything about the meaning of ‘day certain’ in s.49(2), since that point was conceded;
the ratio of CE Energy, so far as concerns one of the claims on which summary judgment was granted under a guarantee, is (or at any rate includes) that (a) it had to be shown that an action for the price in question could have been maintained under s.49(2) against the primary obligor, and (b) such an action could have been maintained because that price was payable on a ‘day certain’ within the meaning of s.49(2), as to which Shell-Mex should no longer be followed;
CE Energy is wrong to treat Readie Construction as an authority on ‘day certain’, but I do not need to decide anything about that part of s.49(2) or, therefore, about the decision in CE Energy not to follow Shell-Mex;
CE Energy does not decide anything about the meaning of ‘irrespective of delivery’ in s.49(2), and I respectfully take a different view of Readie Construction to the view taken, obiter, in CE Energy, which was that the difficulties with Readie Construction are not such as should lead to a refusal to follow it.
In Readie Construction, the claimant buyer contracted to buy from the defendant seller a quantity of GSB Type 1 aggregate at £19.50 per tonne, for delivery to a construction site at Marston Vale, Wootton, Beds. There was a retention of title clause. 31,000 tonnes of GSB Type 1 were delivered, invoiced and paid for. 9,576 tonnes were delivered, invoiced and not paid for, because (so the defendant alleged) after heavy rainfall at the site over the weekend of 13-14 October 2018, “the aggregate” had liquified and turned into slurry and the defendant decided to suspend payments (per Martin Spencer J at [4]). By then, 34,000 tonnes of the GSB Type 1 delivered by the seller had been laid at the site, creating a sub-base that was 87% complete (ibid). The judgment does not say whether “the aggregate” that had become slurry was (said to be) all of it (40,576 tonnes), the quantity not paid for (9,576 tonnes), the quantity not yet laid (6,576 tonnes), or some other portion.
The payment clause required payment “in full without any deduction or withholding whatsoever on any account by the end of the calendar month following the month in which the relevant invoice was dated” (Clause 4.1, quoted by Martin Spencer J at [5]). The buyer conceded that that made the price payable on a ‘day certain’ within s.49(2) (per Martin Spencer J at [21]).
In the Central London County Court, HHJ Johns QC granted summary judgment to the seller for the unpaid price, and the buyer appealed, claiming an entitlement to abate the price that was not precluded (so it argued) by the terms of the payment clause, alternatively that s.49(2) was not satisfied by that clause. Martin Spencer J dismissed the appeal.
As regards s.49(2), the appeal was dismissed on the ground that s.49(2) did not concern the conditionality or unconditionality of the obligation to pay the price upon performance by the seller of its obligation to deliver, but concerned instead (per Martin Spencer J at [48]) “the time of delivery and the time of payment. Once these are divorced from each other under the terms of the contract, the contract becomes one whereby the price is payable on a day certain irrespective of delivery” (original emphasis). Hence Mr Debattista’s submission that the question, following Readie Construction, is whether the contract provides for payment to be made on a ‘day certain’ that is not the contractual delivery date.
In taking that view of s.49(2), Martin Spencer J, at [48], adopted “the judgment and reasoning of Judge Yang [sic., Asst. Registrar Tan] in Mitsubishi”, adding that in his view:
(at [49]) it was further supported by what Longmore LJ said, obiter, in Caterpillar, supra, at [44] (as to which Martin Spencer J agreed with HHJ Johns QC that Longmore LJ’s dictum was referred to apparently without criticism by Lord Mance, obiter, in The Res Cogitans, supra, at [50]), and by what Males J had said, obiter, at first instance in The Res Cogitans, supra, at [73].
The seller’s argument in Readie Construction was that payment was linked to invoicing rather than delivery and even if invoices in fact followed deliveries, payment was not concurrent with delivery as envisaged by s.28 of the Act – delivery prior to payment had the effect of breaking the linkage between the two (per Martin Spencer J at [33]).
