HT-2025-000282 - [2025] EWHC 850 (TCC)
Technology and Construction Court

HT-2025-000282 - [2025] EWHC 850 (TCC)

Fecha: 09-Abr-2025

Conclusions

J. CONCLUSION

115.

If, which I have not, I had found the Defendant liable to the Claimant I would have awarded the Claimant damages in the sum of £2,533,789.81 together with statutory interest at a rate of 3.5% above the base rate. The period during which interest would have been awarded would have required further submissions.

116.

However for the reasons set out in this Judgment the Defendant is not liable to the Claimant as alleged or at all andin all the circumstances the Claimant’s claims are dismissed. I invite the parties to agree the appropriate orders in the light of this judgment.

MARTIN BOWDERY K.C.

(sitting as a Deputy High Court Judge)

1st April 2025