D. The Interim Valuation Date
D. The Interim Valuation Date
As finally formulated by reamendment, this contention was put as follows:
“10A. The 2022-23 Payments Schedule:
(a) Was an instruction given by VCL under, and not a variation to the Subcontract.
(b) Had therefore to be read subject to the Subcontract, and in particular subject to clause 4 of the Subcontract.
(c) Did not set out a clear and transparent regime setting out what sums became due and when for the purposes of clause 4 of the Subcontract. In particular, the 2022-23 Payments Schedule did not set out any (alternatively any clear and unambiguous) Interim Valuation Dates for the purposes of continuing the interim payment regime beyond the dates set out in Numbered Document 6 to the Subcontract, meaning that the Scheme for Construction Contracts (England & Wales) Regulations 1998 (SI 649/1998) applied to fix the relevant (valuation) periods instead. That in turn meant that (so long as the 2022-23 Payments Schedule applied) there was no relevant right under the Subcontract to submit a contractually-compliant application pursuant to clause 4.6.3.1 as had otherwise been the case;
(d) Alternatively, contemplated Gypcraft’s interim payment applications were to be submitted on the interim valuation date, and not 4 days in advance of it, meaning that any applications submitted in accordance with the 2022-23 Payments Schedule would not be submitted in accordance with the Subcontract;
(e) Therefore on either basis the Subcontract at all material times (whether as amended, varied or supplemented by the 2022-23 Schedule) was not (or was no longer) a contract which required or permitted Gypcraft to submit an application within the meaning of s110B (4) of the Housing Grants, Construction & Regeneration Act 1996.”
As an initial observation, this argument is very technical and would have the practical result that the payment regime cannot work as, broadly speaking, the Act and the Sub-Contract intended. That does not necessarily mean that the argument is wrong, but the Court is, in my view, entitled to approach this part of the case with some scepticism. As Coulson LJ observed in Bennett Construction Ltd. v CIMC MBS Ltd. [2019] BLR 587 at [42]:
“the courts expect the parties to adopt business common sense as to the arrangements for invoicing and payment.”
What this argument really amounts to is the contention that it was not possible, reading together clause 4 and the 2022/3 and subsequent Schedules, for Gypcraft to give “such notification in accordance with the contract” as contemplated by section 110B(4)(b) of the Act.
I do not agree.
As to the first way of putting the case – that the Payments Schedule did not set out any (alternatively any clear and unambiguous) Interim Valuation Dates – this seems to me to be an impossible reading of the Schedule. In relation to the application with which the Adjudicator was concerned, the Schedule stated in terms that:
Sub-Contractor Submission Valuation Date was 16th January;
DUE date was 28th January;
Accounts to issue Payment Notice by 2nd February;
Payless Notice to be issued by 16th February;
Final date for Payment was 17th February.
(all dates in 2023)
This was clearly and methodically giving effect to the dates and regime contemplated by clause 4. It would be perverse and uncommercial to hold that the regime could not work as intended because the words “Sub-Contractor Submission Valuation Date” were used rather than “Interim Valuation Date”. Furthermore, it is clear from footnote 4 the expression “Sub-Contractor Submission Valuation Date” does not refer to Applications for Payments, but to the valuation of those applications.
The second way this case is put – that interim payment applications were to be submitted on the interim valuation date, and not 4 days in advance of it, so that they would not be submitted in accordance with the Subcontract – fails for a number of reasons:
Note 4 does not say that Applications for Payment were to be issued on the Valuation Date but “by end of business on the Valuation date above”. Reading this provision with clause 4.6.3.1, as one should, the Sub-Contractor would have to comply with both obligations: a compliant Payment Application submitted 4 days prior to the Interim Valuation Date would also comply with the Schedule;
Further or alternatively, the Payments Schedule was either a contractual document or an instruction/direction given under the Sub-Contract. Under clause 3.4 of the Sub-Contract, VCL were empowered to issue directions and by clause 3.5 Gypcraft were obliged to comply therewith. It would be a strange result if Gypcraft, acting in compliance with what the Adjudicator held to be “an instruction and/or direction” issued by VCL were not, in making payment applications as required, acting “in accordance with the contract”. (Footnote: 1)
For these reasons, I reject the Interim Valuation date argument.
- Heading
- Adrian Williamson KC
- The Subcontract fails to adequately identify a relevant “Interim Valuation Date” for Payment Cycle #23, meaning that clause 4 must be substantially re-written by Part II of the Scheme. The necessary m
- There was a course of conduct between the parties under which a convention arose that Gypcraft would accept VCL’s Payment Notice #23 out of time. This involves looking how the parties treated the othe
- Lastly, if VCL’s Payment Notice #23 was out of time to serve as a payment notice, it was (indisputably) nevertheless in time to serve as a Pay Less Notice. It contained all the relevant information to
- 110APayment notices: contractual requirements
- This section applies in a case where, in relation to any payment provided for by a construction contract— (a)the contract requires the payer or a specified person to give the payee a notice complying with section 110 A (2) not later than five days af
- Subject to subsection (4), the payee may give to the payer a notice complying with section 110 A (3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the
- Where pursuant to subsection (2) the payee gives a notice complying with section 110 A (3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postpone
- If— (a)the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person o
- that notification is to be regarded as a notice complying with section 110A (3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection)”
- B. Procedural matters
- The relevant facts
- D. The Interim Valuation Date
- E. Estoppel
- F. Payment Notices and Pay Less Notices
- Conclusions
![HT-2025-000036 - [2025] EWHC 2707 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)