HT-2023-000006 - [2024] EWHC 2516 (TCC)
Technology and Construction Court

HT-2023-000006 - [2024] EWHC 2516 (TCC)

Fecha: 03-Oct-2024

This judgment was handed down by the court remotely by circulation to the parties’ representatives by email and released to The National Archives. The date and time for hand-down is deemed to be 3 Oct

This judgment was handed down by the court remotely by circulation to the parties’ representatives by email and released to The National Archives. The date and time for hand-down is deemed to be 3 October 2024 at 10.30am

Mr Roger ter Haar KC :

1.

In this action and an associated action, I have previously handed down six judgments:

(1)

On 15 February 2023: [2023] EWHC 301 (TCC);

(2)

On 16 June 2023: [2023] EWHC 1483 (TCC);

(3)

On 6 October 2023: [2023] EWHC 2475 (TCC);

(4)

On 17 October 2023: [2023] EWHC 2576 (TCC);

(5)

On 18 June 2024: [2024] EWHC 1510 (TCC);

(6)

On 6 September 2024: [2024] EWHC 2295 (TCC).

2.

In this judgment, as in my previous judgments, I refer to J & B Hopkins Ltd as “J&BH” and to A & V Building Solution Limited as “A & V”.

3.

In the Fifth judgment handed down on 18 June 2024, I decided almost all the issues between the Parties on the merits. At paragraphs 521 and 522 I decided:

521.

Accordingly the amount due to A & V is as follows:

Claim

Amount Awarded

Measured works

£407,156.25

Variation account

£53,200

Loss of profit

£6,096.56

Less paid

-£364,909.64

Amount due

£101,543.17

522.

This does not allow for interest or adjudicators’ fees.

4.

In the Sixth judgment handed down on 6 September 2024 I determined the issues between the Parties as to adjudicators’ fees and interest.

5.

Issues have now arisen as to the amounts which I should award which have not previously been raised. There are some issues also outstanding as to the calculation of interest.

6.

The issues which I am asked to consider are:

(1)

The calculation of the sum due for the measured works claim;

(2)

VAT;

(3)

The effect of the Construction Industry Scheme;

(4)

Interest;

(5)

The sums due to J&BH;

(6)

Appropriate order at this stage.