THE AGREED CHRONOLOGY

D.

THE AGREED CHRONOLOGY

Date

Event

Ref.

27 Aug 2015

Claimant’s initial project brief

[E/895-898]

30 Sept 2015

Claimant sent Defendant initial project brief

[E/895-898]

30 Sep 2015

First meeting between Claimant and Defendant

Adams [30]

Waugh 1 [103]

7 Oct 2015

Defendant proposes fee

[E/903-909]

Nov 2015

Defendant begins preparing outline designs

RAPOC [15A]

Ogle 1 [81]

11 Dec 2015

Mark Francis email following meeting attended by Mark Adams, Vincent Wang, Adam Waugh, Alastair Ogle, Martin Francis and others

[E/934]

Jan 2016

Defendant begins preparing more detailed designs

RAPOC [15A]

Ogle 1 [82]

18 Feb 2016

Meeting between Claimant and Defendant agreeing that Kingerlee would not be used to build the building

[E/983]

22 Feb 2016

Meeting between Claimant, Defendant and Vincent Wang at which construction management decision made and Kingerlee to carry out pre-construction services

[E/983]

25 Jan 2016

Defendant produces a project outline

Ogle 1 [92] [E/957]

23 Feb 2016

Interviews of potential timber contractors at Defendant's offices.

AR [2.4]

Adams [42]

Westwood [44]-[45] [E/992]

24 Feb 2016

Hess provided quotation to Kingerlee

[E/1001]

25 Feb 2016

Hess provided further information to Kingerlee

[E/1008]

29 Feb 2016

Pre-appointment meeting for JCA, attended by Tom Westwood (Defendant).

AR [2.3]

Westwood [40]

5 Mar 2016

Vincent Wang circulated his analysis of timber package tenders and recommended Hess

[E/1094]

5 Mar 2016

Mark Adams email stating Hess had agreed to be timber sub-contractor; Claimant would not proceed with Kingerlee; Claimant was in discussions with a construction manager.

[E/1096]

16 Mar 2016

Defendant produces a Timber Frame performance specification for the roofing works

RAPOC [31.lA]

Ogle 1 [93] [E/1121]

21 Mar 2016

Hess provided tender letter to Claimant

[E/1132-1138]

21 Mar 2016

Claimant engages Hess as timber frame contractor

RRAD [8]

22 Mar 2016

Kick-off meeting attended by Claimant, Defendant, JCA, Hess, and others. Minutes by Defendant.

Adams [46]

Westwood [56]

Waugh 1 [118] [E/1144]

12 Apr 2016

Disputed conversation between Andrew Waugh

(Defendant) and Mark Adams and Mr Wang (Claimant) regarding possibility of constructing a protective canopy

RRAD [25(5)]

AR [19.3]

Adams [48]

Waugh 1 [120)-(124]

15 Jun 2016

Defendant produces Combined Specification, Rev C for windows, cladding and roofing

Ogle 1 [97] [E/45]

23 Aug 2016

Visit to Hess in Germany attended by Mark Adams, Alastair Ogle and Tom Westwood among others. Email from Hess's Mr Thompson after visit

Ogle 1 [108] [E/1222]

5 Sep 2016

Work began on site

28 Sep 2016

Mark Adams email attaching Claimant’s brief

[E-1282 to 1283]

30 Sep 2016

Claimant and Defendant enter into the Appointment

RAPOC [4] [E-129]

4 Oct 2016

Claimant engages JCA as construction manager

RRAD [7] [E-159]

21 Oct 2016

Email from Adrian Kenny with latest programme

[E-1342]

7 Nov 2016

Alastair Ogle email to Rensteph Thompson asking about methods of protection among other things

[E-1375]

15-16 Nov

2016

Emails regarding weather protection and Christmas shutdown between Defendant, Hess and JCA.

RRAD [19(1A)]-

[19(3)] [E/1389-1394],

[E/1398], [E/1400-

1404]

18 Nov 2016

Mr Jung (Hess) email to Mr Kenny about timing of installation of roof and Mr Kenny's response

[E/1418-1419]

18 Nov 2016

Emails regarding timing of roofing works between Defendant and JCA

RRAD [19(3A)]-

[19(3B)]

AR [13.3] [E/1422]

28 Nov 2016

Hess's works began on site

[E/1381] [E/1463-1464]

5 Dec 2016

Mr Williams (JCA) email regarding handover

[E/1470]

8 Dec 2016

Mr Jung (Hess) email regarding roofing work

[E/1495]

12 Dec 2016

Claimant contract .with Hess

[E/333]

