Case No. HT-08-331
Technology and Construction Court

Case No. HT-08-331

Fecha: 08-Dic-2008

Introduction

1.The claimant (“PTB”) seeks summary judgment for £314,242.18 plus interest against the defendant (“ROK”) in respect of sums held due to PTB in an adjudicator's decision dated 1 October 2008. ROK oppose enforcement of the adjudicator's decision on a number of grounds. 2.PTB was engaged by ROK to carry out work to kitchens and bathrooms in council-owned properties in Harlow, Essex as part of the Harlow Decent Homes project. There is a dispute as to the contractual relationship between PTB and ROK and, in particular, whether there was a contract in writing within the provisions of s.107 of the Housing (Grants) Construction Regeneration Act 1996 (“The 1996 Act”).