I find myself persuaded by Mr Nolan KC’s argument that Readie Construction is wrongly decided and should not be followed. If it was a considered decision after full argument not to follow the long-standing first instance decisions with which it is inconsistent, I may have needed to hesitate longer over whether I ought nonetheless to follow it despite my disagreement with it. However, and it is one of the reasons why I respectfully consider that Readie Construction is not a satisfactory decision, Martin Spencer J did not identify that he was not following long-standing prior authority and was “depart[ing] from conventional understandings of s.49(2) as being based on independent promises irrespective of delivery …” (Benjamin, at 16-027, n.197).
For the reasons given in my discussion of Mitsubishi, Caterpillar, and The Res Cogitans in Appendix B, in my respectful view:
the obiter dicta of Longmore LJ in Caterpillar and Males J in The Res Cogitans provide no reason to doubt or depart from what has been the accepted understanding of ‘irrespective of delivery’ in s.49(2), which (in my view) simply gives effect to the ordinary meaning of the statutory language; and
the obiter dictum of Lord Mance in The Res Cogitans at [50] is unclear, but not a basis for departing from Stein Forbes and Muller Maclean.
As regards Lord Mance having referred without criticism to Longmore LJ’s dictum (per Martin Spencer J within [49], quoting HHJ Johns QC at [39]),that concerned ‘day certain’, which was not in issue in Readie Construction, and not ‘irrespective of delivery’, which was.
At [48], Martin Spencer J noted that on the interpretation advocated by counsel for the buyer, “the fact I have held that delivery, or purported delivery, is a pre-condition to the obligation to pay the price would mean that section 49(2) is not fulfilled”, and continued: “However, in my judgment that interpretation is not correct”, citing Mitsubishi. If by that Martin Spencer J was drawing a distinction between cases where delivery and payment are concurrent conditions (to which s.49(2) would not apply) and cases where delivery is a condition precedent to payment (to which s.49(2) would apply, subject to ‘day certain’), that would, I think, still be inconsistent with the ratio of the prior decisions. There is also an internal inconsistency there, I think, in that Martin Spencer J’s conclusion that delivery was a pre-condition for payment was in these terms, at [39]:
“The starting point is, as [counsel for the buyer] submitted, that this contract is one which provides that delivery of the goods is a “condition precedent” to payment of the price. … . Thus, this is not one of those contracts such as in Totsa [], where the obligation to pay arose on delivery of documents, irrespective of delivery of the goods” (my emphasis).
In Totsa, viz. Totsa Total Oil Trading SA v Bharat Petroleum Corp [2005] EWHC 1641 (Comm), s.49 of the Act was not raised or considered. The contract was an f.o.b. contract, payment against invoice and usual shipping documents not later than 30 days after the bill of lading date. Martin Spencer J does not identify a source for the view that the price in Totsa was payable irrespective of delivery. If it was simply the contrast he drew between a delivery of usual shipping documents and a delivery of goods, in my view that misunderstood the ordinary incidents of international sales. As it happens, therefore, I think it was incorrect to say that the contract in Totsa provided for the price to be payable ‘irrespective of delivery’; but that does not remove the internal inconsistency in Readie Construction between holding at [39] that the contract was not a contract providing for payment irrespective of delivery, and deciding the case at [46]-[49] on the basis that it was such a contract.
At [22]-[24], Martin Spencer J recorded that the buyer relied on Stein Forbes, Muller Maclean, the obiter dictum of Lord Keith of Avonholm in White & Carter (Councils) Ltd v McGregor, and Otis Vehicle Rentals, and submitted that they decided between them that “a contract cannot be “irrespective of delivery” if delivery and payment are interdependent …”. The judge did not say anything different as to what those cases decided, and in my view the buyer’s submission was correct, save that, strictly, the point was decided only in Stein Forbes and Muller Maclean, as I explain in Appendix B. From his summary of the seller’s argument at [35]-[36] and his adoption of HHJ Johns QC’s reasoning at [49], I respectfully wonder if Martin Spencer J may have been led astray by dicta that, properly understood, concern ‘day certain’, which had been conceded before him, and do not touch ‘irrespective of delivery’, which was in issue.
