Interim payment as to costs
Interim payment as to costs
IRDL applies for an order for an interim payment in respect of its costs.
Such an order is usual practice: Arcadis submitted that if I had found in its favour and made a costs order as requested by it, an interim payment would be appropriate.
IRDL’s approved costs budget was in the sum of £1,164,708.50. Of that, £399,753.50 was in respect of incurred costs.
I accept Ms Slow’s submission that the appropriate approach is to award 90% of budgeted costs as approved and 75% of the incurred costs.
Thus, as to budgeted costs, the interim payment will be 90% of 60% of £764,955, i.e. £413,075.70. As to incurred costs the interim payment will be 75% of 60% of £399,753.50, i.e. £179,889.07. Accordingly the total interim payment will be £592,964.77.
- Heading
- This judgment was handed down by the court remotely by circulation to the parties’ representatives by email and released to The National Archives. The date and time for hand-down is deemed to be 9 Aug
- Interest and Financing Costs
- Interest Claim 1: Work completed prior to Arcadis defect discovery
- Interest Claim 2: Interest applicable to the recovered costs awarded (up to 23 July 2021)
- Interest Claim 3: Interest applicable to the increased cost of remedial works after completion
- Interest Claim 5: Additional Lending Fees
- Costs
- CPR Part 44
- The Costs of the Action
- The costs of Arcadis’s disclosure application
- Interim payment as to costs
- Conclusions
![HT-2021-000466 - [2024] EWHC 2110 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)