Discharge Ground 3: Breaches of or a departure from the terms of the JVA in relation to the timing of the sale of the villas and other matters relating to the joint venture
Discharge Ground 3: Breaches of or a departure from the terms of the JVA in relation to the timing of the sale of the villas and other matters relating to the joint venture;
The Defendant contends that the guarantee is also discharged on the grounds that there has been a “not unsubstantial” breach by a creditor of a term of the principal contract which has been itself “embodied” into the guarantee (relying on Millett & Andrews §6-029).
These points do not arise for consideration in light of my findings that (a) the Claimant’s claims are statute barred and (b) the guarantee was discharged pursuant to Discharge Ground 2, as set out in Section H.2.2 above.
However, for completeness, I reach the following conclusions on this part of the case. In summary, the Defendant alleges the following breaches of the JVA:
Clause 9 –the parties failed to act in utmost good faith towards one another in all aspects and in particular in connection with leases and sales of the villas.
Clauses 1, 3, 8, 11, 12 and 14 – the joint venture ceased to be joint. The Defendant alleges that (a) Mr Dunn ran the venture for himself without regard for Mr Kazolides or Mr Stylianou; (b) Mr Dunn insisted that Mr Stylianou resign as a director and banned him from entering the property; and (c) Mr Dunn insisted on taking all or nearly all relevant decisions himself.
Clause 3(a)(ii) – the decision to replace the Company secretary in 2011.
Clause 3(c) – Mr Dunn’s failure to act in the best interests of the Company and on sound commercial profit-making principles.
Clause 15(1) – failure to keep full accounts sufficient to calculate the Net Profit or Net Loss.
Clause 6(d) and 15(2) – failure to prepare completion accounts forthwith after the sale of all of the villas.
Clause 8 – failure to keep Mr Kazolides informed of all aspects concerning the villas.
Clause 5(a)(iii) – causing the Company to accept loans in amounts which were not reasonable and which it did not reasonably require to complete the development.
Clause 14(2) - failure to obtain approval from Mr Kazolides in respect of any sales that took place or any leases.
Putting aside the arguments over breach which were fact sensitive, I do not consider that the Defendant has established that these were the duties of the creditor in its principal contract with the Company. Further, I do not see that these were terms which were then embodied into the guarantee as an obligation of the creditor. In the circumstances, I do not consider that any of these matters could give rise to a discharge.
- Heading
- I direct that no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic Introduction
- The Parties and other relevant persons
- The Land
- The Contractual Arrangements
- General Observations on the Evidence The oral witness evidence
- The recollection of witnesses generally
- The central issues for determination
- The Construction Issues
- The profit sharing arrangements under the JVA
- The payment waterfall under the JVA
- The Guarantee Validity Issues
- Validity Issue 1: Did Mr Kazolides provide a guarantee under the JVA?
- The argument that the joint venture was intended to be a 50/50 arrangement and the guarantee is inconsistent with that arrangement
- The failure to name Mr Kazolides expressly and the Statute of Frauds
- Whether Mr Michael had authority to enter the guarantee
- Validity Issue 2: Should clause 18 be rectified to name Mr Kazolides as the Guarantor?
- The Limitation Issues
- Limitation Issue 1: Is the Limitation Period 6 or 12 years?
- Limitation Issue 2: What is the test for insolvency under clause 5(c)?
- Limitation Issue 3: Was the Company in default more than 6 / 12 years before the issue of the claim?
- The expert evidence on valuation of the Property
- The Liabilities of the Company in March and December 2010
- The solvency of the Company in early March 2010
- Cashflow insolvency
- Legal Principles
- Variation of the contract between creditor and debtor
- Agreement between creditor and debtor to give debtor additional time to pay
- Breach by the creditor
- Grounds for Discharge
- Discharge Ground 1: Material change in the JVA due to the execution of the SJVA
- Discharge Ground 2: Mr Dunn giving an extension of time for payment by the Company
- Discharge Ground 3: Breaches of or a departure from the terms of the JVA in relation to the timing of the sale of the villas and other matters relating to the joint venture
- Discharge Ground 4: An oral agreement between Mr Dunn and Mr Kazolides
- Other matters
- Conclusions
![BL-2022-000438 - [2025] EWHC 2212 (Ch)](https://backend.juristeca.com/files/emisores/logo_O3rEzCI.png)