16 Dec 2016

Claimant engages Stoneleigh as roofing contractor

RRAD [9] [E/395]

22 Dec 2016

Email from Mark Adams (Claimant) to Defendant asking Defendant to make enquiries of Hess

RRAD [19(6)] [E/1648]

Defendant inquired of Hess whether the CLT panels would dry out from the inside

RAPOC [31.3(2)]

RRAD [19(7)] [E/1656], [E/1655]

Rensteph Thompson (Hess) email to Alastair Ogle

(Defendant) warning of the risks of moisture in CLT panels

RAPOC [27]

RRAD [19(5)],

[19(8)]

[E/1657]

23 Dec 2016

Emails between Claimant, Defendant, Hess and JCA regarding protection of roof over Christmas period

RRAD [19(9)]-

[19(13)]

[E/1658-1680]

Telephone call between Mr Garwood (Claimant) and Mr Ogle (Defendant). Terms disputed. Mr Ogle's emails following call.

RRAD [19(12)], [20]

AR [13.7], [15.5]

Ogle 1 [160] [E/1668], [E/1670]

Emails between Hess and Defendant regarding timing of VCL membrane installation

RRAD [15(2)] [E/1678], [E/1680]

Timber frame completed

RAPOC [24]

RRAD [18(1)]

Christmas shutdown begins

RRAD [19(4)]

3 Jan 2017

Christmas shutdown ends

RRAD [19(4)]

4 Jan 2017

Mr Westwood emailed Mr Ogle and others at Defendant following call with Mr Garwood

[E/1685]

5Jan2017

Mr Williams (JCA) emailed Mr Westwood that Hess had completed

[E/1686]

12 Jan 2017

Site meeting at which condition of roof was discussed. Terms disputed

RRAD [25(7)]

AR [13.9], [19.4]

Adams [63]

Waugh 1 [151]-[159] [E/1713]

16 Jan 2017

Defendant sent email to Stora Enso, manufacturer of the CLT with queries concerning installation of VCL when CLT is wet

[E/1729]

20 Jan 2017

Defendant received a response email from the manufacturer of the CLT regarding queries raised including whether it could dry out from its internal face

RRAD [23(15)] [E/1734]

23 Jan 2017

Mr Westwood email to Mr Ogle and Mr Williams (JCA) following discussion including "Temporary rainwater strategy"

[E/1736]

8 Mar 2017

Mr Adams email regarding water damage

[E/1796]

Mid-Mar 2017

Roof covering is completed

RAPOC [24]

RRAD [18(1)]

27 Apr 2017

Mr Adams emailed Mr Waugh a draft Note from Probyn Miers

[E/1829-1834]

26-28 May

2017

Move in apparently this weekend

[E/1881]

23 May 2017

TRADA / Exova moisture content survey

[E/1861]

23 June 2017

TRADA / Exova moisture content survey

[E/1889]

1-2 Aug 2017

TRADA / Exova moisture content survey

[E/1926]

28 Nov 2017

TRADA / Exova moisture content survey

[E/1978]

3 Apr 2018

TRADA / Exova moisture content survey

[E/2011]

7 Dec 2018

Claimant notified claim against Stoneleigh

[F/50]

21 Dec 2018

Claimant notified claim against Hess

[F/27]

24 Dec 2018

Claimant notified claim against JCA

[F/35]

4-5 Feb 2018

TRADA / Exova condition survey finds rot and decay

[E/2061]

3 Jul 2019

Claimant notified claim against Defendant

[F/3]

4 Sep 2020

Claimant allegedly takes out CBILS loan

RAPOC [39]

Adams [78]

5 Nov 2021

Remedial works begin

Adams [80]

8 Dec 2022

Remedial works are completed

Adams [83]

10 Jan 2023

Claimant allegedly takes out a further loan

RAPOC [39]

Adams [84]

24.

I did not hear from any witnesses from

- JCA the Construction Manger

- AMK Construction Subcontractor to the Construction Manager

- Hess the timber frame trade contractor

- Stoneleigh the roofing trade contractor

Nor did I hear from Vincent Wang the Claimant’s Development Manager or Simon Garwood the Claimant’s employee and the Claimant’s Project Manager as described in the Agreed Dramatis Personae.

25.

It is not for me to question why these potential witnesses were not called to give evidence. I must decide the case on the pleadings, the written evidence and the oral evidence provided and tested by the parties through their cross examination and re-examination and the parties written and oral submissions. I certainly do not think it is appropriate to draw any inferences from the absence of any evidence from those potential witnesses who were not called to give evidence.