In CE Energy, Paul Stanley KC granted summary judgment on claims under a guarantee, one of which, he decided, required it to be shown that there had been a debt due from the primary obligor, which required in turn that the claimant could have maintained an action for the price against that party under a contract for the sale of goods, namely (in the event) 14,941.015 m.t. of industrial gasoil on the m.t. Kmarin Restraint, for delivery ex-ship offshore Lomé, Togo.
By the contract, payment was to be made “latest 45 calendar days from NOR Lagos (NOR=1) to seller’s nominated bank account …”, and there was a retention of title clause. At [27], the learned deputy judge said that initially it was common ground that the NOR triggering the payment obligation was “the first notice of readiness given by a daughter vessel that was to tranship the cargo after its arrival at Lome”, but that it became common ground finally that it was “the first notice of readiness given on the arrival of the daughter vessel at Lagos to unload”.
If I have understood the facts of CE Energy correctly, the daughter vessels to which the deputy judge was referring were those that would receive delivery ex-ship Lomé from Kmarin Restraint, and their envisaged subsequent voyage to Lagos for discharge would come after such receipt. The learned deputy judge said (ibid) that nothing turned on the change in counsel’s joint position on the meaning of the payment clause, and it is clear from [103] that he decided the case on the basis, therefore, that the case did not turn on the meaning of ‘irrespective of delivery’, only on whether payment a fixed number of days after a NOR anticipated by the contract amounted to payment on a ‘day certain’. There may be a subtlety about that:
I would envisage that the arrival of a first daughter vessel at Lagos ready to discharge was not conditional upon the performance of the delivery obligation ex-ship Lomé for the balance of the contractual quantity not delivered by Kmarin Restraint to that first daughter vessel;
however, as regards the quantity so delivered, it might have been thought that that daughter vessel could not give the NOR Lagos required by the contract as a condition of payment without that part performance of the ex-ship delivery obligation;
however again, there is no hint in the judgment that any point was taken about that, so that in judging what CE Energy can be said to have decided and, if it arises, whether I should refuse to follow it, I think it right to treat it, as Mr Nolan KC submitted, as a case in which the only point in issue under s.49(2) was ‘day certain’.
That means CE Energy decided nothing of relevance to these appeals, which turn on payability ‘irrespective of delivery’. As regards ‘day certain’, Mr Stanley KC decided CE Energy on the ground, [102], that an obligation to pay latest 45 days after a defined NOR was an obligation to pay on a ‘day certain’ within s.49(2). I agree with Mr Nolan KC’s submission that the learned deputy judge erred in treating Readie Construction as a decision on ‘day certain’ (ibid and [99]), whereas the point was conceded in that case. But that is not the limit of Mr Stanley KC’s reasoning, and he did reach a considered view, after full argument, that Shell-Mex is not good law and should not be followed on the meaning of that term under s.49(2). Since the point does not arise here, though, I say no more about it.
As regards ‘irrespective of delivery’, Mr Stanley KC, at [100]-[101], and in part of [102], recognised that there were difficulties with the view adopted by Martin Spencer J, particularly its inconsistency with Stein Forbes, Muller Maclean and (the learned deputy judge thought) Otis Vehicle Rentals. Recognising that it did not affect the outcome in CE Energy, Mr Stanley KC indicated, at [101], that his doubts about the correctness of Readie Construction would not have led him to refuse to follow it. Having been persuaded by a clear margin that Readie Construction was wrongly decided, I do not consider that Mr Stanley KC’s obiter reluctance to say that he would not have followed it, despite concerns as to its correctness, is reason enough to decide these appeals on what I would consider to be an erroneous view of the meaning and effect of s.49(2) of the Act.
