HT-2022-000311 & HT-2022-000254 - [2024] EWHC 3179 (TCC)
Fecha: 11-Dic-2024
The claimants’ case in summary
The claimants’ case in summary
RTM was incorporated for the purpose of acquiring the freehold pursuant to the Leasehold Reform Housing and Urban Development Act 1993.
RTM and the defendants entered into an Agreement for Sale, also referred to as the Freehold Purchase Agreement (“the FPA”), made on 26 February 2020 pursuant to which it was agreed that Click St Andrews would, within a period of not more than 2 years, develop the Property by removing the existing pitched roof and erecting an additional storey of three prefabricated modular units which would be lifted into place. In summary, the intention was that RTM would then purchase the freehold for £100,000 in its capacity as nominee for the participating leaseholders and simultaneously grant leases to Click St Andrews for the three new flats which would then be sold. Click Group Holdings guaranteed the obligations of Click St Andrews under the Agreement.
The claimants’ case is that the crane lift to install the modular units was scheduled to take place on 24 to 25 July 2021. Adverse weather warnings were issued by the Met Office between 19 and 25 July 2021. On 24 and 25 July there was repeated rainfall and thunderstorms across London and the South East of England. The pitched roof had been removed and the roof structure not kept watertight, which allowed water ingress throughout the building causing damage of varying severity in the flats. The defendants made some efforts to remedy the damage but the claimants’ case is that those efforts were inadequate, poorly managed and ultimately incomplete.
The claimants engaged experts to undertake their own investigations and that led to the identification of other alleged defects in workmanship in the modular units, including structural and fire safety issues. Recommendations were made for further investigations. At trial, the claimants adduced the evidence of:
John Rivett, a building surveyor
Philip Ebbatson, a civil and structural engineer
Alastair Ferguson, an architect
Jonathan Chick, a civil engineer (on remedial works)
David Daly, a quantity surveyor (quantum).
A Dangerous Structure Notice was issued by Southwark Council on 9 February 2024 shortly before trial on which the claimants rely.
In the Particulars of Claim, the claimants’ claims were advanced on the following bases:
RTM claimed damages for breach of the FPA. There were 29 particulars of breach which encompassed, in a somewhat random order, breaches which had led to the water ingress; defects in fire protection and compartmentation; structural defects; and other miscellaneous items, including most substantially a claim that the Property needs to be re-roofed.
RTM advanced the same claims against Click Group Holdings under the terms of the guarantee within the FPA.
The leaseholder claimants principally claimed damages for breach of the covenant of quiet enjoyment in their leases. These claims were made against Click St Andrews only.
They also framed their claims on the basis of breach of statutory duty, negligence, and nuisance.
- Heading
- The parties
- The claimants’ case in summary
- Procedural matters and representation
- Amended Particulars of Claim
- The Agreement for Sale
- The purported rescission of the FPA and RTM’s claim
- The no loss defence
- The position of the leaseholders and the leaseholders’ claims
- The leases
- Insurance
- Breach of statutory duty
- Negligence
- Nuisance
- The rainwater ingress
- Breaches
- Click St Andrews’ position
- Discussion
- Other defects and expert evidence
- The Rivett reports
- Mr Ferguson
- Miscellaneous defects
- Mr Ebbatson
- Remedial works
- Quantum
- Flat 1
- Flat 5
- Flat 6
- Flat 7
- Flat 8
- Flat 9
- Flat 10
- Flat 11
- Flat 12
- Flat 13
- Mitigation
- Conclusions