Mistake
Mistake
If the parties did have the common intention that I have held that they did have, then if as a matter of true interpretation thereof the effect of clause 13 of the Deed of Postponement was, contrary to my primary finding, to confer priority upon JAK in the event that the JAK Loan Agreement was terminated first, then I consider that it must follow that clause 13 of the Deed of Postponement so provided by mistake. Thus, I consider that this particular requirement is satisfied.
- Heading
- Rectification 60
- Overall conclusion 135
- Background
- Meaning of Clause 13 of the Deed of Postponement
- Correct approach to contractual interpretation
- The proper meaning of clause 13 of the Deed of Postponement
- Rectification
- The legal principles to be applied
- The witnesses
- The pre-Deed of Postponement correspondence
- Is Together’s case for rectification made out?
- Common continuing intention
- Outward expression of accord
- Continuing intention
- Mistake
- Terms of proposed rectified clause 13
- Conclusion regarding rectification
- Conclusions
![BL-2023-MAN-000072 - [2025] EWHC 2442 (Ch)](https://backend.juristeca.com/files/emisores/logo_O3rEzCI.png)