PROCUREMENT LAW
PROCUREMENT LAW
I should start by setting out the law so far as relevant to the Application.
The Remedies Directive
Overview and implementation
Directive 89/665/EEC, as amended in 2007 by Directive 2007/66/EC, (“the Remedies Directive”) concerns various minimum requirements as regards legal review procedures and remedies for breaches of procurement law in respect of public works contracts. It applies to public supply and public works contracts falling within the directive containing the substantive regulations concerning public procurement, which was Directive 2004/18/EC but is now to be read as a reference to Directive 2014/24/EU. Such contracts include framework agreements.
The Remedies Directive, in its amended form of 2007, was implemented in the UK by the Public Contracts (Amendment) Regulations 2009. The PCR of 2015 implemented the new procurement directive to which I have referred (2014/24/EU), and following the revocation of the 2009 Amendment Regulations, re-enacted the relevant provisions concerning remedies as they then stood.
Regulation 92(2) and 92(3) of the PCR therefore contain the regulations on limitation which seek to implement the Remedies Directive, in the context of which they must be construed. For the primacy of the Remedies Directive when interpreting the Regulations, see International Game Technology PLC v The Gambling Commission [2023] EWHC 1961 TCC [2024] PTSR 65 (Coulson LJ) (a decision under the Concession Contracts Regulations 2016).
Rapidity
Article 1 of the Remedies Directive required Member States to ensure that decisions taken by contracting authorities could be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in Articles 2 to 2f.
The principle of rapidity is a key part of procurement law, which underpins the regulations on limitation. It is a useful principle to have in mind when considering whether a party’s contentions on limitation are, or are not, consistent with it.
Article 2(1)(b)
Article 2(1) required Member States to ensure that review procedures were put in place and included a power to award damages; and to “either set aside or ensure the setting aside of decisions taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the invitation to tender, the contract documents or in any other document relating to the contract award procedure” (Article 2(1)(b)). The Claimant does not seek by its procurement claim to set aside the award of the Assist Contract, but this provision is relevant to its case on the true construction of Regulation 92(3)(c), as will be seen below.
Standstills
An important aspect of the amendments made to the Remedies Directive in 2007 was to require a standstill period between the time a decision was made to award a contract and that contract being concluded. The purpose of this was explained in the recitals to the Remedies Directive, see e.g. (4) and (6).
The new Article 2a(2) provided that:
“A contract may not be concluded following the decision to award a contract falling within the scope of Directive 2004/18/EC before the expiry of a period of at least 10 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned if fax or electronic means are used or, if other means of communication are used, before the expiry of a period of either at least 15 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned or at least 10 calendar days with effect from the day following the date of the receipt of the contract award decision.”
The communication must be accompanied by a summary of the relevant reasons for the decision.
It can therefore be seen that the standstill period depends on whether the contract award decision was sent to the tenderers and candidates by fax/electronically or not. If it was, then the period is at least 10 days after the date of sending; if not electronic, then the period is at least 15 days after sending or 10 days after receipt. (It is plain in this context that the date of sending, or receipt if applicable, is not included in the calculation of the specified days.)
The Claimant’s procurement claim does not raise any issue of standstill. However, this provision has a resonance in Article 2c, which provides for time limits.
Time limits under the Remedies Directive
Article 2c of the Remedies Directive provides as follows (emphasis added):
“Time limits for applying for review
Where a Member State provides that any application for review of a contracting authority's decision taken in the context of, or in relation to, a contract award procedure falling within the scope of Directive [2014/24/EU] must be made before the expiry of a specified period, this period shall be [A:] at least 10 calendar days with effect from the day following the date on which the contracting authority's decision is sent to the tenderer or candidate if fax or electronic means are used or, if other means of communication are used, this period shall be [B:] either at least 15 calendar days with effect from the day following the date on which the
contracting authority's decision is sent to the tenderer or candidate or at least 10 calendar days with effect from the day following the date of the receipt of the contracting authority's decision. The communication of the contracting authority's decision to each tenderer or candidate shall be
accompanied by a summary of the relevant reasons. [C:] In the case of an application for review concerning decisions referred to in Article 2(1)(b) of this Directive that are not subject to a specific notification, the time period shall be at least 10 calendar days from the date of the publication of the decision concerned.”
