HT-2023-000006 - [2024] EWHC 1510 (TCC)
Technology and Construction Court

HT-2023-000006 - [2024] EWHC 1510 (TCC)

Fecha: 18-Jun-2024

Measured Works

Measured Works

229.

After earlier iterations of the pleading, with which parts of my previous judgments are concerned, A & V’s claims are pleaded in the Scott Schedule which is at Section 8.1 of Volume 1 of the Trial Bundle.

230.

The Measured Works claims are set out at pages 1/50 to 1/52 under item nos. 1.0 to 47.0.

231.

In paragraph 48 of his written Opening Submissions, Mr Frampton helpfully summarised the differences between the Parties:

48.1

7 items (1.0, 2.0, 3.0, 32.0, 33.0, 34.0 and 37.0) account for £63,000 (c.84%) of the £73,256.66 difference between the parties. Save for item 37, these relate to the Podium works.

48.2

2 further items (4.0 and 35.0) should be considered alongside item 3.0 and 34.0 respectively.

48.3

For 16 items relating to the installation of heating, domestic water and waste on the different floors to Tower 2 (15.0 to 30.0) A&V had not completed the final fix of the domestic and waste pipes to the kitchens (as explained at paragraph 37 of Defence …. For some of these items, there were other elements of the works (including fitting radiators or the sink in the cleaner’s/janitor’s cupboard which had not been completed. These account for £7,942.40 of the difference between the parties.

48.4

For 6 items (12.0, 13.0, 14.0, 44.0, 45.0 and 46.0) relating to the installation in the top 2 floors of Towers 1 and 3 (and follow on testing fir all floors), JBH does not have evidence that the physical works were incomplete. However, A&V had not completed the quality assurance paperwork or sign off, meaning that it had to be checked by others. These items account for £2,472.80 of the difference between the parties.

48.5

There are 2 other miscellaneous items (31.0, 47.0).

232.

A & V’s workforce left site on 19 March 2021, in circumstances discussed in detail above. Mr Paduraru’s evidence, which I have accepted, was that he last attended at site on 22 March 2021.

233.

On Mr Paduraru’s evidence it was clear by the time he left site on the morning of 22nd March 2021 that the sub-contract had come to an end and the actions of J&BH were consistent with that having been the de facto position (I have analysed the legal position above).

234.

Shortly before the events of 19 March 2021, on 15 March 2021, A & V submitted its Application for Payment 13 which claimed the value of work done up to the end of February 2021. It was the figures for completeness of the Measured Works which found their way into the Scott Schedule and which found the basis for A & V’s claims at pages 50-52 of the Scott Schedule.

235.

In his oral evidence, Mr Paduraru explained that for the purpose of that payment application, he had walked the site and assessed the level of completeness of each part of A & V’s sub-contract works.

236.

This was the same procedure as had been adopted in respect of all previous applications.

237.

What did not happen, as happens on many projects, was a joint exercise in assessing progress on a monthly basis.

238.

On JBH’s part, monthly assessments of completeness were also carried out, which resulted in payments being made on a monthly basis against JBH’s assessments.

239.

Those assessments are set out in the third column on pages 50-52 of the Scott Schedule.

240.

On 22 March 2021, surveys were carried out by Mr Ian Davidson and Mr Julian Smart to assess the level of completeness of the works. Mr Davidson’s evidence in paragraph 17 of his witness statement was as follows:

I went around the site with Julian Smart (JBH’s Site Manager) to establish what works remained outstanding and what labour levels would be needed to complete the outstanding works. In order to help manage the remaining works, we made sure that photographs were taken of incomplete works and the status of A&V’s works was recorded by reference to the drawings.

241.

In March 2021 marked-up drawings were prepared by Mr Seth Brown (the J&BH Quantity Surveyor) and Mr Paul James. These are in the Trial Bundle at pages 5/2208 to 2209.

242.

Mr Davidson said that the photographs which are inserted into the marked-up drawings and which are also helpfully included elsewhere in the Trial Bundle in full size were taken by Mr Smart on the walk around.

243.

When he gave oral evidence, Mr Davidson accepted that the drawings at 5/2208 to 2210 were the drawings of the areas where there were incomplete works. On that basis he accepted that the sub-contract works to Towers 1 to 3 were complete, and also the works to level 0 in both Podiums (although he said that these works were limited in nature. He also accepted that the works to the East Side of Podium 1 were complete.

244.

In respect of the works to level 1 in the West Side of Podium 1, and to both West and East sides of Podium 2 were partially complete, although he said that most areas of the Podium works were to be completed.

245.

Mr Davidson made it clear in his oral evidence that he had no part in assessing the percentage completeness of any parts of the works. His job was to assist Mr Smart in his walk round. Mr Smart himself does not appear to have carried out the assessments: my impression is that these were carried out by Mr Brown, which would be appropriate in his role and profession of quantity surveyor. However, Mr Brown was not called as a witness, and there is no evidence before me as to the way in which he calculated his assessments.

246.

The same criticism can be made of Mr Paduraru’s assessments (i.e. that there is no evidence as to precisely how he came to his various assessments) but he was at least available to answer questions, and I formed the impression that overall his assessments seemed reasonable, albeit that I had little firm basis upon which to test some of his assessments. I would comment that had Mr Paduraru had access to the IAuditor system on 22 March 2021, then A&V’s position as to the completeness of the Project would have been on the contemporaneous record.

247.

Further, it will be seen below that in many cases J&BH’s assessments in the Scott Schedule of the completeness of parts of the sub-contract works depart significantly from its earlier assessments.

248.

In those circumstances, I generally prefer A & V’s assessments to J&BH’s.

Item 1.0 – Podium 1 Commercial, Level 00, Install lateral out runs

249.

This item relates to the lateral out runs for Level 00 in Podium 1. The description “commercial” is potentially misleading. This item does not concern a particular commercial area. Rather, it refers to all the pipework running laterally from the energy centre to the bottom of each of the risers, so that the services can move up the floors of the Podiums and the Towers. The reference to “commercial” signifies that it does not include the pipework in the rooms themselves.

250.

The scope of works was set out in Appendix 2 of the sub-contract:

“Podium 1 – continued –Install all distribution pipe runs on levels 1 and 2 including all rain waters and soils. Pipe works will include installing and pressure testing of all Heating & domestics & drainage pipework distribution runs in all areas area’s [sic] concerned with podium 1.”

251.

While this refers to “levels 1 and 2”, there are only 2 levels in the podiums: ground or street level and an upper level. The Tower floors are above the upper level. The reference to levels 1 and 2 in Appendix 2 is therefore to Levels 00 and 01 respectively in A&V’s quote and the Scott Schedule.

252.

The total sum allowed for “Podium 1 Commercial” works in Appendix 8 was £38,000 (Footnote: 63), split as to £25,000 for level 00 and £13,000 for level 01.

253.

A & V claims that these works were 80% complete, and therefore claims 80% of £25,000, namely £20,000.

254.

J&BH’s present position is that these works were 40% complete, thus allowing £10,000. It is to be noted that in Payment Certificate 11 (measuring the position as at December 2020) J&BH had assessed these works as being 50% complete, accepting A & V’s assessment. Since that date A & V had been working in the Podium areas, right up to the date works stopped.

255.

In paragraph 4.2 of A & V’s written closing submissions, reliance is placed upon the evidence given by Mr Davidson:

(a)

JBH [Trial Bundle 5, page 2208-2213] JBH does not detail any evidence of outstanding works for this item and/or area.

(b)

Mr Davidson in his witness evidence on trial day 3 confirmed within his paragraph 17 that he had undertaken an inspection and report with Julian Smart to detail all of the remaining outstanding works and that there were no works outstanding to this level. Upon me questioning this for a second time Mr Davidson reconfirmed this statement. Mr Davidson confirmed the photographs were from that inspection on the 22nd March 2021 and that Julian Smart coordinated the document as Mr Davidson was not very good with technology.

(c)

Although I was not able to undertake a record of the completeness of this item as a result of being removed from the IAuditor system on the 22nd March 2021 by JBH (an act of prevention), this item should be paid in full.

256.

In my judgment it was too late in closing submissions to put forward what was in essence an application to amend the Scott Schedule.

257.

However, the evidence referred to casts doubt upon accuracy of the assessment put forward by J&BH (40%) and raises questions as to the basis upon which Mr Brown carried out his exercise.

258.

This evidence also suggests to me that A & V’s assessments may be an underestimate of the amount which should be allowed.

259.

I am prepared to accept J&BH’s case that these works were not complete, but I accept A & V’s case that they were at least 80% complete by 19 March 2021.

260.

I allow the sum claimed by A & V, £20,000.

Item 2.0 – Podium 1 Commercial, Level 01, Install lateral out runs

261.

The issues here are the same as in respect of item 1.0, except here the works were to level 01 and the contract allowance was only £13,000.

262.

Again, A & V claims that the works were 80% complete, thus claiming £10,400.

