HT-2023-000379 - [2024] EWHC 1201 (TCC)
Technology and Construction Court

HT-2023-000379 - [2024] EWHC 1201 (TCC)

Fecha: 20-May-2024

OUTLINE OF THE PARTIES’ POSITIONS

D.

OUTLINE OF THE PARTIES’ POSITIONS

The Defendants’ case on the Application

19.

The Defendants rely on Regulation 92(2) of the PCR which reads as follows:

92.— General time limits for starting proceedings

(1)

This regulation limits the time within which proceedings may be started where the proceedings do not seek a declaration of ineffectiveness.

(2)

Subject to paragraphs (3) to (5), such proceedings must be started within 30 days beginning with the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen.

(i)

July case

20.

They submit, first, that the Claimant had actual or constructive knowledge within the meaning of Regulation 92(2) to bring the procurement claim by 20 July 2023, and therefore that the 30 day period which is triggered by such knowledge had expired long before the Claim Form was issued on 18 October 2023. They rely in that regard on a letter from the Claimant’s solicitors dated 26 July 2023. I will refer to this as the “July case”.

(ii)

18 September letter

21.

Alternatively, the Defendants submit that the Claimant had actual or constructive knowledge on 18 September 2023 as a result of the information in a letter emailed to its solicitor, Mr Lobo, by the First Defendant’s solicitors on 18 September 2023 (“the 18 September letter”). Therefore, time expired on 17 October 2023, and the Claim Form was issued one day late.

(iii)

Day 1 point

22.

Critical to that alternative argument is the question whether the 30 days include the 18 September, as the Defendants submit, or whether, as the Claimant contends, time runs from the day after the letter, namely 19 September. If the Claimant is right on that point, then the Claim Form was in time, even if (which the Claimant does not accept) it had sufficient knowledge on 18 September 2023. I will call this the “Day 1 point”, i.e. what day counts as the first of the 30 days.

The Claimant’s response to the Application

(i)

Regulation 92(3)(c)

23.

The Claimant’s primary position, or at least what became its primary position by the time of the hearing, is that the 30 day period never applied or started running at all (and still has not started running), but in any event has not expired, as a result of Regulation 92(3)(c), to which Regulation 92(2) is expressly subject. I set out the terms of Regulation 92(3)(c) at paragraph 47 below.

(ii)

Regulation 92(2) – the July case

24.

If that is wrong, and Regulation 92(2) and the 30 day period does apply, it objects to the Defendants seeking to run the July case on this application, on grounds that no or insufficient notice was given of it. But in any event, it would deny that it had the necessary knowledge then.

(iii)

Regulation 92(2) – 18 September letter

25.

As regards September 2023, the Claimant submits that there is a real prospect of it showing that it did not have either actual knowledge or constructive knowledge, within the meaning of Regulation 92(2), on 18 September 2023 itself, as opposed to a day or so later. That is largely a factual contention, at least as regards actual knowledge. If that is right, then whether the 30 days would have included or excluded the 18 September itself - the Day 1 point - is moot.

(iv)

Day 1 point

26.

If the Claimant did have sufficient knowledge on 18 September, then on the Day 1 point, it submits that on its true construction, time did not start running under Regulation 92(2) until at the earliest 19 September, such that the Claim Form issued on 18 October was in time. This is on the basis that the 30 days excludes the day on which sufficient knowledge was acquired.