Case No. HT-2025-000039 , HT-2-25-000040 - [2025] EWHC 2005 (TCC)
Technology and Construction Court

Case No. HT-2025-000039 , HT-2-25-000040 - [2025] EWHC 2005 (TCC)

Fecha: 04-Ene-2025

Conclusions

Conclusion and Disposal

78.

The result, therefore, is that the application for summary judgment is dismissed. The Defendants succeed on their Part 8 claim. I make no order in relation to the adjudicator’s fees.

79.

I have provisionally concluded that declarations in accordance with paragraphs 18.1 to 18.5 in the Part 8 claim would be appropriate, but I will hear counsel as to the appropriate orders.

End of Judgment.

Transcript of a recording by Acolad UK Ltd

291-299 Borough High Street, London SE1 1JG

Tel: 020 7269 0370

Acolad UK Ltd hereby certify that the above is an accurate and complete record of the proceedings or part thereof.

This transcript has been approved by the judge.