Conclusions
Section X - Conclusions
For the reasons set out above, I find as follows:
Winsopia was in breach of the ICA in respect of Items 1 to 30, 34, 35, 37, 38, 40, 41, 43, 45, 46, 49 and 50 as summarised in paragraphs [838] to [844] above.
The above breaches of the ICA did not fall within the rights conferred by the Software Directive/the CDPA.
LzLabs and Mr Moores unlawfully procured the above breaches of the ICA by Winsopia.
The procurement claim against LzLabs UK fails.
Mr Rockmann and Mr Cresswell are entitled to rely on the principle in Said v Butt by way of defence and therefore are not liable for the tort of unlawfully procuring breaches of the ICA by Winsopia.
LzLabs, Winsopia and Mr Moores are liable for the tort of unlawful means conspiracy.
The unlawful means conspiracy claims against LzLabs UK, Mr Cresswell and Mr Rockmann fail.
The audit request made by IBM was valid and Winsopia was in breach of the ICA in failing to comply with it.
IBM validly terminated the ICA and associated agreements under clause 1.12.2 and/or 4.5.3; alternatively, IBM was entitled to treat the breaches as repudiatory and terminate at common law, as set out in paragraphs [980] to [987] above.
Clause 1.11.4 is an effective time bar provision as between IBM and Winsopia in respect of the claims against Winsopia but does not apply to the claims against the other defendants and does not apply to wrongdoing where there has been deliberate concealment until IBM discovered the concealment or with reasonable diligence could have done so.
The defendants deliberately concealed the connection between Winsopia and LzLabs and/or Winsopia’s breaches of the ICA for the purpose of section 32 of the Limitation Act 1980 and IBM could not with reasonable diligence have discovered the concealment prior to August 2020. IBM could not with reasonable diligence have discovered the concealment regarding the unlawful conspiracy claim prior to June 2023.
The claims are not contractually time-barred or statute-barred for limitation.
Following hand down of this judgment, the hearing will be adjourned to a date to be fixed for the purpose of any consequential matters, including the form of order, any declaratory, injunctive or other relief, future quantum determination or other disposal, any applications for costs or permission to appeal. Therefore, any relevant time limits are extended until the adjourned hearing or further order.
- Heading
- Mrs Justice O’Farrell
- Section II - Background to the dispute
- The SDM
- Hercules
- Neon litigation
- Formation of LzLabs and Winsopia
- The ICA
- SDM development and the clean room procedures
- Launch of the SDM
- Project Eiger
- Further development of the SDM
- Audit request and termination
- Section III - The proceedings
- The Issues
- The factual witnesses
- Section IV - Construction of the ICA
- Approach to construction of the ICA
- Scope of licence
- The ICA Programs
- Customer applications
- Licensed Program Specifications
- Independent software vendors (ISVs)
- Debugging tools
- Restrictions on use of ICA Programs
- Legislative framework
- Berne Convention
- TRIPS
- WIPO
- Software Directive
- Copyright, Designs and Patents Act 1988 (CDPA)
- Applicable legal principles
- Conclusions on ICA
- Section V - Alleged breaches of the ICA
- Disassembly, decompilation and translation
- Item 2: Load Module Decompiler (“the LMD”) (Paragraph 11.2 of the Technical Particulars)
- Item 3: CICS Control Blocks Document (Paragraph 11.3 of the Technical Particulars)
- Item 4: EXEC DLI (Paragraphs 27.18 & 28.19 of RRRAPOC)
- Item 5: IBM Binder Software (Paragraph 11.4 of the Technical Particulars)
- Compiler listings – summary of the dispute
- Item 6: IGZCIVL COBOL runtime module (Paragraph 11.6 of the Technical Particulars)
