PT-2025-000379 - [2025] EWHC 2628 (Ch)
Chancery Division of the High Court

PT-2025-000379 - [2025] EWHC 2628 (Ch)

Fecha: 14-Oct-2025

II Background

II Background

2.

The following paragraphs contain a summary of the background to this application to put the issues into context. It goes without saying that nothing in these paragraphs is intended to be a conclusive finding of fact where such matters are in dispute between the parties and will need to be determined at trial.

The occupation of the Hangar

3.

DH has a leasehold interest in the Hangar.

4.

Jet Support and Charter are companies in common (albeit not identical) ownership and operate their business from the east half of the Hangar which is a very substantial diamond-shaped aircraft hangar and associated offices, stores, and engineering spaces. I was shown an invoice dated 1 January 2025 under which DH invoiced Jet Support in advance for (i) £150,462.50 being one quarter of “Annual Rent” (the total annual rent being £601,850) and (ii) £30,050.72 being one quarter of “Annual Service Charge” (the total annual amount of which was £120,202.88). I was also shown an invoice dated 1 February 2025 under which DH invoiced Jet Support for £30,000 for “Gas and Electricity”, that sum being the monthly apportionment of the “Annual Utilities Charge” of £360,000.

5.

Unfortunately, and notwithstanding the very substantial sums invoiced by DH and paid by Jet Support, there is a substantial dispute between the parties as to the basis on which the Claimants (or either of them) occupy the Hangar because there is no single documented agreement which deals with this. Instead there is:

5.1.

A written Hangar Services Contract dated 27 November 2019 between Jet Support and DH (“the HSC”). The HSC was expressed to be for a term of three years from 9 December 2019 and among the “Services” to be provided by DH was “Adequate Heating and Lighting in the Hangar and defined offices/Ground Floor

5.2.

A written Hangar Parking/Handling Agreement dated 1 September 2020 between LJC and Charter (and an entity referred to as “AirX Malta”) (“the HPHA”). This agreement was referred to in clause 4 as a “Lease Agreement” and had a “renewable” term of 18 months from 7 August 2020. It provided that “general maintenance and repair of the Hangar, not caused by the negligence or wilful misconduct of The Client, its agents, employees, or guests, will be the responsibility of London Jet Centre”.

5.3.

A draft Lease between Jet Support and DH which the Claimants say is in agreed terms (and which Jet Support has executed) but which remains unexecuted by DH as the other party. It is common ground that this document does not satisfy the requirements of s.2 of the Law of Property (Miscellaneous Provisions) Act 1989. The draft Lease provides for a term from 1 June 2021 to 31 May 2028 and obliges Jet Support (as tenant) to pay, amongst other things: (i) Main Rent (at an amount of £601,850 per annum), (ii) Outgoings which includes Supply Costs, with gas being amongst the Supplies, and (iii) the Service Charge.

6.

Based on these documents, the Claimants advance a series of alternative cases as to the nature of their occupation of the Hangar ranging from their primary case – that they hold an equitable lease in the same terms as the draft Lease referred to in paragraph 5.3 above – down to a tenancy on the terms of the HPHA and/or the HSC. The Claimants then say that, whatever the basis of their occupation, they are owed obligations by the Defendants to keep the roof of the Hangar in good repair and to provide heating to the Hangar.

7.

For their part, the Defendants say that neither LJC nor Charter has any interest in the Hangar, and that Jet Support occupies the east half of the Hangar as a licensee of DH from month to month or as a tenant at will. They also deny that they owe the repairing and heating obligations relied on by the Claimants but accept that it would be an implied term of the licence or tenancy at will on which they rely that the east half of the Hangar will be reasonably fit for purpose and that such a term “in principle extends to the repair of the roof and the provision of adequate heating” (Defence, ¶36.2-36.3). In his oral submissions, Mr Grundy KC for the Defendants, submitted that this implied term could not extend as far as ensuring that the roof did not leak.

The state of the roof

8.

The roof of the Hangar and of the associated buildings is substantial in size. I have seen one estimate that the Hangar roof is some 10,000 square metres with a further 2,000 square metres for the roof covering the office/plant block and 4,000 square metres for the lower rooves covering the engineering/stores areas and a covered roadway.

9.

As with the nature of the occupation of the Hangar, there is a substantial dispute between the parties about the state of the roof and the steps which have been taken to repair it over the years. Moreover, identifying the current state of the roof has been complicated by the various further rounds of evidence which have been filed since the Application was issued. The evidence is summarised below.

10.

The Claimants’ principal evidence when the Application was issued came from Mr Greenwood in an expert report dated 25 February 2025. I return below to the question of whether Mr Greenwood is suitable to act as an expert (as the Defendants say that his report should not be admitted) but his report contained a substantial amount of material which is factual in nature. His report included the following:

10.1.

Mr Greenwood’s firm, Seeco (Single Ply) Ltd (“Seeco”), had been involved with the Hangar roof since 2012.

10.2.

Between 2012 and 2019, while the Hangar was in different ownership, Seeco had carried out maintenance on the roof from time to time including replacing various damaged areas of the roof.

10.3.

Mr Greenwood and Seeco became involved with the roof of the Hangar again in November 2021 at the request of LJC because large areas had blown off. Seeco undertook further repairs to the roof in 2022 and 2023.

10.4.

A storm in early April 2024 caused substantial damage including a large section being torn up resulting in sections of the roof being open to the elements. Mr Greenwood inspected these on 15 April 2024. The damaged sections had not been repaired when Mr Greenwood next visited the Hangar in May 2024.

10.5.

Mr Greenwood visited the Hangar again in December 2024 and observed both damage to the roof itself (with daylight visible where the roof membrane and insulation had blown off and the fixing holes were open) and water on the Hangar floor. Mr Greenwood was not allowed to access the roof itself.

11.

In addition to a witness statement from Gemma Staples, a partner at the Claimants’ solicitors, the Claimants also relied at that stage on:

11.1.

The first witness statement of Carly Swetman (the general manager of Jet Support) dated 15 April 2025 which included the following:

(a)

There had been issues with the roof since 2018 with leaks affecting both the office space and the area used for aircraft maintenance.

(b)

Maintenance on the roof was carried out on an ad hoc basis and only when absolutely necessary, with repairs being a temporary fix. Although this did result in periods when there were no leaks, there was no long-term solution.

(c)

The leaks which occurred on 31 July 2023 were particularly difficult to deal with, and there were further leaks in April and May 2024.

(d)

Repairs to the roof were then carried out which appear to have held until further stormy and rainy conditions in November 2024 (Storm Conall), December 2024 (Storm Darragh) and January 2025 when there was particular flooding on 5 January.

(e)

Despite repairs in late 2024 or early 2025, there was continued water ingress into the Hangar (such as in late February 2025).

11.2.

The first witness statement of Mr Matthews (the Chairman and founder of Jet Support and Charter) dated 15 April 2025 which provided further detail as to the issues with the roof in December 2024/January 2025 and the impact which it was having on operations in the Hangar. Mr Matthews’s evidence was that the Hangar continued to leak even in mild rainy conditions.

12.

The response from the Defendants came on 3 June 2025 from Ms Covaci (Chief Executive of DH) and Mr Simmonds (the director of Elevation Roofing Limited (“Elevation”)).

12.1.

Ms Covaci’s evidence was that:

(a)

There had been intermittent issues with the roof since 2018.

(b)

Elevation was engaged from April 2024 to carry out repairs on the roof. These repairs were concluded in August 2024 and prevented further leaks in September 2024 despite heavy thunderstorms.

(c)

Storm Darragh in December 2024 then caused severe damage to the roof in response to which Elevation carried out further repairs which concluded in February 2025.

(d)

To her knowledge there were no leaks from the roof as at the date of her statement. DH were also in negotiations with Elevation about a maintenance programme for the long-term maintenance needs of the roof. In the meantime, Elevation was inspecting the roof on a monthly basis.

12.2.

Mr Simmonds’s evidence was that:

(a)

Elevation was appointed as an approved contractor to DH in March 2024.

(b)

The first notable repairs to the roof by Elevation were carried out in July/August 2024.

(c)

The damage to the roof caused by Storm Darragh was significant but extensive repairs using a liquid system were carried out over a period of approximately 3 months.

13.

The Claimants responded to this evidence as follows:

13.1.

Mr Greenwood prepared a witness statement report dated 27 June 2025. This report did not contain any further detail of the condition of the roof as of June 2025 but largely took issue with aspects of Mr Simmonds’s statement.

13.2.

Mr Matthews prepared a second statement dated 18 June 2025. His evidence was that the situation in the Hangar has worsened since his first statement, with further leaks occurring in May and early June 2025. He provided Ms Covaci with videos of what he described as water pouring into the Hangar and photographs of the water pooling in the Hangar.

13.3.

Mr Mathews prepared a fourth witness statement dated 4 September 2025 which referred to new leaks occurring in late August 2025.

14.

The final round of evidence was the second witness statement of Ms Covaci dated 16 September 2025. Ms Covaci’s evidence was that:

14.1.

A contractor had inspected the roof on 6 July 2025 and had repaired weather related damage by 11 July 2025 such that there were no leaks as at the date of her statement.

14.2.

Regular inspections of the Hangar had been taking place, including on 29 August 2025 and 12 September 2025, which revealed no leaks. Ms Covaci exhibited videos of these inspections.

14.3.

There were heavy rains and wind on 13 September 2025 but no leaks were seen at a further inspection that day.

15.

It will be immediately apparent from the description set out above that, while there is common ground about some of the issues with the roof (such as the damage from Storm Darragh), there is not just a very real dispute about the state of the roof from time to time but that the position at any moment depends on whether new leaks have occurred or whether the next set of repairs (or at least works on the roof) have taken place. This back and forth in the evidence reflects the fact that, although the Application was certified as urgent back in April 2025, it was not heard until some five months later, in September 2025. I consider the significance of this passage of time and the developments in the evidence further in section IV below.

The heating

16.

The factual position in relation to the heating of the Hangar is more straightforward than for the roof. It appears that, until October 2024, the Hangar was heated by means of a gas-powered heating system (which the Defendants say was operated only for part of the year) but the gas supply was then cut off due to a dispute between the DH and its gas supplier. DH says that it has since provided alternative heating which is sufficient.

17.

The evidence from the Claimants, principally through the first witness statements of Mr Matthews and Ms Swetman referred to above, disputes the adequacy of the heaters provided by DH and included details of:

17.1.

the temperatures recorded in the Hangar in manual and electronic temperature logs for January and February 2025 which showed, by way of example, consistently low single figure temperatures at 8am between 12 January 2025 and 6 February 2025;

17.2.

the disruption which those low temperatures had caused to the workforce and therefore the operations of Jet Support. In particular, it has been forced to shut down its operations completely for several days in early January 2025 which has caused particular losses identified in the Particulars of Claim. It has also had to put in place additional measures to allow work to continue in cold conditions, including additional breaks and the provision of extra clothing for its personnel;

17.3.

the need, in particular, for higher temperatures to allow the sealant used in the aircraft maintenance to cure properly; and

17.4.

the proposals made by the Claimants to instal a new boiler and heating system which were rejected by the Defendants.

18.

Although the warm summer had alleviated the temperature issues in the Hangar, the evidence also explained that the Claimants were concerned that, as autumn/winter approaches, the same issues with the lack of adequate heating would begin to occur again.

19.

The most recent evidence from the Defendants, in the second witness statement of Ms Covaci referred to above, was that some progress has been made in negotiations between DH and the supplier such that the gas supply (and therefore the gas-powered heating) may be restored in the relatively near future although this will depend not just on DH but also the supplier.

Jet Support’s EASA accreditation

20.

Aside from the factual position in relation to the state of the roof and the heating, the other factual matter which occupied a material part of the hearing related to Jet Support’s accreditation or certification by the European Air Safety Agency (“EASA”).

21.

The Claimants’ case is that:

21.1.

Jet Support is obliged by Part 145.A.25 of UK Regulation 1321/2014 (extracts of which were contained in the bundle for the hearing) to ensure that it provides facilities which are appropriate for all planned work ensuring, in particular, protection from the weather. The need to provide facilities appropriate to the tasks being carried out includes ensuring that the working environment is such that the effectiveness of personnel is not impaired. Specific reference is made to maintaining temperatures such that personnel can carry out required tasks without undue discomfort. Part 145.A.25(a) provides that protection from the weather relates to the normal prevailing local weather that is expected throughout any twelve month period, and that aircraft hangar and component workshop structures should prevent the ingress of rain.

21.2.

Jet Support has been unable to satisfy these requirements since the gas central heating stopped in October 2024.

21.3.

Jet Support was the subject of an onsite audit by EASA on 23 June 2025, the findings of which included that Jet Support could not demonstrate compliance with Part 145.A.20(a) “with regard to Scope of work”. The narrative setting out the evidence for this finding (which was at “level 2”) was as follows:

37740 - The paint activity is not defined in the MOE as a specialised

activity

A “paint tent” is used to carry out the touch up paint on removed parts.

- The mixing of paint is done outside of the tent, directly in the hangar

environment without temperature control. The temperature in the

hangar is found outside of the range in april 2025 (10.34 to 18.51°C)

- the tent is under temperature and humidity control but

1/ The temperature is found during winter months to be outside of the

required value (from 11.15 to 16.96°C in October 2024 and 5.56 to

12.61°C in December 2024).

2/ The humidity is found during winter months to be outside of the

required value (from 62 to 89 % in October 2024 and from 62 to 87%

during December 2024).

21.4.

The consequences of losing its accreditation would be potentially catastrophic for Jet Support as it would have to cease its operations. Further, the audit report requires Jet Support to provide a response by 23 September 2025.

22.

The Defendants were critical of the nature and impact of the evidence relied upon by Jet Support on this point. They said that: (i) only a very short extract of the audit report had been provided; (ii) the extract which was available related only to one specific activity – painting - which was, Ms Covaci said, not permitted in the Hangar in any event; (iii) the report made no mention of leaking from the roof and, in any event, Jet Support had been accredited throughout the period since 2019 when complaints had been made about the roof; (iv) the only reference in the report to humidity related to the paint tent which was a local environment created by the Claimants; and (v) the report suggested the existence of additional temperature data which had not been provided by the Claimants.