263.

Again, J&BH puts forward an assessment of 40%, having previously accepted 50% in Payment Certificate 11.

264.

In paragraph 4.3 of A & V’s written Closing Submissions, it submits:

(a)

JBH [Trial Bundle 5, page 2208 (drawing with 16 photographs) and 2213 (list of 16 items)] JBH does not detail any outstanding works for half of the floor area to this item and only to drawing sheet 1of 2.

(b)

[Trial Bundle 5, page 2213] with its list of items JBH only refers to issues of outstanding works to 9 of the items.

(c)

Mr Davidson in his witness evidence on trial day 3 confirmed within his paragraph 17 that he had undertaken an inspection and report with Julian Smart to detail all of the remaining outstanding works and that there were only works to half of the floor outstanding to this level (only sheet 1 of 2). Upon me questioning this for a second time Mr Davidson reconfirmed this statement. Mr Davidson confirmed the photographs were from that inspection on the 22nd March 2021 and that Julian Smart coordinated the document as Mr Davidson was not very good with technology.

(d)

A&V contract value for this item is £13,000.00 so therefore based on Mr Davidson evidence, the maximum value outstanding for works remaining could only be half of that in the sum of £6,500.00.

(e)

Within JBH assessment in application 12 [trial bundle 4, page 1658] for works up to January 2021 JBH had already valued the entire floor level at 50%.

(f)

A&V continued with works to the podiums into February and March 2021 therefore the level of install would have increased.

(g)

The evidence of photographs and schedule of the 22nd March 2021 Trial bundle 5, page 2213 only details comments for 9 items outstanding and these all of a minor nature and not really relating to matters of “lateral out runs” and only likely to be a cost of approximately £1,000.00 to complete

(h)

Although I was not able to undertake a record the completeness of this item as a result of being removed from the IAuditor system on the 22nd March 2021 by JBH (an act of prevention), the court should consider the minor nature of works to complete as only being approximately £1,000.00. A&V would contend that they should be paid in full for this contract item as by JBH acts of prevention in taking over A&V works without permission and not awarding further time from the contract period of 12th March 2021 prevented this from being completed.

265.

I accept the above submissions as justifying the pleaded valuation in the sum of £10,400.

266.

I do not accept that there should now be a re-assessment of this item on the basis of carrying out an assessment of the cost to complete the works, this being a case of which J&BH should have had notice before the evidence was complete.

267.

I also do not accept the case that the item should be valued at 100% on the basis that J&BH prevented A & V from completing the work. There is a separate claim which I consider below for loss of profit/recovery of overheads as a result of the sub-contract coming to an end, which is the appropriate legal basis for such a claim.

268.

I am prepared to accept J&BH’s case that these works were not complete, but I accept A & V’s case that they were at least 80% complete by 19 March 2021.

269.

I allow the sum claimed by A & V, £10,400.

Item 3.0 – Podium 1, Level 01, Install risers per room with Heating, Domestic and SVP and

Item 4.0 – Podium 1, Level 01, Connect radiators in each room 1st and 2nd fix

270.

In respect of both these items A &V claims 80% completeness. The contract sum for item 3.0 is £22,800 and for item 4.0 is £1,000. Accordingly, the amount claimed for 3.0 is £18,240 and for item 4.0 £800.

271.

In respect of item 3.0, J&BH allows 30%, i.e. £6,840 and in respect of item 4.0 J&BH allows nil.

272.

In respect of item 3.0, in Payment Certificate 11 allowed 30% for item 4.0 (the same figure as claimed then by A&V) and nil for item 4.0 (in this instance A&V then agreed with the nil assessment).

273.

I do not accept that A & V did not make any further progress after December 2020, although it is to be noted that in Payment Application 12 A & V did not suggest that there was any increase in level of completeness up to 20 January 2021.

274.

In paragraph 4.4 of its written Closing Submissions, A & V submitted:

(a)

[Trial bundle 5, page 2208 (drawing with 16 photographs) and 2213 (list of 16 items) JBH does not detail any outstanding works for half of the floor area to this item and only to drawing sheet 1of 2.

(b)

[Trial bundle 5, page 2213] with its list of items JBH only refers to issues of outstanding works to 9 of the items.

(c)

Mr Davidson in his witness evidence on trial day 3 confirmed within his paragraph 17 that he had undertaken an inspection and report with Julian Smart to detail all of the remaining outstanding works and that there were only works to half of the floor outstanding to this level (only sheet 1 of 2). Upon me questioning this for a second time Mr Davidson reconfirmed this statement. Mr Davidson confirmed the photographs were from that inspection on the 22nd March 2021 and that Julian Smart coordinated the document as Mr Davidson was not very good with technology.

