I direct that no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic Introduction
I direct that no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.
Sharif A Shivji K.C. :
Introduction
This case concerns a dispute over an alleged guarantee relating to a joint venture between the Claimant (“Mr Dunn”), the Defendant (“Mr Kazolides”) and Mr Christopher Stylianou (“Mr Stylianou”) to develop and sell villas in Droushia, Cyprus. The joint venture vehicle was a company, incorporated in Cyprus, called Astriver Co Limited (“Astriver” / “the Company”).
In summary, whilst the construction of the villas was ultimately completed, the project was beset by various difficulties and ran behind schedule and over budget. The original main contractor for the project was removed and a new contractor appointed. Even then, further remedial works were required. The villas were eventually completed in October 2010.
Whilst efforts were made to sell the villas at various points, there is a dispute between the parties as to whether these efforts were sufficiently diligent and whether the pricing was realistic. The first villa was sold in 2018 and the other six villas were sold in 2019 to a company connected to Mr Dunn called Black Flamingo Limited (“Black Flamingo”) although there is a dispute over whether this was a genuine transaction. Four villas have since been sold by Black Flamingo.
Mr Kazolides and Mr Stylianou provided the land for the joint venture and Mr Dunn provided the funding by way of loan to the Company. Under the terms of Mr Dunn’s loan, save for a grace period up to 2008, interest was running at a rate of 8% per annum compounded.
The long period that it has taken to sell the villas has meant that the size of Mr Dunn’s outstanding loan has grown significantly over the years and there is a large outstanding balance, even after taking into account the sales of the villas that have occurred.
Mr Dunn brings the present proceedings claiming that Mr Kazolides has guaranteed the repayment of Mr Dunn’s loan to the Company and, pursuant to that alleged guarantee, he seeks recovery of the whole outstanding balance of his loan.
Mr Kazolides denies that he gave any guarantee and argues, in the alternative, that if the Court finds a guarantee was given, it was discharged on various bases.
Background
- Heading
- I direct that no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic Introduction
- The Parties and other relevant persons
- The Land
- The Contractual Arrangements
- General Observations on the Evidence The oral witness evidence
- The recollection of witnesses generally
- The central issues for determination
- The Construction Issues
- The profit sharing arrangements under the JVA
- The payment waterfall under the JVA
- The Guarantee Validity Issues
- Validity Issue 1: Did Mr Kazolides provide a guarantee under the JVA?
- The argument that the joint venture was intended to be a 50/50 arrangement and the guarantee is inconsistent with that arrangement
- The failure to name Mr Kazolides expressly and the Statute of Frauds
- Whether Mr Michael had authority to enter the guarantee
- Validity Issue 2: Should clause 18 be rectified to name Mr Kazolides as the Guarantor?
- The Limitation Issues
- Limitation Issue 1: Is the Limitation Period 6 or 12 years?
- Limitation Issue 2: What is the test for insolvency under clause 5(c)?
- Limitation Issue 3: Was the Company in default more than 6 / 12 years before the issue of the claim?
- The expert evidence on valuation of the Property
- The Liabilities of the Company in March and December 2010
- The solvency of the Company in early March 2010
- Cashflow insolvency
- Legal Principles
- Variation of the contract between creditor and debtor
- Agreement between creditor and debtor to give debtor additional time to pay
- Breach by the creditor
- Grounds for Discharge
- Discharge Ground 1: Material change in the JVA due to the execution of the SJVA
- Discharge Ground 2: Mr Dunn giving an extension of time for payment by the Company
- Discharge Ground 3: Breaches of or a departure from the terms of the JVA in relation to the timing of the sale of the villas and other matters relating to the joint venture
- Discharge Ground 4: An oral agreement between Mr Dunn and Mr Kazolides
- Other matters
- Conclusions
![BL-2022-000438 - [2025] EWHC 2212 (Ch)](https://backend.juristeca.com/files/emisores/logo_O3rEzCI.png)