Conclusions
The appropriate order at this stage
I accept J&BH’s submission to the extent that at this stage it is too early to determine what sum should be paid by either Party and when, which will depend very much on what is contained in the Court’s orders as to costs.
It is time for this drawn out litigation to be brought to a close, at least in this Court (there has been an indication that I may have to consider an application for leave to appeal).
I direct that each Party submits its submissions as to the costs by 27 September 2024 with each Party having a right to reply by 4 October 2024.
- Heading
- This judgment was handed down by the court remotely by circulation to the parties’ representatives by email and released to The National Archives. The date and time for hand-down is deemed to be 3 Oct
- The effect of the Fifth and Sixth Judgments
- The calculation of the sum due for the measured works
- VAT
- CONSTRUCTION INDUSTRY SCHEME
- Interest