HT-2023-000006 - [2024] EWHC 2516 (TCC)
Technology and Construction Court

HT-2023-000006 - [2024] EWHC 2516 (TCC)

Fecha: 03-Oct-2024

The calculation of the sum due for the measured works

The calculation of the sum due for the measured works

13.

As set out above, in calculating the amount due from J&BH to A & V, I gave credit for £364,909.64 which had already been paid by J&BH to A & V.

14.

That sum had at all stages been the agreed amount in respect of amounts already paid.

15.

In its submissions in respect of the hand down of the Sixth judgment, A & V submitted that there was an error in the amount paid, as it should have been the sum of £344,255.75, not £364,909.64.

16.

A & V asks the Court to correct this error.

17.

In response, J&BH submits, firstly, that the calculation was correct, and, secondly, that in any event “it is too late for any change to the sum previously paid. The sum previously paid was common ground between the parties and was determined in the June Judgment which has previously been handed down”.

18.

I agree with this second point. I decline to “correct” the alleged error as, in my judgment, I have no jurisdiction to do so.