- Item 7: CICS Translators (Paragraph 20.1-2 of the Technical Particulars)
- Item 8: Floating point rounding rules (Paragraph 20.3 of the Technical Particulars)
- Item 9: IBM PL/1 compiler (Paragraph 20.4 of the Technical Particulars & Paragraph 27 of the POC)
- Item 10: XML Parse statements (Paragraphs 33-38 of the Technical Particulars)
- Item 11: COBOL initialisation, branching and I/O declaratives (Paragraphs 27.4&27.5 RRRAPOC)
- Item 12: PL/I Condition handling (Paragraphs 27.10-27.12 of RRRAPOC)
- Reverse engineering through the systematic use of traces, dumps, slip traps, packet sniffing and other debugging tools techniques – summary of the dispute
- Item 13: CICS-to-CICS communications (Paragraph 28.1 of the Technical Particulars)
- Item 14: AMBLIST analysis of CICS Stubs (Paragraph 28.2 of the Technical Particulars)
- Item 15: Colesoft z/XDC and COBOL initialisation (Paragraph 28.3 of the Technical Particulars)
- Item 16: XDC and IMS (Paragraph 28.4 of the Technical Particulars)
- Additional examples
- Item 17: SLIP Traps and CICS (Paragraph 28.5 of the Technical Particulars)
- Item 18: SLIP Traps and COBOL (Paragraph 28.6 of the Technical Particulars)
- Macros and Copybooks - introduction
- Macros (Paragraphs 32.1-32.9 of the Technical Particulars) – summary of the dispute
- Item 19: DR-3246 (Paragraph 32.1 of the Technical Particulars)
- Item 20: DR-10237 (Paragraph 32.2 of the Technical Particulars)
- Item 21: DR-2753 (Paragraph 32.3 of the Technical Particulars)
- Item 22: DR-2771 (Paragraph 32.4 of the Technical Particulars)
- Item 23: DR-2796 (Paragraph 32.5 of the Technical Particulars)
- Item 24: DR-3280 (Paragraph 32.6 of the Technical Particulars)
- Item 25: DR-4281 (Paragraph 32.7 of the Technical Particulars)
- Item 26: DR-4322 (Paragraph 32.8 of the Technical Particulars)
- Item 27: DR-0847 (Paragraph 32.9 of the Technical Particulars)
- Macros - discussion
- Copybooks (Paragraphs 2.1.1.3 and 32.10-32.12 of the Technical Particulars) – nature of the dispute
- Item 28: DR-715 (Paragraph 32.10 of the Technical Particulars)
- Item 29: DR-753 (Paragraph 32.11 of the Technical Particulars)
- Item 30: DR-756 (Paragraph 2.1.1.3 of the Technical Particulars)
- Copybooks - discussion
- Transferring “unscrubbed” materials
- Item 31:Epiphany
- Item 32: Db2 Catalog table metadata
- Item 33: DSS dump
- Item 34: Kednos
- Item 35: CSECTs deliberately omitted from scrubbing
- Items 36 and 42: Unscrubbed CSECTs
- Items 37 and 40: IMS PROCLIB & DLIBATCH
- Item 38: DFHEI1 module
- Item 39: IGZXANE
- Item 41: IGZXNE3N
- Item 43: CEEBETBL, CEEBLLST, IBMPINPL & CEESG*
- Item 44: DR-4617
- Item 45: DR-171
- Item 46: Scrubbing failures
- Item 47: @@TRGLOC CSECT
- Item 48: PARMLIB & PROCLIB
- Use outside Enterprise and beyond Designated Machine
- Item 49: Brad Taylor (Paragraph 44.2 of the Technical Particulars)
- Item 50: Winsopia Pizzabox (Paragraph 44.5 of the Technical Particulars)
- Item 51: Justin Bendich (Paragraph 44.6 of the Technical Particulars)
- Conclusions on technical breaches
- Section VI - Wrongful procurement of breach
- Applicable legal principles
- LzLabs
- LzLabs UK
- Claims against the directors
- Mr Moores
- Summary on unlawful procurement
- Section VII - Unlawful means conspiracy
- Applicable legal principles
- Knowledge of unlawfulness
- Summary on unlawful means conspiracy
- Section VIII – Audit and Termination
- Validity of audit request
- Validity of termination
- Section IX - Limitation
- Contractual limitation
- Statutory Limitation
- Deliberate concealment
- Finding - section 32(1)(b)
- Finding - Section 32(2)
- Actual or constructive knowledge – legal principles
- Date of knowledge issues
- ICA 2013
- Mr Knight - 2017
- Mr Anzani - 2018
- Conclusions
![HT-2021-000363 - [2025] EWHC 532 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)