(d)

A&V contract value for this item is £22,800.00 so therefore based on Mr Davidson evidence, the maximum value outstanding for works remaining could only be half of that in the sum of £11,400.00.

(e)

Within JBH assessment in application 12 for works up to January 2021 JBH had already valued the entire floor level at 50%.

(f)

A&V continued with works to the podiums into February and March 2021 therefore the level of install would have increased.

(g)

The evidence of photographs and schedule of the 22nd March 2021 [Trial bundle 5, page 2213] only details comments for 9 items outstanding and these all of a minor nature and only likely to be a cost of approximately £2,000.00 to complete

(h)

Although I was not able to undertake a record the completeness of this item as a result of being removed from the IAuditor system on the 22nd March 2021 by JBH (an act of prevention), the court should consider the minor nature of works to complete as only being approximately £2,000.00. A&V would contend that they should be paid in full for this contract item as by JBH acts of prevention in taking over A&V works without permission and not awarding further time from the contract period of 12th March 2021 prevented this from being completed.

275.

As I read Certificate 12, the valuation was for 30%, not 50%, as suggested in paragraph (e) above.

276.

However, I accept the above submissions as justifying the pleaded valuation in the sum of £18,240.

277.

I do not accept that there should now be a re-assessment of this item on the basis of carrying out an assessment of the cost to complete the works, this being a case of which J&BH should have had notice before the evidence was complete.

278.

I also do not accept the case that the item should be valued at 100% on the basis that J&BH prevented A & V from completing the work. There is a separate claim which I consider below for loss of profit/recovery of overheads as a result of the sub-contract coming to an end, which is the appropriate legal basis for such a claim.

279.

I am prepared to accept J&BH’s case that these works were not complete, but I accept A & V’s case that they were at least 80% complete by 19 March 2021.

280.

Item 4.0 is a small item, in respect of which I see no reason to doubt Mr. Paduraru’s assessment.

281.

Accordingly, I accept Mr Paduraru’s assessments in the Scott Schedule, and allow £18,240 for item 3.0 and £800 for item 4.0.

Item 5.0: Level 01, Test SVP – Domestic and Heating pipe

282.

A & V makes no monetary claim against this item.

Item 32.00: Podium 2 Commercial, Level 00, Install lateral out runs

283.

I agree with J&BH’s suggestion in Mr Frampton’s written Opening Submissions that it is convenient to deal with all the Podium issues before turning to the Towers works.

284.

This is the same work as item 1.0, save that it relates to Podium 2 (instead of Podium 1).

285.

In the Scott Schedule, A & V claims 50% completeness against a contract allowance of £20,000, thus claiming £10,000.

286.

In its written Closing Submissions, A&V points out that in the marked up drawings at TB 3/2208-2213 J&BH does not detail any evidence of outstanding works for this item and/or area. The submission at paragraphs 4.8 (b) and (c) of those submissions was:

(b)

Mr Davidson in his witness statement on trial day 3 confirmed within his paragraph 17 that he had undertaken an inspection and report with Julian Smart to detail all of the remaining outstanding works and that there were no works outstanding to this level. Upon me questioning this for a second time Mr Davidson reconfirmed this statement. Mr Davidson confirmed the photographs were from that inspection on the 22 March 2021 and that Julian Smith coordinated the document as Mr Davidson was not very good with technology.

(c)

Although I was not able to undertake a record [of] the completeness of this item as a result of being removed from the IAuditor system on the 22nd March 2021 by JBH (an act of prevention), this item should be allowed in full.

287.

In my judgment it was too late in closing submissions to put forward what was in essence an application to amend the Scott Schedule.

288.

However, the evidence referred to casts considerable doubt upon the accuracy of the assessment put forward by J&BH (10%) and raises questions as to the basis upon which Mr Brown carried out his exercise.

289.

This evidence also suggests to me that A & V’s assessments may be an underestimate of the amount which should be allowed.

290.

As mentioned above, J&BH puts forward a figure of 10%, allowing £2,000.

291.

In Payment Certificates 11 and 12 J&BH assessed completeness at 25%.

292.

Given Mr Davidson’s evidence, I have no hesitation in accepting A & V’s case that these works were at least 50% complete by 19 March 2021.

293.

I allow the sum claimed by A & V, £10,000.

Item 33.00 Podium 2 Commercial, Level 01, Install lateral run outs

294.