- Heading
- Introduction
- Facts and Issues
- A Procedural Objection
- Flawed Appeal (Wrong Remedy)?
- Error of Law?
- Day Certain
- Irrespective of Delivery
- Case Law on s.49(2)
- The Seller’s Arguments
- Readie Construction & CE Energy
- Conclusions
- Appendix A – The Procedural Objection In Vitol SA v Norelf Ltd [1996] AC 800, a case under the Arbitration Act 1979 , at 814B Lord Steyn explained, in holding that a respondent did not require leave to argue on appeal that an award should
- The permissibility in principle of arguing, substantially in line with a case advanced in the arbitration, that on the facts set out in an award, a result reached by the arbitrators is correct in law
- On that question, in Ramburs Inc v Agrifert SA [2015] EWHC 3548 (Comm) at [10], Andrew Smith J considered that
- That view was not decisive in Ramburs Inc , because “ the argument that the [respondent] buyers seek to raise … was not argued in the arbitration, and certainly not distinctly argued … . More importan
- MRI Trading (paragraph 27 above) was not referred to in Ramburs Inc , and according to the report at [2016] Bus. L. R. 135, Andrew Smith J was not referred in argument to any cases not mentioned in th
- Where a respondent does oppose a leave to appeal application under s.69 , so that CPR PD62 para 12.6 requires a respondent’s notice to be filed and served, the requirement in sub-paragraph (2) to stat
- That leads me not to agree with the view that a respondent’s notice filed and served under CPR 62 para 12.6 is in every respect ‘spent’, as Andrew Smith J expressed it in Ramburs Inc , once the leave
- In MRI Trading , Eder J indeed stated in unqualified terms, at [39], that “ a party who wishes to contend that an award should be upheld for reasons not expressed (or not fully expressed) in the award
- Furthermore, although the present case disproves, with respect, Jacobs J’s claim in MUR Shipping v RTI (paragraph 22 above), at [49], that it is “ invariably the case ” that the respondent to an appli
- I therefore do not consider that either MRI Trading or Cottonex Anstalt is authority for the proposition that CPR 62 para 12.6 requires a respondent who does not oppose the leave to appeal application
- Jacobs J’s view, for the case where a respondent does oppose the leave to appeal application, is in my view consistent with what I have said in paragraph A8 above. The careful way in which Jacobs J ex
- Stepping back, there might perhaps be room to consider that it would be better to require a respondent that opposes the leave to appeal application to file and serve a document setting out the grounds
- In MRI Trading , Eder J cited, as do Russell on Arbitration , 24 th Ed. (2015) at 8-167, and Ambrose et al. at 22.29, the decision of Moore-Bick J (as he was then) in Icon Navigation Corp v Sinochem I
- Moore-Bick J concluded that a contention of that kind was not a contention that the award should be upheld for a reason not expressed within the award, but an argument that it was not just and proper
- In his reasoning, Moore-Bick J observed ( ibid , at [22]) that s.69(7) of the 1996 Act “ must be read in the context of s.69 as a whole. The intention of the legislation is that the powers of the cour
- That was also the applicable provision when Field J decided The Mary Nour (No.2) . At that time, therefore, a respondent was required, whatever their stance in relation to the grant of leave to appeal
- In Cottonex Anstalt , supra , at [41], having stated in seemingly unqualified terms that a respondent wishing to contend that the award should be upheld on other grounds had to do so at the leave to a
- Acadia Chemicals , to which Hamblen J referred, a decision of Colman J under the 1979 Act , concerned what was then RSC Order 73, rule 5(9). That rule, like CPR PD62 para 12.3(3) that followed, but un
- It is fair to expect a respondent to be limited, as in Cottonex Anstalt itself, to points it took before the arbitrators that, if sound, would defeat or avoid a point which the appellant has brought t
