Case No. CL-2019-000290
Commercial Court

Case No. CL-2019-000290

Fecha: 14-Feb-2020

The proper approach on a s.9 application

14.S.9 of the Arbitration Act 1996 provides for a mandatory stay of legal proceedings in the English court in respect of a matter which the parties have agreed to refer to arbitration: "Stay of legal proceedings. (1) A party to an arbitration agreement against whom legal proceedings are brought (whether by way of claim or counterclaim) in respect of a matter which under the agreement is to be referred to arbitration may (upon notice to the other parties to the proceedings) apply to the court in which the proceedings have been brought to stay the proceedings so far as they concern that matter. … (4) On an application under this section the court shall grant a stay unless satisfied that the arbitration agreement is null and void, inoperative, or incapable of being performed." 15.Before ordering a s.9 stay, the Court must be satisfied both that there is an arbitration clause, and that the subject matter of the claim falls within that clause (