This item is the same as item 32.00, save that it relates to Level 01.

295.

A & V claims 80% completeness against a contract allowance of £10,000, thus claiming £8,000.

296.

J&BH puts forward a figure of 10%, allowing £1,000.

297.

In Payment Certificates 11 and 12 J&BH assessed completeness at 25% in both Certificates.

298.

In paragraph 4.9 of its written Closing Submissions, A&V submitted as follows:

(c)

Mr Davidson in his witness evidence on trial day 3 confirmed within his paragraph 17 that he had undertaken an inspection and report with Julian Smart to detail all of the remaining outstanding works Upon me questioning this for a second time Mr Davidson reconfirmed this statement. Mr Davidson confirmed the photographs were from that inspection on the 22nd March 2021 and that Julian Smart coordinated the document as Mr Davidson was not very good with technology.

(d)

A&V contract value for this item is £10,000.00. A&V have claimed 80% complete. These works being major runs of brackets and pipework’s above corridor areas. Mr Frampton and I having a long discussion regarding this during my questioning. The court has since been provided with a video taken by myself of the podiums on the 12th March 2021 showing these completed pipe runs etc.

(e)Within JBH assessment in application 12 for works up to January 2021 JBH had already valued the entire floor level at 25%. Therefore, the maximum works to complete at that time was £7,500.00.

(f)

A&V continued with works to the podiums to this level January into February and March 2021 therefore the level of install would have increased.

(g)

The evidence of photographs and schedule of the 22nd March 2021 [Trial bundle page 5, pages 2211 and 2212] details comments for 49 items outstanding for the entire podium 2 level 1and in A&V opinion these all likely to be a cost of approximately £2,000.00 to complete. From the photographs presented at trial and reviewed and evidenced by Mr Frampton these clearly show quite an element of A&V works already installed.

(h)

Many of the items refer to pod connections, this an item relating to the install of the connections being separately fabricated by A&V within variation item 22 to which I explained within my cross examination by Mr Frampton.

(i)

Much of the work outstanding would require an instruction for a return visit due to changes in design, incomplete walls to the pods described by Mr Davidson in his cross examination “The podiums were not ready, pods not built, no walls and JBH wouldn’t accept areas”

(j)

Although I was not able to undertake a record the completeness of this item as a result of being removed from the IAuditor system on the 22nd March 2021 by JBH (an act of prevention), the court should consider the works to complete this Podium 2 Level 1 works as only being approximately £2,000.00. A&V would contend that they should be paid in full for this contract item as by JBH acts of prevention in taking over A&V works without permission and not awarding further time from the contract period of 12th March 2021 prevented this from being completed.

299.

I accept the above submissions as justifying the pleaded valuation in the sum of £8,000.

300.

I do not accept the case that the item should be valued at 100% on the basis that J&BH prevented A & V from completing the work. There is a separate claim which I consider below for loss of profit/recovery of overheads as a result of the sub-contract coming to an end, which is the appropriate legal basis for such a claim.

301.

I therefore allow the sum claimed by A & V, £8,000.

Item 34: Podium 2 level 01 Install risers per room with Heating, Domestic and SVP and

Item 35: Connect radiators in reach room 1st fix and 2nd fix

302.

These items are the same work scope as items 3.0 and 4.0, save that they relate to Podium 2 rather than Podium 1.

303.

Item 34 claims 70% of a contract allowance of £26,400, namely £18,480. Item 35 claims 70% of £1,000, namely £700.

304.

J&BH has an allowance of 10% for each item, therefore £2,640 and £100.

305.

This contrasts with the valuations in Certificates 11 and 12 (0% for both items in each certificate).

306.

Thus these are instances where, albeit modestly, J&BH’s position is more favourable to A & V than the earlier Certificates.

307.

The difference between the Parties in respect of this Item is particularly marked – hardly any progress on J&BH’s case, moving towards completion on A & V’s case.

308.

A & V’s submissions in respect of these items, as in respect of other items considered above, concentrate on Mr Davidson’s evidence.

309.

In respect of Item 34 A & V submitted in paragraph 4.10:

(a)

Trial bundle 5, page 2209 and 2210 (2 drawings with photographs) and 2211 and 2212 (list of 39 items)

(b)

Trial bundle 5, page 2211 and 2212 with its list of items JBH refers to issues of outstanding works to 49 of the items.