- Appendix B – Case Law on s.49(2) Sale of Goods Act 1893 / 1979 Chalmers, “ The Sale of Goods Act 1893 ”, took the form of a commentary on the Act by its draftsman, Sir Mackenzie Chalmers. On p.91, Chalmers explained the understanding of the law that
- The references to “ goods sold ” are to goods the property in which has passed to the buyer pursuant to the sale contract. That historical account of the indebitatus counts for recovery of the price o
- The last edition of Chalmers is the 18 th Ed. (1981). The footnote citing Dunlop v Grote remains (p.222); and the paragraph quoted above is retained as a statement of the “ History ” of s.49 (p.223)
- The view expressed in Chalmers , that in some circumstances a claim for a sale contract price might lie outside s.49 , is the view expressed 35 years later by the Supreme Court, obiter , in The Res Co
- In Dunlop v Grote , a contract for 1,000 tons of No.1 Clyde or Dundyvan pig-iron, at 95s. cash per ton, stipulated that payment was to be made on 30 April for any balance of the contract quantity not
- The defendant argued that the case was like Laird v Pim (1841) 7 M & W 474, in which Parke B. had said, at 478, that “ a party cannot recover the full value of a chattel, unless under circumstances wh
- In Laird v Pim , a purchaser had been let into possession of land it had contracted to buy, but the sale was not completed. The vendor’s claim for payment of the price failed, but at trial it was awar
- For its part, the purchaser sought to overturn the award of damages inter alia on the basis that under the law as to dependent and independent covenants set out in the notes to Pordage v Cole , a vend
- Properly understood, therefore, Laird v Pim and Dunlop v Grote concerned the distinction elaborated in the notes to the report of Pordage v Cole , between dependent and independent covenants. In Dunlo
- Polenghi Bros v Dried Milk Co, Ltd (1904) 10 Com Cas 42 Polenghi Bros concerned a contract for the sale of dried milk powder by sample, where the delivery might be either c.i.f. London or f.o.b. Genoa. It provided that: “ Payment is to be made in cas
- The seller’s claim for the price seems to have been treated as standing or falling with its claim for a declaration, and s.49 was not mentioned either in argument or in the very short judgment. The se
- Kennedy J was not asked to decide, and did not purport to decide, anything about the meaning or effect of s.49(2) , and Polenghi Bros therefore does not assist either side in the present case. Benjami
- Workman Clark & Co, Ltd v Lloyd Brazileño [1908] 1 KB 968 The Court of Appeal dismissed an appeal against a decision of Walton J upholding a summary judgment granted by a Master (strictly, his order granting leave to sign judgment for the amount clai
- Order xiv , rule 1, required the plaintiff’s claim to have been for a “ debt or liquidated demand in money ” within what was then Order iii , rule 6. The ground of appeal was that, since no property h
- There was no issue before the Court of Appeal, therefore, as to the meaning of “ a day certain irrespective of delivery ”, and Workman Clark is no authority on that. In any event, the relevant instalm
- The ground of decision ( per Lord Alverstone CJ at 974-975, per Farwell LJ at 978, per Kennedy LJ at 979-981), was that whatever the rules had been concerning the old, distinct common law actions of d
- Farwell LJ, at 978-979, considered that “ any action falling under any of the eight common indebitatus counts, which is brought on an executed consideration for a fixed sum to be paid for such executi
- Benjamin , at 19-375, n.1686, says that there is doubt as to whether Workman Clark is any authority on the interpretation of s.49(2) because there are several reports of the case and, “ In the Law Rep
- It is doubtful nonetheless that Workman Clark decides anything about s.49(2) , but that is because it is arguable that what all three judges said about it is obiter . I do not need to take a final vie
- Stein Forbes & Co v County Tailoring Co (1916) 115 L.T. 215 That brings me to Stein Forbes , a decision of Atkin J (as he was then). Benjamin , at 19-379, n.1702, suggests that a difference in the sellers’ respective abilities readily to resell the g
