The local authority’s application for an extension of time
The local authority’s application for an extension of time
The District Tribunal Judge, on behalf of the FTT, refused the LA’s application for permission to appeal on 21 July 2025. Her ruling was issued to the LA (and the claimant) on 22 July 2025. The LA therefore had until 22 August 2025 to lodge an application directly with the Upper Tribunal. In fact, the LA’s renewed application for permission to appeal, although it was dated 21 August 2025, was not received by the Upper Tribunal until 28 August 2025. It was therefore six days late.
The LA’s application for an extension of time was put in the following terms:
We respectfully ask that the application to appeal is accepted if it is a few days late. The current appeal team members have been under an increasing workload and time constraints. This is because the 3.5 members deal with Housing Benefit, Council Tax liability, Council Tax Reduction and NNDR appeals. We are given strict deadlines by the Valuation Tribunal Service and have to respond to directions received by the HMTBS. We are currently down a full-time member of staff due to a medical emergency and it is also the holiday season and there are childcare responsibilities within the team members.
The proper approach to deciding whether to admit applications which are out of time was set out by the Court of Appeal in Mitchell v News Group Newspapers Ltd [2013] EWCA Civ 1537, [2014] 1 WLR 795, Denton v TH White Ltd [2014] EWCA Civ 906, [2014] 1 WLR 3926 and R (Hysaj) v Secretary of State for the Home Department [2014] EWCA Civ 1663. The approach was aptly summarised in Secretary of State for the Home Department v SS (Congo) & Others [2015] EWCA Civ 387 as comprising three stages. First, the seriousness of the delay must be assessed. Second, the reason for the delay must be considered. Third, all the circumstances of the case must be weighed so as to deal with the matter fairly and justly.
The relevant principles from the case law were helpfully set out by the Upper Tribunal (Immigration and Asylum Chamber) in R (Onowu) v First-tier Tribunal (Immigration and Asylum Chamber) (extension of time for appealing: principles) (IJR) [2016] UKUT 185 (IAC):
Turning to the first in time of the three recent and relevant decisions of the Court of Appeal, Mitchell v News Group Newspapers Ltd [2013] EWCA Civ 1537, [2014] 1 WLR 795. The Court of Appeal therein upheld a Master’s decision that a claimant who had served a costs budget six days late required relief from sanctions under CPR 3.9 before the costs budget could be considered by the court.
The decision in Mitchell was followed shortly thereafter by that of Denton v White [2014] EWCA Civ 906, [2014] 1 WLR 3926, which concerned three conjoined appeals each of which involved the application of CPR 3.9. to cases where the claimants had failed to comply with court orders or rules. For the purposes of our decision it is only necessary to draw attention the following passages:
[35] [The court] will take account of the seriousness and significance of the breach (which has been assessed at the first stage) and any explanation (which has been considered at the second stage). The more serious or significant the breach the less likely it is that relief will be granted unless there is good reason for it. Where there is good reason for a serious or significant breach, relief is likely to be granted. Where the breach is not serious or significant, relief is also likely to be granted.
[36] But it is always necessary to have regard to all the circumstances of the case. The factors that are relevant will vary from case to case. As has been pointed out in some of the authorities that have followed Mitchell, the promptness of the application will be a relevant circumstance to be weighed in the balance along with all the circumstances. Likewise, other past or current breaches of the rules, practice directions and court orders by the parties may also be taken into account as a relevant circumstance.
The decisions in both Mitchell and Denton had as their contextual setting private law civil proceedings. However, in R (Hysaj) v Secretary of State for the Home Department [2014] EWCA Civ 1663 the Court concluded that the same approach should be adopted in the public law arena, acknowledging when doing so that a public law claim may raise important issues for the public at large and that this should be a factor taken into account when considering whether there is a good reason for extending time.
At [93] of its decision in Secretary of State for the Home Department v SS (Congo) & Others [2015] EWCA Civ 387, the Court of Appeal drew together the learning from Mitchell, Denton and Hysaj, in these terms:
“…a Judge should address an application for relief from sanction in three stages, as follows:
i) The first stage is to identify and assess the seriousness or significance of the failure to comply with the rules. The focus should be on whether the breach has been serious or significant. If a judge concludes that a breach is not serious or significant, then relief will usually be granted and it will usually be unnecessary to spend much time on the second or third stages; but if the judge decides that the breach is serious or significant, then the second and third stages assume greater importance.
ii) The second stage is to consider why the failure occurred, that is to say whether there is a good reason for it. It was stated in Mitchell (at para. [41]) that if there is a good reason for the default, the court will be likely to decide that relief should be granted. The important point made in Denton was that if there is a serious or significant breach and no good reason for the breach, this does not mean that the application for relief will automatically fail. It is necessary in every case to move to the third stage.