I have added [A], [B] and [C] to the above text for ease of reference.
Article 2c does not prescribe the limitation period for procurement claims as such, which is a matter for the national court. It does however require minimum periods in certain situations. This is apparent from Article 2f(2):
“… the time limits for the application for a review shall be determined by national law, subject to the provisions of Article 2c.”
Where there has been a competitive exercise involving tenderers and candidates, Article 2c provides that the limitation period must be at least 10 or 15 days, depending on the circumstances: see [A] and [B] above in the text above. The time limits mirror the standstill provisions in Article 2a(2). However, both the Claimant and the Defendants now agree that these time limits do not apply, because the award of the Assist Contract did not involve a competitive process in respect of which tenderers/candidates and the Claimant were involved.
The Claimant instead relies on the final sentence of Article 2c [C]. It says that its application for review, i.e. its claim for damages, concerns a decision “referred to in Article 2(1)(b)”. It interprets that reference as being to any unlawful decision, irrespective of whether a claimant is seeking to set it aside. I shall come back to that when looking at the PCR and examining how that aspect of Article 2c was implemented.
Time limits under the PCR
Overview
Regulation 92 sets out the general time limit for starting proceedings, where (as here) those proceedings do not seek a declaration of ineffectiveness. The basic rule is found in Regulation 92(2): proceedings must be started within 30 days beginning with the date when the claimant first knew or ought to have known that grounds for starting the proceedings had arisen. I have set out the text in paragraph 19 above.
The basic rule in Regulation 92(2) is expressly subject to Regulation 92(3) to (5).
Sub-paragraphs (4) and (5) provide that the Court may extend time where there is a good reason for doing so, but not beyond 3 months after the date of knowledge under Regulation 92(2). The Claimant, at times, suggested that sub-paragraphs (4) and (5) were provisions which prescribed the limitation period. In my judgment, that is not so. The limitation period is as set out in Regulation 92(2), to be read subject to sub-paragraph (3).
Regulation 92(3)
Regulation 92(3) provides:
“Paragraph (2) does not require proceedings to be started before the end of any of the following periods:—
where the proceedings relate to a decision which is sent to the economic operator by facsimile or electronic means, 10 days beginning with—
the day after the date on which the decision is sent, if the decision is accompanied by a summary of the reasons for the decision;
if the decision is not so accompanied, the day after the date on which the economic operator is informed of a summary of those reasons;
where the proceedings relate to a decision which is sent to the economic operator by other means, whichever of the following periods ends first:—
15 days beginning with the day after the date on which the decision is sent, if the decision is accompanied by a summary of the reasons for the decision;
10 days beginning with—
(aa) the day after the date on which the decision is received, if the decision is accompanied by a summary of the reasons for the decision; or
(bb) if the decision is not so accompanied, the day after the date on which the economic operator is informed of a summary of those reasons;
where sub-paragraphs (a) and (b) do not apply but the decision is published, 10 days beginning with the day on which the decision is published.”
This scheme reflects the Remedies Directive. As Article 2f(2) of the Remedies Directive makes plain, the limitation period is a matter for the national court (this is Regulation 92(2)), subject to the minimum time periods identified in Article 2c. Regulation 92(3) is designed to implement the requirement for those minimum periods.
- Heading
- INTRODUCTION
- BACKGROUND
- THE PROCUREMENT CLAIM
- OUTLINE OF THE PARTIES’ POSITIONS
- PROCUREMENT LAW
- THE DISPUTE CONCERNING REGULATION 92(3)
- DISCUSSION AND DECISION ON REGULATION 92(3)(c)
- REGULATION 92(2) - Introduction
- REGULATION 92(2) - THE JULY CASE
- REGULATION 92(2) - THE 18 SEPTEMBER LETTER
- K. DAY 1 POINT
- EXTENSION OF TIME
- Conclusions
![HT-2023-000379 - [2024] EWHC 1201 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)