VAT
VAT
A & V’s Claim Form and Particulars of Claim (which went through several iterations) claimed VAT.
In respect of the amounts claimed by A & V (except the claims for amount for Mr Blizzard’s fees) the amounts I have awarded are net of VAT.
A & V submits, and J&BH accepts, that I have still to deal with the amount, if any, to be awarded in respect of VAT on the other amounts I have awarded.
The amount of £6,096.56 awarded in respect of loss of profit is an award of damages, upon which VAT is not payable.
On the other sums awarded, it is A & V’s position that 20% should be awarded in respect of VAT.
J & BH’s position is contained in paragraphs 17 to 19 of its Note prepared for the purposes of the handing down of the Sixth judgment:
17. JBH reasonably assumed that the approach to VAT was common ground, given it was the approach the parties had adopted throughout the works on the Project.
18. In particular:
(1) JBH had made gross payments to A&V of £369,040.
(2) It was common ground, as explained in Section B above, that this was a net, i.e. exc. VAT, payment of £364,909.64.
19. The VAT payable on the Project was ratified by HMRC (via VAT audits) and has been applied to all previous payments to A&V.
(1) The vast majority of the project was zero rated. The works were for new student accommodation, which is generally subject to zero rating (https://www.gov.uk/hmrc-internal-manuals/vat-construction/vconst15380).
(2) A small part of the works (those relating to commercial areas) was subject to VAT at the standard rate.
(3) The agreed approach was that 5.66% of the value of the Works would be subject to VAT (at 20%).
(4) I.e. if the value of the works was £100, £5.66 of the works would be subject to VAT at 20%, giving VAT of £1.132 (or an effective VAT rate of c.1.1%).
J&BH has produced documentation which appears to me to support this case.
In those circumstances in my judgment I should add VAT at 20% on 5.66%, in the sum of £1,069.22, calculated as follows:
Measured works | £407,156.25 | |
Variation account | £53,200 | |
Less paid | -£364,909.64 | |
Amount due | £95,466.61 | |
5.66% | £5,346.13 | |
VAT at 20% | £1,069.22 | |
That is the sum which I award, but subject to this caveat, that there will be liberty to A & V to apply within 6 months of the handing down of this judgment to vary this order in the event that HMRC contends that the rate of 20% is applicable to the whole sum of £95,466.61. I make it clear that I grant this liberty in case HMRC disagrees with J&BH’s interpretation of the application of VAT, but I do not determine what is the correct interpretation.
- Heading
- This judgment was handed down by the court remotely by circulation to the parties’ representatives by email and released to The National Archives. The date and time for hand-down is deemed to be 3 Oct
- The effect of the Fifth and Sixth Judgments
- The calculation of the sum due for the measured works
- VAT
- CONSTRUCTION INDUSTRY SCHEME
- Interest
- Conclusions
![HT-2023-000006 - [2024] EWHC 2516 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)