(c)

Mr Davidson in his witness evidence on trial day 3 confirmed within his paragraph 17 that he had undertaken an inspection and report with Julian Smart to detail all of the remaining outstanding works. Upon me questioning this for a second time Mr Davidson reconfirmed this statement. Mr Davidson confirmed the photographs were from that inspection on the 22nd March 2021 and that Julian Smart coordinated the document as Mr Davidson was not very good with technology.

(d)

A&V contract value for this item is £26,400.00. A&V have claimed 70% complete.

(e)

A&V continued with works to the podiums at this level from January into February and March 2021on an uneconomical basis at the behest of JBH and their 2 weeks look ahead therefore the level of install would have increased.

(f)

The evidence of photographs and schedule of the 22nd March 2021 [Trial bundle page 5, 2211 and 2212] details comments for 49 items outstanding for the entire podium 2 level 1and in A&V opinion these all likely to be a cost of approximately £5,000.00 to complete. From the photographs presented at trial and reviewed and evidenced by Mr Frampton these clearly show quite an element of A&V works already installed. In many instances the pipes were installed, just final connections with crimping etc. Mr Frampton and I having quite a discussion about crimping pipes. Mr Harman later during his cross examination confirming that crimping was acceptable but not his preferred method of pipe joints.

(g)

Many of the items refer to pod connections, this an item relating to the install of the connections being separately fabricated by A&V within variation item 22 to which I explained within my cross examination by Mr Frampton.

(h)

Much of the work outstanding would require an instruction for a return visit due to changes in design, incomplete walls to the pods described by Mr Davidson in his cross examination “The podiums were not ready, pods not built, no walls and JBH wouldn’t accept areas”

(i)

Although I was not able to undertake a record the completeness of this item as a result of being removed from the IAuditor system on the 22nd March 2021 by JBH (an act of prevention), the court should consider the works to complete to the entirety of Podium 2 Level 1 as only being approximately £5,000.00. A&V would contend that they should be paid in full for this contract item as by JBH acts of prevention in taking over A&V works without permission and not awarding further time from the contract period of 12th March 2021 prevented this from being completed.

310.

A & V’s submission in paragraph 4.11 in respect of Item 35 was similar:

(a)

Trial bundle 5, page 2209 and 2210 (2 drawings with photographs) and 2211 and 2212 (list of 39 items)

(b)

Trial bundle 5, page 2211 and 2212 with its list of items JBH refers to issues of outstanding works to 49 of the items.

(c)

Mr Davidson in his witness evidence on trial day 3 confirmed within his paragraph 17 that he had undertaken an inspection and report with Julian Smart to detail all of the remaining outstanding works Upon me questioning this for a second time Mr Davidson reconfirmed this statement. Mr Davidson confirmed the photographs were from that inspection on the 22nd March 2021 and that Julian Smart coordinated the document as Mr Davidson was not very good with technology.

(d)

A&V contract value for this item is £1,000.00. A&V have claimed 70%.

(e)

A&V continued with works to the podiums into February and March 2021 therefore the level of install would have increased.

(f)

The evidence of photographs and schedule of the 22nd March 2021 [Trial bundle 5, page 2211 and 2212] details comments for 49 items outstanding for the entire podium 2 level and do not generally detail incomplete radiator works.

(g)

Although I was not able to undertake a record the completeness of this item as a result of being removed from the IAuditor system on the 22nd March 2021 by JBH (an act of prevention), the court should consider the works to complete to the entirety of Podium 2 Level 1 as only being approximately £300.00. A&V would contend that they should be paid in full for this contract item as by JBH acts of prevention in taking over A&V works without permission and not awarding further time from the contract period of 12th March 2021 prevented this from being completed.

311.

In my view, if these works were as incomplete as J&BH contends, that this would have been reflected in the marked-up drawings. Accordingly, A & V’s reliance upon Mr Davidson’s evidence appears to me to be justified.

312.

However, as in respect of the other items considered above, I do not think it appropriate at this stage to allow A & V to put forward an amended case, I do not regard it as appropriate to rely upon a late case as to the cost to complete the works, nor to assess these items on the basis of 100% of the contract allowance for works which were not complete.

313.

In the circumstances I accept the valuations put forward in the Scott Schedule, namely £18,480 for Item 34 and £700 for Item 35.

Item 36: Podium 2 Level 01, Test SVP – Domestic and Heating Pipe Contract

314.

In the Scott Schedule there is no claim against this item.

315.

In paragraph 4.12 of A & V’s written Closing Submissions submits:

A&V have not undertaken this item, A&V would contend that they should be paid in full for this contract item as by JBH acts of prevention in taking over A&V works without permission and not awarding further time from the contract period of 12th March 2021 prevented this from being completed.

