Section IX - Limitation
Section IX - Limitation
The material dates are as follows:
Winsopia and IBM entered into the ICA on 15 August 2013.
The SDM was marketed from March 2016.
The technical breaches span the period August 2013 through to September 2021.
IBM terminated the ICA and associated agreements by letter dated 24 February 2021.
These proceedings were started on 21 September 2021 against LzLabs, Winsopia, LzLabs UK, Mr Cresswell and Mr Rockmann in respect of the ICA breaches and unlawful procurement of breach claims (“the Original Claims”).
The unlawful means conspiracy claim against all defendants and the unlawful procurement of breach claim against Mr Moores (“the New Claims”) were made on 29 November 2023. Those amendments were made on the basis that IBM would not seek to rely on the ‘relation-back’ rule and limited its claims to those that were not time-barred as at 29 November 2023.
The defendants’ pleaded case raises the following issues of limitation:
Clause 1.11.4 of the ICA provides for a two-year contractual limitation period, said to be enforceable by Winsopia to bar all (or most) claims against it and the other defendants.
The Original Claims in both contract and tort are said to relate to causes of action accruing prior to 21 September 2015 and, therefore, are statute-barred by reason of sections 5 and 2 of the Limitation Act 1980.
The New Claims in tort are said to relate to causes of action accruing prior to 29 November 2017 and, therefore, are statute-barred by reason of section 2 of the Limitation Act 1980.
IBM disputes that the claims are time-barred and raises a plea of deliberate or dishonest concealment:
It is said that on a proper construction of clause 1.11.4 of the ICA, it applies only to the parties who entered into it, namely, IBM and Winsopia; and/or it does not apply in respect of claims where the relevant cause of action involves dishonest or deliberate concealment.
It is alleged that acts by the defendants constituted deliberate concealment within the meaning of section 32 of the Limitation Act 1980.
IBM’s case is that it did not discover, and could not with reasonable diligence have discovered, the concealment prior to 25 August 2020, less than two years prior to the issue of proceedings in respect of the Original Claims and less than six years prior to the New Claims.
- Heading
- Mrs Justice O’Farrell
- Section II - Background to the dispute
- The SDM
- Hercules
- Neon litigation
- Formation of LzLabs and Winsopia
- The ICA
- SDM development and the clean room procedures
- Launch of the SDM
- Project Eiger
- Further development of the SDM
- Audit request and termination
- Section III - The proceedings
- The Issues
- The factual witnesses
- Section IV - Construction of the ICA
- Approach to construction of the ICA
- Scope of licence
- The ICA Programs
- Customer applications
- Licensed Program Specifications
- Independent software vendors (ISVs)
- Debugging tools
- Restrictions on use of ICA Programs
- Legislative framework
- Berne Convention
- TRIPS
- WIPO
- Software Directive
- Copyright, Designs and Patents Act 1988 (CDPA)
- Applicable legal principles
- Conclusions on ICA
- Section V - Alleged breaches of the ICA
- Disassembly, decompilation and translation
- Item 2: Load Module Decompiler (“the LMD”) (Paragraph 11.2 of the Technical Particulars)
- Item 3: CICS Control Blocks Document (Paragraph 11.3 of the Technical Particulars)
- Item 4: EXEC DLI (Paragraphs 27.18 & 28.19 of RRRAPOC)
- Item 5: IBM Binder Software (Paragraph 11.4 of the Technical Particulars)
- Compiler listings – summary of the dispute
- Item 6: IGZCIVL COBOL runtime module (Paragraph 11.6 of the Technical Particulars)
- Item 7: CICS Translators (Paragraph 20.1-2 of the Technical Particulars)