- Stein Forbes was not about instalment prices, so I think it no surprise that Workman Clark is not mentioned, although Atkin J can be taken to have been familiar with it having been counsel for the suc
- Various defences raised by the defendant failed, leading Atkin J to conclude that it had broken the contract by not taking up the documents, and paying, for the Den of Glamis sheepskins, and then (at
- The first argument for the plaintiff was that it was entitled to the price although property had not passed on the ground that “ here was a sum certain payable at a fixed time and that, as the defenda
- Stein Forbes is, therefore, authority that a contract for the sale of goods for delivery c.i.f., payment “ cash against documents on arrival of the steamer ”, is not a contract falling within s.49(2)
- Although Stein Forbes concerned a c.i.f. sale, there is no basis for a different analysis of an f.o.b. sale where the price is payable against shipping documents through which the seller retains const
- Martin et al. v Hogan (1917) 24 CLR 234 Martin v Hogan is an unusual decision in the High Court of Australia. It is unusual because the Court sat as a constitution of six judges (Barton, Isaacs, Higgins, Gavan Duffy, Powers and Rich JJ) and
- Colley v Overseas Exporters [1921] 3 KB 302 A quantity of leather belting was contracted to be sold f.o.b. Liverpool. The goods to be sold under the contract were not ascertained when the contract was concluded, but leather belting was prepared
- McCardie J gave judgment for the buyer, dismissing the claim for the price. At 306, he said that s.49(2) of the Act “ does not apply, as it apparently did in Workman, Clark & Co. v Lloyd Brazileño , w
- Muller Maclean & Co v Leslie & Anderson (1921) 9 Ll. L. Rep. 328 In Muller Maclean , there was a contract for the sale of steel padlocks, prompt shipment with payment cash against documents in London, the price being £90 4s 3d and described in the he
- The seller’s claim for the price failed ( ibid , at 330 lhc-331 lhc). The seller said that s.49(2) applied. Roche J dismissed that claim, following and applying Stein Forbes . He rejected a submission
- A.A. Nortier & Co v Wm. Maclean, Sons & Co (1921) 9 Ll. L. Rep. 192 It is not clear from the report of Nortier v Maclean that any claim for the price was made, as opposed to claims for damages. The case concerned two separate contracts between the sa
- Shell-Mex, Ltd v Elton Cop Dyeing Co, Ltd (1928) 34 Com Cas 39 That brings me to Shell-Mex , under which a contract for the sale of 1,000 tons of fuel oil, for delivery by instalments, gave the seller (by Clause 15): “ the right at any time to invoic
- It is not easy to see that Clause 15, the special payment clause, did not provide for a price payable ‘irrespective of delivery’ as much as, and on that point in the same way as, the clause in Dunlop
- However, Wright J concluded that any price invoiced under Clause 15 “ still remains the price as of goods sold and delivered ”, or was “ still the price payable under the contract, which includes the
- The real ground on which Wright J decided Shell-Mex was that Dunlop v Grote could be distinguished, and s.49(2) did not apply, because Clause 15 of the sale contract did not provide for a ‘day certain
- White and Carter (Councils) Ltd v McGregor [1962] AC 413 This well-known case concerns the circumstances in which a contracting party that can complete performance of its obligations without any input from its counterparty is entitled to do so, and c
- Tradax v Goldschmidt [1977] 2 Lloyd’s Rep 604 In this case, decided by Slynn J (as he was then), the buyer under a contract for the sale of White Syrian barley f.o.b. stowed trimmed Lattakia, payment “ Cash against documents on presentation ”, re
- That decision was upheld on an appeal by way of case stated under the Arbitration Act 1950 . The first question stated for the court was whether the seller was entitled to recover US$26,728.24 (or any
- Otis Vehicle Rentals Ltd [2002] EWCA Civ 1064
