[2024] EWHC 3625 (TCC)
Technology and Construction Court

[2024] EWHC 3625 (TCC)

Fecha: 13-Sep-2024

Issue 2: Was there a further certain and binding oral agreement (or a certain and binding variation to any prior agreement) between Orchard House and the Defendants in or around July 2020 as to the Pu

Issue 2: Was there a further certain and binding oral agreement (or a certain and binding variation to any prior agreement) between Orchard House and the Defendants in or around July 2020 as to the Purchase Price for Plot C as part of a wider agreement, the total consideration for which was £601,000

273.

For the reasons set out between paragraphs 227 to 246 above, I do not find that such an agreement was reached.