HT-2024-000423 - [2025] EWHC 942 (TCC)
Technology and Construction Court

HT-2024-000423 - [2025] EWHC 942 (TCC)

Fecha: 16-Abr-2025

Conclusions

Were the Invoices intended to be payment notices pursuant to the Scheme or the Act?

140.

In his oral submissions, Mr Hanna set out the Claimant’s case that the invoices were not intended to be payment notices under the Act and the Scheme.

141.

He drew together that argument in paragraphs 35 to 37 of the Claimant’s Post-Hearing Submissions:

Whether the Invoices were intended as notices under the Scheme / Act

40.

The law is that the document must make “plain” that it is a payment application (payee’s default notice) and that the question is whether, viewed objectively, it had the requisite intention to fulfil that function [Claimant’s Skeleton at [68]].

41.1

At the hearing, the Defendant argued that the way in which the Scheme and Act operated (under the Claimant’s case) was so complex and convoluted that not only would a small contractor be unable to understand it, but that the Court could not expect them to do so. In the Claimant’s submission, that is telling:

41.2

The Scheme is, in Coulson LJ’s words “badly drafted”. When it is necessary to apply the Act and Scheme in full because parties have not agreed payment terms, the exercise would require even an experienced construction lawyer to reach for a cold towel. However, two points may be made. First, for all its infelicities, it is the law. Secondly and as the authorities emphasise, if a payee wishes to take the benefits of the draconian system that the legislation imposes in relation to payments, then the payee must comply with the requirements of the legislation in full. (Footnote: 6) There is nothing in the case law to the effect that the Court should strive to find that notices are compliant when that is not plainly so.

42.

There is nothing in the evidence in this case to indicate that the Defendant was aware of the existence or provisions of the Act / Scheme, let alone that his intention was operate those provisions when producing and submitting the Invoices. There was no Act-compliant set of agreed payment terms (indeed, no payment terms were agreed at all) and no mention of the Act / Scheme was ever made. The evidence indicates that the Defendant was aware that he was issuing invoices too quickly, but was indifferent to this: when challenged that the second Invoice was too soon, he replied., “Well I know I have to wait 30 days now or what ever it is and I’ve finished all inside sections… So will you please pay me something mate”. (Footnote: 7)

The Defendant argues that the Claimant understood the Invoices to be applications for payment. The evidence does not support that. The Claimant of course recognised the invoices as requests for payment (in general terms), but the contemporaneous evidence shows that the Claimant considered that the Invoices were not compliant. The Claimant noted internally that the Invoices were being issued too quickly and it then wrote to the Defendant to put him straight on the payment mechanism and dates: see the Claimant’s Skeleton at [34]-[35].

142.

The Defendant’s response to this argument is in the Defendant’s Post-Hearing Submissions at paragraphs 35 to 37:

35.

The Claimant’s final argument is that the invoices were not, generally, intended as payment notices pursuant to the Scheme or the Act. This argument is incorrect:

35.1

The Defendant does not rely on the invoices as payee’s payment notices under section 110A(1)(b) of the Act. There is no provision for such notices in the Contract.

35.2

The Defendant relies on the invoices as applications or claims for payment which satisfy section 110B(4) in circumstances where the Claimant, the payer, failed to issue a payment notice. They are payee’s notices in default.

35.3

The question is whether objectively a reasonable recipient, in the context of the Claimant, would have understood that the invoices were applications for payment.

35.4

It is clear that a reasonable recipient would have so understood (a relatively low threshold):

35.4.1

The invoices requested payment.

35.4.2

The Defendant had previously used invoices on earlier contracts/projects as its applications for payment.

35.4.3

In the WhatsApp discussions on 17 May 2023 when discussing applications, the Defendant specifically referred to payment following “invoice”.

35.4.4

The Claimant in fact understood that the first two invoices were applications and described them as such in its internal email at [MB/995].

36.

Overall, this was a simple contract between two small entities for demolition works expected to take around 12 weeks. The Claimant’s arguments as to the requirements of the Contract, the application of the Scheme and the requirements for the Invoices are divorced from the factual context and, with respect, the reality as to how these sorts of contracts can and do operate.

37.

The Claimant never complained at the time that the invoices were unclear or needed more information. The Court has made clear that the sort of contrived, technical complaints relied on by the Claimant should not be accepted. If the Court did now mandate such a strict approach, the reality is that very few contractors like the Defendant would ever be able comply and, contrary to the intent of Parliament, the right to interim payments which the Act and Scheme specifically seek to provide for where not agreed, would be lost because compliance with those implied terms would be so complicated and technical that a party seeking payment is unlikely to have ever complied with it. The whole purpose of the Scheme is that it fills a gap where payment terms are not agreed, often therefore it is not understood at the time to apply. Any analysis of compliance must be carried out in that context.

143.

I accept the Defendant’s submissions set out above.

Only three invoices were valid

144.

I return to my conclusion set out above that the Defendant was only entitled to render one invoice per month.

145.

In Mr Frampton’s skeleton argument for the hearing on 19 March 2025, he submitted as follows at paragraphs 81 and 82:

81.

Alternatively, even if the Claimant is correct that the Defendant was limited to one application each month, 3 of the 4 invoices were still valid:

81.1

Absent a statement as to when the monthly period was to run, it should be interpreted as running from the date of the agreement, i.e. 17 May 2023.

81.2

It follows that the Claimant was entitled to make:

81.2.1

One application by 17 June 2023.

81.2.2

One application between 18 June and 17 July 2023.

Monthly Period

Invoice (ref & amount ex. VAT)

Date

Up to 17 June 2023

1078: £48,000 [CB/39]

9 June 2023

18 June to 17 July 2023

1079: £100,000 [CB/40]

1081: £38,750 [CB/41]

23 June 2023

14 July 2023

18 July to 17 August 2023

1083: £9,107.50 [CB/42]

27 July 2023

81.2.3

One application between 18 July and 17 August 2023.

81.3

Three of the four invoices fit into these periods:

82.

It follows that even if the Claimant is successful on its “monthly applications” argument, declaration (3) in the Claim Form [MB/4] should be limited to a declaration that Invoice 1081 did not constitute a valid application for payment. Invoices 1078, 1079 and 1083 were issued one application a month and were valid.

146.

I accept the above analysis, with the consequence that the third declaration should be modified as suggested by the Defendant.

Consequential matters

147.

I hope that the Parties will be able to reach agreement as to the consequences of my judgment above.