- The claimant had pleaded readiness and willingness to deliver the tractor units pursuant to the repurchase contract created by the exercise of its option, but by the time the case came to trial the cl
- There were two grounds for the Court of Appeal’s decision ( per Potter LJ at [14]-[16])
- Caterpillar (NI) Ltd [2013] EWCA Civ 1232 , [2014] 1 WLR 2365 In Caterpillar , s.49 of the Act was relevant because the defendant buyer claimed to set off against claims for unpaid invoices two larger claims it asserted against the claimant, and cont
- The claim for the price in Caterpillar , then, like the claim for the price in Tradax v Goldschmidt , supra , was not a claim for goods sold and delivered, nor for goods bargained and sold, but a clai
- For summary judgment purposes, the payment clause in Caterpillar was taken to have required payment on the twenty-fifth day of the fifth month after the month in which the invoice was dated, meaning t
- In the section of his judgment concluding that there could be no claim for the price outside s.49 of the Act (which forms part of the ratio in Caterpillar as to which the court was unanimous), Longmor
- I have laboured that slightly because it makes clear, I think, that Longmore LJ took it to be settled law that ‘irrespective of delivery’ in s.49(2) required the obligation to pay the price not to be
- On the orthodox view of English law recognised and otherwise adopted by Longmore LJ, the payment clause in FG Wilson’s terms and conditions did not provide for the price to be payable irrespective of
- The Res Cogitans , [2015] EWHC 2022 (Comm) , [2016] UKSC 23 , [2016] AC 1034 In The Res Cogitans , arbitrators decided that the bunker supply contract at issue was not a contract for the sale of goods to which s.49 applied. That decision was upheld b
- At first instance, Males J said (at [71]-[73]) that if s.49 had applied, he would have held that a price payable within a fixed period after delivery was a price payable “ on a day certain irrespectiv
- I respectfully disagree with the reasons Males J gave for his ‘doubly obiter ” view, to the extent that it concerned the meaning of ‘irrespective of delivery’
- In the Supreme Court, as I noted at paragraph 61 above, it was said, obiter , that Caterpillar should be overruled on whether a claim for the price under a sale contract may lie outside s.49 of the Ac
- In reasoning to the conclusion that, had it mattered, Caterpillar would have been overruled on the exclusivity of s.49 for claims to the price in sale of goods contracts, at [45], Lord Mance, JSC, ref
- Lord Mance continued ( ibid ) by mentioning Longmore LJ’s obiter dictum in Caterpillar to the effect that a price payable within 30 days of an invoice date would be a price payable on a ‘day certain’
- I do not find it easy to identify the meaning of s.49(2) that Lord Mance had in mind. The reference to s.49(2) possibly having a ‘main focus’ on cases where there has not been delivery might suggest a
- However, the sentence which follows (“ Section 49 does not focus … ”) might suggest a view that a claim for the price of goods delivered but not sold is within s.49(2) , if the price is payable on a ‘
- Garmin Australasia Pty Ltd v B & K Holdings (Qld) Pty Ltd [2018] QCA 353 By contractual arrangements enabling the defendant to operate as a dealer in Garmin products, the defendant was obliged to pay for products ordered 45 days from invoice, the pla
- The New South Wales Sale of Goods Act 1923 applied, s.51(1)-(2) of which (quoted at [20]) are identical to s.49(1) -(2) of the Act s of 1893 and 1979. On the appeal, it was held that s.51(2) did not j
- Mitsubishi Corp RTM International Pte Ltd v Kyen Resources Pte Ltd [2019] SGHCR 6 This is a decision of Asst. Registrar Tan Xue Yang (Elton) (‘Tan AR’) in the High Court of Singapore. It concerned a contract for the sale of aluminium ingots by the pl
- The seller sought judgment on admissions for the total unpaid price amounts, arguing that the buyer’s pleaded admissions that it entered into the contract, that the goods were delivered to and receive
- Conclusions
![CL-2024-000457, 000458, 000459 - [2025] EWHC 1803 (Comm)](https://backend.juristeca.com/files/emisores/logo_WAai98v.png)