HT-2025-000036 - [2025] EWHC 2707 (TCC)
Technology and Construction Court

HT-2025-000036 - [2025] EWHC 2707 (TCC)

Fecha: 21-Oct-2025

If— (a)the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person o

(4)

If—

(a)the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person of—

(i)the sum that the payee considers will become due on the payment due date in respect of the payment, and

(ii)the basis on which that sum is calculated, and

(b)

the payee gives such notification in accordance with the contract,