E. KML’s Allegations of Breach
E. KML’s Allegations of Breach
The pleaded claim in respect of Clause 4 of the warranties set out at paragraph 37(4) of the Amended Defence and Counterclaim alleges that the UTV-670 was not fit for its intended purpose in that:
Throughout the works the UTV-670 suffered various issues including (i) sensor issues; (ii) repeated failure to maintain pressure; (iii) inability to maintain traction; (iv) hose failures; and (v) HPU failures.
On average for every 1.6 hours that the UTV-670 worked 1 hour of breakdown/maintenance time was incurred.
The burial depth of the cable was not achieved throughout the length of the cable (although this appears to relate to a claim for potential future remedial work which has not been pursued).
The tether length installed onto the UTV-670 was 250m rather than 350m (this does not appear to have been pursued).
In its pleaded answers to Requests for Further Information, KML set out other equipment which the equipment supplied continually failed (‘by way of examples’). Reference was then made to just 3 events, on 26, 27 and 29 June relating to the anchor wires disconnecting: a hose connection failing and a hose fitting parting.
Further criticisms of the equipment were made indirectly in paragraphs 37(5) of the Amended Defence and Counterclaim, which introduced an alleged failure on the part Pharos to exercise reasonable skill and care in:
failing to conclude that the UTV-670 was unsuitable for the conditions which it was likely to encounter on site, to have advised accordingly and to have provided alternative apparatus which was suitable for operation in the conditions;
failing properly to assess the suitability of the lay-flat hoses which were prone to sink when filled with water, to strain the rigging securing the buoys used to keep them afloat, and to kink and become entangled with the guideline and the communication umbilical leading to the UTV-670. It is said that Pharos should have deployed appropriate floating hoses;
failing to advise on or before 24 May 2022, that the UTV-670 should be deployed first to work in the offshore area, concurrent with the MBES survey, and to amend the Method Statement accordingly. This would have, it is alleged, minimised the reasonably foreseeable risk of delays and difficulties in the event that the MBES survey of the near and very near inshore areas revealed seabed conditions which required dredging or other remedial works before the UTV-670 would be suitable to operate in those areas.
Against KML’s pleaded case, I consider the breaches pursued by KML in Closing.
Lay Flat Hoses
The water used by the UTV-670’s jetting sword was fed into it via an 8-inch water hose which was connected to two water pumps on board the vessel. This was a “lay flat” hose, meaning that it folded down when there was no water in it, similar, as Mr Gamble put it, to an extra-large fireman’s hose. The hose used on this project came in 15m sections and needed to be connected via couplings.
There is no dispute that the couplings initially procured by Pharos to connect lengths of the lay flat hoses did not work. Although in opening a case relating to these couplings was advanced based on a combination of the urgency of operations combined with the ‘ultimate’ cause being the requirement for 200m of hoses attributable to the choice of the Suzanne A, this was effectively abandoned when Mr Gamble fairly conceded in cross-examination (as, indeed, he had already accepted at paragraph 67 of his witness statement) that irrespective of these issues, the procurement of sub-standard couplings was an error or failing on the part of Pharos.
Mr Moore attributed 36 hours and 4 minutes to ‘Lay Flat Hoses’. The majority of the relevant time related explicitly to the coupling issue. The only other entries attributable to the lay flat hoses by Mr Moore were:
30 minutes on 24 June 2022 (‘Completed integration of 30m 8” water hose to vehicle’);
2 hours and 39 minutes on 25 June 2022 (‘Drone shows water hose section snagged with the y anchor of the rigging…..Shore team working to release hoses’). This is the same entanglement issue identified by Mr Scott at paragraphs 7.58 and 7.60 of his Report; and
2 hours 35 on 29 July 2022, after the new couplings had been deployed, (‘8” flat lay hose parted at the vehicle…repair maintenance underway’).
In addition to the specific coupling issue, KML contends that Pharos was in breach by reason of the decision to use lay flat hoses itself, rather than flexible hoses (i.e. like large garden hoses) to supply water to the UTV-670 during very nearshore trenching operations. Although its allegations about the use of lay flat hoses per se are pleaded with somewhat greater particularly under its claim for a failure to have assessed their suitability with reasonable skill and care, the issue in dispute is clear, and no point was taken by Pharos as to the pleadings in relation to the criticism made of the decision to use lay flat hoses at all.