316.

I do not accept this submission: the works were not completed and therefore payment on the basis that they should be treated as having been completed is inappropriate. It is another matter as to whether A & V can recover loss of profits and overhead recovery in respect of this work.

Items 6.0 to 31.0 and 38.00 to 45.00: Works to Towers

317.

It is convenient to consider these Items together as they raise the same issues.

318.

Items 6.0 to 31.00 relate to Towers 1 and 2 and total £225,280. Items 38.00 to 45.00 relate to Tower 3 and total £74,240.

319.

In Certificate 12, J&BH had accepted that levels 1 to 7 were 100% complete. Levels 8 and 9 were treated as 98% complete with a note saying “Value held for kitchens and snag completion”. There was a separate line item for “Levels 2-9 test” which was also assessed at 98% on the same basis.

320.

In respect of Tower 2, Certificate 12 was recorded as 100% and other items at 98% on the same basis (“Value held for kitchens and snag completion”).

321.

In respect of Tower 3, levels 2 to 7 were recorded in Certificate 12 as being 100% complete, levels 8, 9 and the testing item were recorded as 98% complete on the same basis (“Value held for kitchens and snag completion”).

322.

In the Scott Schedule, J&BH still accepts that levels 2 to 11 of Tower 1 and levels 2 to 7 of Tower 3 were 100% complete.

323.

In respect of Tower 1, J&BH’s position changed in the Scott Schedule as follows: level 8 went from 98% to 95%; level 9 from 98% to 93% and the testing item from 98% to 89%.

324.

In respect of Tower 2, J&BH’s position changed in the Scott Schedule as follows: level 2 went from 100% to 94%; level 3 from 98% to 94%; levels 4, 5, 6, 7 8, 910, 11, 12, 13, 14 level 8 went from 98% to 95%; levels 15, 16, and 17 from 98% to 94% and the testing item from 98% to 84%.

325.

In respect of Tower 3, J&BH’s position changed in the Scott Schedule as follows: level 8 went from 98% to 95%; level 9 from 98% to 93% and the testing item from 98% to 89%.

326.

There is no evidence before me as to how precisely the revised figures were calculated, but three main issues of principle emerged in the course of the trial: firstly that there were some incomplete works in some kitchens; that there were some defective works; and that the QA process remained outstanding.

327.

In respect of the issue as to kitchens, this was explained carefully and fully in paragraphs 125 to 139 of Mr Frampton’s written Opening Submissions. The total deduction sought is £6,783.75.

328.

As to the QA issue, it is common ground that QA needed to be completed in a number of areas.

329.

As to the defective works, these were mentioned in respect of J&BH’s counterclaim for costs to complete as consisting of leaks to pipework, which had to be fixed (see paragraphs 19 and 20 of Mr Ian Davidson’s witness statement (Footnote: 64)).

330.

In paragraph 4.7 of A & V’s written Closing Submissions, it is submitted in respect of Towers 1 and 2:

(a)

Trial bundle 5, page 2208-2213 JBH does not detail any evidence of outstanding works for this item and/or area.

(b)

Prior to the dispute JBH had valued many of these items as complete or a high percentage complete.

(c)

Mr Davidson in his witness evidence on trial day 3 confirmed within his paragraph 17 that he had undertaken an inspection and report with Julian Smart to detail all of the remaining outstanding works and that there were no works outstanding to the 3 towers. Upon me questioning this for a second time Mr Davidson reconfirmed this statement. Mr Davidson confirmed the photographs were from that inspection on the 22nd March 2021 and that Julian Smart coordinated the document as Mr Davidson was not very good with technology.

(d)

Although I was not able to undertake a record the completeness of this item as a result of being removed from the IAuditor system on the 22nd March 2021 by JBH (an act of prevention), this item should be paid in full.

331.

In respect of Tower 3, paragraph 4.14 of A & V’s written closing submissions was to like effect.

332.

As set out above, the total claimed by A & V for all three towers was £299,250 (£225,280 + £74,240).

333.

The amount contended for by J&BH in respect of the kitchens is £6,783.75. That is a little over 2% of the contract allowance for the direct works in the Towers. There is evidence of incomplete works in the kitchens as analysed by Mr Frampton in his written Opening Submissions, and as explored in cross-examination of Mr Paduraru.

334.

In my view there should be a reduction of that sum (£6,783.75) to reflect those outstanding works, but otherwise I accept A & V’s case that the works to the Towers were substantially complete.

335.

