HT-2021-000466 - [2024] EWHC 2110 (TCC)
Technology and Construction Court

HT-2021-000466 - [2024] EWHC 2110 (TCC)

Fecha: 09-Ago-2024

Interim payment as to costs

Interim payment as to costs

50.

IRDL applies for an order for an interim payment in respect of its costs.

51.

Such an order is usual practice: Arcadis submitted that if I had found in its favour and made a costs order as requested by it, an interim payment would be appropriate.

52.

IRDL’s approved costs budget was in the sum of £1,164,708.50. Of that, £399,753.50 was in respect of incurred costs.

53.

I accept Ms Slow’s submission that the appropriate approach is to award 90% of budgeted costs as approved and 75% of the incurred costs.

54.

Thus, as to budgeted costs, the interim payment will be 90% of 60% of £764,955, i.e. £413,075.70. As to incurred costs the interim payment will be 75% of 60% of £399,753.50, i.e. £179,889.07. Accordingly the total interim payment will be £592,964.77.