The reason the distance between the Suzanne A (on which the High Pressure Unit (‘HPU’) feeding the water to the UTV-670 sat) needed to be up to 200m when the UTV-670 was near shore was the inability of the Suzanne A to get closer because of its draught. Mr Gamble accepted, rightly, that this was known at the time Pharos entered into its contract with KML. Mr Macey-Dare KC is therefore correct that, in these circumstances, whilst it might be considered that the choice of vessel was itself potentially sub-optimal, as considered by Mr Moore, this is irrelevant to the analysis of fitness for purpose or whether Pharos’ choice of system was reasonably competent. Pharos undertook to provide a system which worked on the Suzanne A; if it could not do so, then it should not have entered the contract.
The allegation of lack of fitness for purpose of the lay-flat hoses in principle, leaving aside the coupling failures, rests on the fact that, unlike flexible hoses which could be kept from sinking with a pillow float system, the flat hoses necessitated a ‘taut wire’ or ‘guiding wire’ system for controlling the hose and the umbilical and ensuring it did not sink.
Mr Moore agreed that the taut wire was ‘sub-optimal’. Mr Moore also agreed that the 200m distance would have presented no significant issues for this operation with the use of flexible hoses. He contended, however, in his report that the use of a lay-flat hose was necessitated by space constraints on the vessel. Notwithstanding this, Mr Moore accepted in cross-examination that it is likely that space would not have been an issue if Pharos had required any unnecessary equipment on the deck of the Suzanne A to be removed, which they would have been entitled to insist upon. I do not therefore consider space to be a justification for the use of lay flat hoses. I note, in addition, that Mr Gamble did not consider that space was the reason behind the choice of a lay flat hose. He said it was because it was lighter when being pulled by the UTV-670 in the water. It is not obvious why this should be the case (with flexible hose supported by floats) and no further detail was given. Weight was not a consideration or justification considered by Mr Moore.
In his report, Mr Scott considered bluntly that ‘the configuration does not work’. He also concluded that the configuration resulted in most if not all the handling problems with the tool at the beach and nearshore, as set out in his Appendix 8. Notwithstanding the general unreliability of Appendix 8 for the reasons described above, I have nevertheless reviewed the document to discern the nature and extent, and impact, of the concerns Mr Scott is referring to. It is very difficult, reading Appendix 8 as generously as possible, to identify what Mr Scott is referring to save for two entries on 13 July and 10 August which appear to relate to the hose/guide wire configuration causing problems, and in respect of which he records no downtime against the latter.
The mere fact that the solution may, particularly compared with another solution, be ‘sub-optimal’ does not render the solution of itself unfit for purpose. I do not accept Mr Scott’s evidence that ‘the configuration does not work’. To the contrary, there is no reliable evidence that the system did not generally work, once the coupling issue was fixed. The entanglement issue identified by both experts appears, on the basis of Mr Moore’s analysis which I have accepted, to have been isolated and resulted in less than 3 hour’s downtime. In the context of the project as a whole, this is not an issue that demonstrates that the system was unfit for purpose, particularly as it happened near the beginning of the works, and did not happen again. The only other specific downtime attributable to lay flat hose related issues, coupling aside, is minimal. Whilst more complicated than using flexible hoses, there is no evidence that the system was necessarily slower: even with lay flat hoses and the taut wire system, speeds in excess of 250m/hour for trenching offshore were achieved (as calculated by Mr Moore in his report). In these circumstances, it is not possible to conclude that the system was not fit for purpose, or that its choice was the result of a failure to take reasonable skill and care.
- Heading
- hand-down is deemed to be 10.30 on the 11 th of July 2025
- B The Factual and Expert Witness Evidence
- Factual Chronology up to Sailaway of the Susanne A
- D. The Contract
- The Proper Approach to Construction
- Daily Charges for more than 10 days
- Daily Charges for more than 7 personnel per day
- Personnel mobilisation and expenses for more than 7 personnel
- Daily charges for personnel prior to the arrival of the UTV-670
- Daily charges during periods of breakdown
- Daily charges for waiting on weather
- Application of LADs
- The Mobilisation Date
- D. Did Pharos deliver to the UTV-670 to Esbjerg with reasonable skill and care and/or within a reasonable time for the purposes of mobilisation?
- E. The Embedment Works: The Causes of Downtime
- Weather Downtime
- Tidal Downtime
- Seabed Condition Downtime
- Technical and Operational/Tool Downtime
- E. KML’s Allegations of Breach
- Supply of the UTV-670 unable to cope with seabed gradients
- The associated equipment, deck layout and personnel
- F. What was a reasonable time for carrying out the Embedment Works?
- G. Quantification of Pharos’ Claim
- Section 25
- Equipment spread costs
- Personnel costs (excluding expenses)
- Personnel daily expenses
- Transportation of the UTV-670 and other equipment
- Transportation (flights) for personnel/employee
- H. Quantification of KML’s Counterclaim
- Conclusions
![HT-2023-000321 - [2025] EWHC 1764 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)