HT-2023-000006 - [2024] EWHC 2516 (TCC)
Technology and Construction Court

HT-2023-000006 - [2024] EWHC 2516 (TCC)

Fecha: 03-Oct-2024

Conclusions

The appropriate order at this stage

46.

I accept J&BH’s submission to the extent that at this stage it is too early to determine what sum should be paid by either Party and when, which will depend very much on what is contained in the Court’s orders as to costs.

47.

It is time for this drawn out litigation to be brought to a close, at least in this Court (there has been an indication that I may have to consider an application for leave to appeal).

48.

I direct that each Party submits its submissions as to the costs by 27 September 2024 with each Party having a right to reply by 4 October 2024.