HT-2025-000036 - [2025] EWHC 2707 (TCC)
Technology and Construction Court

HT-2025-000036 - [2025] EWHC 2707 (TCC)

Fecha: 21-Oct-2025

110APayment notices: contractual requirements

110APayment notices: contractual requirements

(1)A construction contract shall, in relation to every payment provided for by the contract—

(a)require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or

(b)require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.

(2)A notice complies with this subsection if it specifies—

(a)in a case where the notice is given by the payer—

(i)the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and

(ii)the basis on which that sum is calculated;

(b)in a case where the notice is given by a specified person—

(i)the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and

(ii)the basis on which that sum is calculated.

(3)A notice complies with this subsection if it specifies—

(a)the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and

(b)the basis on which that sum is calculated…

110BPayment notices: payee's notice in default of payer's notice