    Conclusion on factual matrix and other points

    Conclusion on factual matrix and other points

    137.

    It follows from what I have said above that these further points do not assist EE to supplant the primacy of Clause 2.3 of the GSA, and indeed they tend to support Avanti’s position instead.

    • Heading
    • INTRODUCTION
    • Nature of the services to be provided by Avanti
    • The contractual framework
    • the facts
    • Section 5
    • The Purchase Orders (“POs”)
    • Changes to the SOW
    • The Parties’ Negotiations
    • The Present Position
    • the law
    • serious issue to be tried
    • Clause 2 of the GSA
    • The SOW
    • The “Mandatory” Point
    • The “Agreement” Point
    • The Term and Duration Point
    • The EE-HO Contracts
    • Effect of an indefinite obligation to supply on Avanti
    • EE’s ability to migrate to a new supplier
    • CCN5
    • The GSA/SOW as an “evergreen” contract
    • Conclusion on factual matrix and other points
    • Conclusions

    Otros enlaces de interés:

    Jurisprudencia clasificada por bienes e inmuebles Jurisprudencia clasificada por contravención de las normas jurídicas Jurisprudencia clasificada por derechos de la unión europea Jurisprudencia clasificada por derechos fundamentales Jurisprudencia clasificada por materias del derecho Jurisprudencia clasificada por profesiones Jurisprudencia clasificada por sector agrario Jurisprudencia clasificada por sectores de la sociedad

    Síguenos en

    Políticas de eliminación | Políticas de privacidad

    © 2026 Juristeca