iii) The third stage is to evaluate all the circumstances of the case, so as to enable the court to deal justly with the application. The two factors specifically mentioned in CPR rule 3.9 are of particular importance and should be given particular weight. They are (a) the need for litigation to be conducted efficiently and at proportionate cost, and (b) the need to enforce compliance with rules, practice directions and court orders…
The following further guidance can also be distilled from the judgment in Hysaj:
There is no merit in constructing a special rule for public authorities; they have a responsibility to adhere to the court’s rules even if their resources are ‘stretched to breaking point’ [42];
A solicitor or public body having too much work will rarely be a good reason for failing to comply with the rules [42];
Particular care needs to be taken in appeals concerning claims for asylum and humanitarian protection to ensure that appeals are not frustrated by a failure by a party’s legal representatives to comply with time limits. The nature of the proceedings and identification of responsibility for a failure are matters to be considered at the third stage of the process [42];
The inability to pay for legal representation cannot be regarded as providing a good reason for delay [43];
In most cases the merits of the appeal will have little to do with whether it is appropriate to grant an extension of time. Only in those cases where the court can see without much investigation that the grounds of appeal are either very strong or very weak will the merits have a significant part to play when it comes to balancing the various factors that have to be considered at stage three of the process [46].
…
Although none of the decisions cited above were made in the specific context that presents itself in the instant matter, we can see no good reason, and none was advanced by the parties, as to why the approach commended in Mitchell, Denton and Hysaj should not equally be applied to the First-tier Tribunal’s, and Upper Tribunal’s, consideration of an application for an extension of time to apply for permission to appeal (assuming of course that the notice of appeal was actually filed out of time). Nothing in the approach rehearsed above is in discord with the overriding objective of either the 2014 FtT Rules or 2008 UT Rules to deal with cases justly and fairly; indeed, it is the aspiration of achievement of these very objectives which was identified by the court in Denton, at [24], as underpinning the rationale for the third stage of the process of consideration.”
Applying the three-stage test set out in paragraph [13] of the Upper Tribunal’s decision in Owusu, I recognise first that the delay in question is relatively modest (six days as against a statutory time limit of one month). That said, it is not a question of a day or two but nearly a week.
I then turn to consider whether there was any good reason for the delay. I bear in mind the observations of the Court of Appeal in Hysaj. In particular, “public authorities have a responsibility to adhere to the court’s rules even if their resources are ‘stretched to breaking point’” and a “public body having too much work will rarely be a good reason for failing to comply with the rules”. Judged by those considerations, the LA’s reasons for requesting an extension of time are less than compelling. For example, the LA appears for whatever reason to have decided to prioritise work related to proceedings in the Valuation Tribunal over HB appeals.
Moving to the third and final stage of the process of consideration, I must consider whether it would be fair and just to grant an extension of time, taking a holistic approach to all relevant factors. Finality in litigation is an important principle. In that regard I consider that the claimant was justifiably entitled to consider that the matter was closed after the time for lodging a renewed application for permission to appeal had been passed. As the Court also explained in Hysaj, maintaining the integrity of procedural requirements is essential to the a court or tribunal’s ability to deal with all its cases justly and in accordance with the overriding objective. Last but not least, the LA’s shocking delay in forwarding the appeal and its response to the FTT means that it would be an affront to justice for the LA to be granted an extension of time.
On the basis of all of these considerations, I am satisfied that it is fair and just and in the interests of justice and in accordance with the overriding objective to refuse to grant an extension of time to admit the LA’s late application for permission to appeal. The factors relied upon for extending time are in my view insufficiently weighty to justify re-opening the dispute after the time for submitting an application for permission to appeal has passed. The matters relied on by the LA are far outweighed in this case by the importance of finality in litigation and the integrity of procedural time limits.
I therefore refuse to extend time for lodging the application for permission to appeal under rule 5(3)(a) of the Tribunal Procedure (Upper Tribunal) Rules 2008.
Accordingly, the LA’s application for permission to appeal to the Upper Tribunal is not admitted.
However, for completeness I proceed to explain briefly why I would have refused permission to appeal in any event.
- Heading
- Introduction
- The background to the local authority’s application for permission to appeal
- The local authority’s delay in forwarding the appeal to the First-tier Tribunal
- The local authority’s application for an oral hearing
- The local authority’s application for an extension of time
- The LA’s application for permission to appeal
- Conclusions
![[2025] UKUT 337 (AAC)](https://backend.juristeca.com/files/emisores/logo_3a2BKne.png)