- Item 8: Floating point rounding rules (Paragraph 20.3 of the Technical Particulars)
- Item 9: IBM PL/1 compiler (Paragraph 20.4 of the Technical Particulars & Paragraph 27 of the POC)
- Item 10: XML Parse statements (Paragraphs 33-38 of the Technical Particulars)
- Item 11: COBOL initialisation, branching and I/O declaratives (Paragraphs 27.4&27.5 RRRAPOC)
- Item 12: PL/I Condition handling (Paragraphs 27.10-27.12 of RRRAPOC)
- Reverse engineering through the systematic use of traces, dumps, slip traps, packet sniffing and other debugging tools techniques – summary of the dispute
- Item 13: CICS-to-CICS communications (Paragraph 28.1 of the Technical Particulars)
- Item 14: AMBLIST analysis of CICS Stubs (Paragraph 28.2 of the Technical Particulars)
- Item 15: Colesoft z/XDC and COBOL initialisation (Paragraph 28.3 of the Technical Particulars)
- Item 16: XDC and IMS (Paragraph 28.4 of the Technical Particulars)
- Additional examples
- Item 17: SLIP Traps and CICS (Paragraph 28.5 of the Technical Particulars)
- Item 18: SLIP Traps and COBOL (Paragraph 28.6 of the Technical Particulars)
- Macros and Copybooks - introduction
- Macros (Paragraphs 32.1-32.9 of the Technical Particulars) – summary of the dispute
- Item 19: DR-3246 (Paragraph 32.1 of the Technical Particulars)
- Item 20: DR-10237 (Paragraph 32.2 of the Technical Particulars)
- Item 21: DR-2753 (Paragraph 32.3 of the Technical Particulars)
- Item 22: DR-2771 (Paragraph 32.4 of the Technical Particulars)
- Item 23: DR-2796 (Paragraph 32.5 of the Technical Particulars)
- Item 24: DR-3280 (Paragraph 32.6 of the Technical Particulars)
- Item 25: DR-4281 (Paragraph 32.7 of the Technical Particulars)
- Item 26: DR-4322 (Paragraph 32.8 of the Technical Particulars)
- Item 27: DR-0847 (Paragraph 32.9 of the Technical Particulars)
- Macros - discussion
- Copybooks (Paragraphs 2.1.1.3 and 32.10-32.12 of the Technical Particulars) – nature of the dispute
- Item 28: DR-715 (Paragraph 32.10 of the Technical Particulars)
- Item 29: DR-753 (Paragraph 32.11 of the Technical Particulars)
- Item 30: DR-756 (Paragraph 2.1.1.3 of the Technical Particulars)
- Copybooks - discussion
- Transferring “unscrubbed” materials
- Item 31:Epiphany
- Item 32: Db2 Catalog table metadata
- Item 33: DSS dump
- Item 34: Kednos
- Item 35: CSECTs deliberately omitted from scrubbing
- Items 36 and 42: Unscrubbed CSECTs
- Items 37 and 40: IMS PROCLIB & DLIBATCH
- Item 38: DFHEI1 module
- Item 39: IGZXANE
- Item 41: IGZXNE3N
- Item 43: CEEBETBL, CEEBLLST, IBMPINPL & CEESG*
- Item 44: DR-4617
- Item 45: DR-171
- Item 46: Scrubbing failures
- Item 47: @@TRGLOC CSECT
- Item 48: PARMLIB & PROCLIB
- Use outside Enterprise and beyond Designated Machine
- Item 49: Brad Taylor (Paragraph 44.2 of the Technical Particulars)
- Item 50: Winsopia Pizzabox (Paragraph 44.5 of the Technical Particulars)
- Item 51: Justin Bendich (Paragraph 44.6 of the Technical Particulars)
- Conclusions on technical breaches
- Section VI - Wrongful procurement of breach
- Applicable legal principles
- LzLabs
- LzLabs UK
- Claims against the directors
- Mr Moores
- Summary on unlawful procurement
- Section VII - Unlawful means conspiracy
- Applicable legal principles
- Knowledge of unlawfulness
- Summary on unlawful means conspiracy
- Section VIII – Audit and Termination
- Validity of audit request
- Validity of termination
- Section IX - Limitation
- Contractual limitation
- Statutory Limitation
- Deliberate concealment
- Finding - section 32(1)(b)
- Finding - Section 32(2)
- Actual or constructive knowledge – legal principles
- Date of knowledge issues
- ICA 2013
- Mr Knight - 2017
- Mr Anzani - 2018
- Conclusions
![HT-2021-000363 - [2025] EWHC 532 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)