[2025] EWHC 1160 (TCC)
Technology and Construction Court

[2025] EWHC 1160 (TCC)

Fecha: 15-May-2025

the facts

the facts

The Statement of Work

25.

At around the same time as the making of the GSA, the parties agreed a Statement of Work (“the SOW”).

26.

It is a very substantial document because it sets out in great detail the precise services to be supplied by Avanti. For present purposes, the material parts are set out below.

27.

The first and second pages read as follows:

28.

Schedule 3 to the SOW deals with the charges for the services provided. It is common ground that there were one-off charges to be paid in connection with the set-up of the infrastructure. These are set out at paragraph 3.1.

29.

There were then the ongoing charges for the provision of the services and Clause 3.2.1 sets out the charges for “Fixed Capacity” which deals with the basic capacity level provided. These were as follows: