25.

The Parties’ rival positions are as follows:

Item

A & V

J&BH

Difference

Measured Works

£413,940.00

£338,683.35

£75,256.65

Variations

£67,200.00

£39,228.00

£27,972.00

A & V Breaches and Losses

£645,100.45

£0.00

£645,100.45

JBH Contra Charges

£0.00

(£88,069.61)

£88,069.61

Mr Blizzard Adjudicator Fees

£17,400

£0.00

£17,400.00

Mr Smith Adjudicator Fees

(£13,962.00)

(£13,962.00)

£0.00

Enforcement proceedings costs

(£20,822.00)

(£20,822.00)

£0.00

Paid to date

(£364,909.64)

(£364,909.64)

£0.00

Total

£743,946.81

(£109,851.90)

£853,798.71