As to the alleged leaks, it seems to me that J&BH was correct to treat the costs of dealing with these leaks as being an element of the cost to complete, and I make no reduction for those defects.

336.

As to the QA elements, it seems to me that the costs of Mr Paduraru attending site to carry out QA assessments would have been minimal. Whilst in respect of other items I have declined to award monies upon the basis that A & V would have carried out 100% of the works but for J&BH’s acts of prevention, my reason for not doing so (namely that A & V’s approach does not allow for the costs which would have been incurred in completing the works) does not apply in respect of Mr Paduraru’s time, given that he was a full-time employee of A & V whose cost A & V would have incurred in any event. Accordingly, I make no reduction for the outstanding QA exercise: I would add that I had and have no basis upon which to test whether the reductions made by J&BH could be justified – they appeared to be somewhat arbitrary as well as conflicting with the assessments in Certificate 12 and Mr Davidson’s evidence as to overall completion, which must have included elements of QA carried out before 19 March 2021.

337.

Accordingly, I assess the value of the works in the Towers in the sum of £299,250 less £6,783.75, namely £292,466.25.

Item 37.00: Preliminaries phase 1 – Towers 1 and 2; Podiums 1 and 2

338.

This is one of two items relating to preliminaries.

339.

The contract allowance was £22,240.

340.

A & V claims 100%.

341.

J&BH suggests 75%.

342.

In paragraph 4.13 of its written Closing Submission, A & V submits:

A&V value this at 100% based upon the value for this item as it directly relates to the contract period on site being to the 12th March 2021. Any time thereafter would require additional preliminaries and thus an instruction.

343.

In Mr Frampton’s written Opening Submissions he submits as follows:

A&V’s position

163.

A&V claims that item 37.0 was 100% complete and values it at £22,240.

164.

A&V does not properly justify or evidence its position. A&V’s comment in the Scott Schedule is the same, verbatim, as for Item 1.0 (see paragraph 57 above).

165.

This comment only goes to why the Works were incomplete. It does not address the extent of the Works which were incomplete.

166.

The comment also contradicts A&V’s assessment. Given it accepts the works were incomplete, A&V cannot claim the full preliminaries sum.

167.

As the claimant, and particularly when it accepts that the Works were incomplete, the burden is on A&V to demonstrate the extent and value of the Works it did complete.

JBH’s position

168.

JBH assesses that item 37.0 was 75% complete, £16,680.

169.

The difference between the parties is £5,560.

170.

JBH’s assessment is a pro rata based on the progress made by A&V. JBH’s assessment aligns with its valuation of the extent to which A&V had completed the Tower 1, Tower 2, Podium 1 and Podium 2 works.

171.

Specific tasks covered by the preliminaries which A&V had not completed included:

171.1

The marked-up/ red line drawings showing any deviations to the installed pipework from the design. The production of these drawings was a management task required by the Sub-Contract Pre-Order Meeting Minutes [Vol 1/ Tab 25/ 293]. In particular see:

a)

Item 7.8A (“Record drawings required” “Yes” [297]).

b)

Item 9.7A) of (“Red lind [sic] mark ups or as build drawings” [299]).

c)

Item 12.9 (“Final account to be submitted within 2 weeks of completion of sub-contract works with full substantiation, instructions, marked up drawings, breakdowns and invoices supporting values claimed” [302]).

A&V had not provided any of these drawings (which would be normally produced once all the Sub-Contract Works were complete).

171.2

The production of the testing certificates for the pressure testing of the pipework.

172.

JBH’s overall position is that A&V had completed £243,500.95 of these works which had a total value of £345,760. That is 70%.

173.

A&V’s claim is that it had completed £311,900, or 90%. 90% of the preliminaries of £22,240 would be £20,016.

344.

As set out above, I have accepted A & V’s case save as to £6,783.75. Accordingly, on a percentage of completion basis A & V would be entitled to about £20,000 for these preliminaries.

345.

However, I accept A & V’s case that, having been on Site for the full contract period, A & V is entitled to the full amount of £22,240.

Item 47.0: Preliminaries, Phase 2, Tower 3

346.

The difference between the Parties is minimal.

347.

A & V claims 100% of the contract allowance of £5,560.

348.

J&BH says that the figure should be 98%, namely £5,448.80 giving rise to a difference of £111.20.

349.

As with Item 37.00, I accept A & V’s claim to be entitled to 100%, namely £5,560.

Measured Works: Conclusions

350.

For the above reasons, I value the Measured Works at £6,783.75 less than the sum claimed of £413,940, namely £407,156.25.