Ashcroft v Curtin
[1971] 1 WLR 1731, the Court of Appeal stressed that, whatever the concerns about imprecision, common sense demands an assessment of damage, even if such an assessment cannot be arrived at with mathematical precision. 58.But everything ultimately turns on the facts of the particular case. There may come a point at which the court may conclude that the evidence as to what was done and what was paid for was so vague and unsatisfactory; that so many of the individual claims made for work done have been shown, on investigation, to have nothing whatsoever to do with the breaches by the defendants; and that the claim was so unreliable from top to bottom, such that a reasonable retrospective valuation of the reinstatement work was the only appropriate basis on which to assess the damages claim. In such a case, the defendant will have demonstrated that, despite the earlier scrutiny, the claimed/actual costs were in fact unreasonable.
3.2 The Problems With Brit Inns’ Claim
- MR JUSTICE COULSON
- Approved Judgment
- Section 2
- Sections 3
- Sections 5
- Section 7
- Section 8
- a) Materials
- b) Contractors/Labour
- c) Total Figure
- East Ham Corporation v Bernard Sunley & Sons Ltd
- The Maersk Colombo
- Trustees of the Hospital for Sick Children v McLaughlin & Harvey PLC
- McGlinn v Waltham Contractors and Others
- Skandia Property (UK) Ltd v Thames Water Utilities Ltd
- Chaplin v Hicks
- Ashcroft v Curtin
- a) Introduction
- b) No Fixed Scope
- c) Inadequate Invoices
- £12925.00
- d) Wrongly Claimed Invoices
- e) The Absence Of Evidence Of Payment
- f) Absence Of Evidence From The Contractors
- g) Comparison With Original Fit-Out Costs
- h) Summary
- Section 4.4
- £47,654.89
- The Claim
- The Problems With The Claim As Presented
- Mr Thomas’ Valuation
- iv) Modifications To Mr Thomas’ Figures
- £17,500
- c) Electricians
- Modifications to Mr Thomas’ Figures
- £25,750
- d) Painters
- £1,650
- f) Plumbing
- Possible Modifications To Mr Thomas’ Figures
- £7,118
- g) SP Contracts
- The Proper Analysis
- £28,681
- The Problems
- £4,842.50
- i) Manhole and Related Works
- j) Conclusions
- a) Overview
- b) The Experts’ Joint Statement
- c) The Individual Items
- Invoice 1: Temporary Signs £13.08
- Invoices 3, 95, 100, 120, 122, 138, 172, 205, 219, 236, 237 and 259
- Invoices 32 and 36: Storage of Cubicles (£300) and New Cubicles (£5,495.62)
- Invoices 56, 59 and 61
- Invoices 101, 101a and 102
- Invoice 149
- Invoice 177: Urinal and Furniture
- Invoices 221 and 222
- Invoice 232: Reprogramming and Training
- Invoice 248
- Invoice 69: TV Cable and Invoice 310: Soap Dispensers
- Invoices 313 and 332 (Various Glazing)
- d) Conclusions
- Section 4.2
- Section 4.4
- Sections 4.2
- Sections 5.2
- Section 6
- Section 6.2
- Sections 6.2
- Section 6.4
- Section 6.5
- Section 6.6
- Section 6.7
- a) The Issue
- b) Uncertainty of Opening Dates
- c) Staff Issues
- d) Equipment Failures
- e) Smell
- f) Summary
- b) Mr Isaac’s Analysis
- £20,779
- £16,403.24
- Section 7
- £173,871.13
