Lastly, if VCL’s Payment Notice #23 was out of time to serve as a payment notice, it was (indisputably) nevertheless in time to serve as a Pay Less Notice. It contained all the relevant information to
Lastly, if VCL’s Payment Notice #23 was out of time to serve as a payment notice, it was (indisputably) nevertheless in time to serve as a Pay Less Notice. It contained all the relevant information to communicate to Gypcraft that VCL intended to pay less than the amount applied for, with a breakdown of why that was. That being all the Subcontract and the HGCRA96 requires, there is no reason not to read the Payment Notice as a Pay Less Notice. Again, this is a pure point of construction on the documents.
I deal with the issues as follows:
The contractual and statutory background;
Procedural matters;
The relevant facts;
The Interim Valuation Date;
Estoppel;
Payment Notices and Pay Less Notices;
Conclusions.
The contractual and statutory background
The parties entered into the Subcontract dated 12 November 2020. This wasexecuted by Gypcraft on 28 June 2021.The Subcontract incorporated, amongst other things, the JCT DBSub/C 2016 standard form.
The Subcontract also incorporated “Numbered Document 6”. Numbered Document 6 set out agreed interim payment dates necessary to make clause 4’s interim payment regime work. However, Numbered Document 6 only covered an 11 month period from 3 April 2020 – 2 February 2021. Since Gypcraft’s works on site were agreed to start no earlier than 1 December 2020 and no later than 31 January 2021, Numbered Document 6 was virtually redundant as at the date of the Subcontract.
VCL therefore issued to Gypcraft a series of updated schedules, with further dates as the works progressed. The relevant Schedules, with fresh dates covering subsequent periods, were:
The 2021/22 Schedule;
The 2022/23 Schedule;
The 2023/24 Schedule.
The Schedules were all in similar terms. They contained, for each payment cycle, columns giving dates for:
Sub-Contractor Submission Valuation Date;
DUE date (sic) ;
Accounts to issue Payment Notice by;
Payless Notice to be issued by;
Final date for Payment.
Footnote 4 stated that “all Applications for Payments and Invoices are to be issued to [email address] by end of business on the Valuation date above”.
The JCT Standard Form set out the following relevant terms:
Clause 4.6.1 provided that the monthly due dates for interim payments were to be 21 days “after the relevant Interim Valuation Date”;
Clause 4.6.3 stated that “… the Sub-Contractor may make a Payment Application in respect of an interim payment to the Contractor…not later than 4 days prior to theInterim Valuation Date”;
Clause 4.7.1, as amended, set the final date for payment as 21 days after the due date;
Clause 4.7.2 required that “Not later than 5 days after the due date in each case the Contractor shall give a notice to the Sub-Contractor which shall specify the sum that he considers to be or have been due at the due date and then basis on which that sum has been calculated (a ‘Payment Notice’) ...”
Clause 4.7.3 provided that “Subject to any Pay Less Notice given by the paying party under clause 4.7.5, the paying Party shall pay the sum specified in the Payment Notice…on or before the final date for payment. If the Contractor fails to give a Payment Notice…in accordance with clause 4.7.2, but a Payment Application has been or is then made, the Contractor shall, subject to any Pay Less Notice given under clause 4.7.5, pay the sum specified in the Payment Application”;
Clause 4.7.5.1 stated that “Where the Contractor intends to pay less than the sums stated in the Payment Notice…. the Party by whom the payment is stated to be payable shall not later than 1 day before its final date for payment give the other Party notice of that intention in accordance with clause 4.7.6 (a ‘Pay Less Notice’). Where a Pay Less Notice is given, the payment to be made on or before the final date for payment shall not be less than the amount stated in it as due.”
Clause 4.7.6 provided that “A Pay Less Notice given by either Party shall specify the sum he considers to be due to the other Party at the date the notice is given and the basis on which that sum has been calculated.”
The above regime, which is intended to give effect to the Act, was accurately expressed pictorially by Mr Bowling in his skeleton argument as follows, using 5th January as an example:
-4d: IPA | IVD | +12d: DD | +5d: PN | +15d: PLN | +1: FDFP |
1 Jan | 5 Jan | 17 Jan | 22 Jan | 6 Feb | 7 Feb |
21d | |||||
The Act contains the following relevant provisions:
- Heading
- Adrian Williamson KC
- The Subcontract fails to adequately identify a relevant “Interim Valuation Date” for Payment Cycle #23, meaning that clause 4 must be substantially re-written by Part II of the Scheme. The necessary m
- There was a course of conduct between the parties under which a convention arose that Gypcraft would accept VCL’s Payment Notice #23 out of time. This involves looking how the parties treated the othe
- Lastly, if VCL’s Payment Notice #23 was out of time to serve as a payment notice, it was (indisputably) nevertheless in time to serve as a Pay Less Notice. It contained all the relevant information to
- 110APayment notices: contractual requirements
- This section applies in a case where, in relation to any payment provided for by a construction contract— (a)the contract requires the payer or a specified person to give the payee a notice complying with section 110 A (2) not later than five days af
- Subject to subsection (4), the payee may give to the payer a notice complying with section 110 A (3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the
- Where pursuant to subsection (2) the payee gives a notice complying with section 110 A (3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postpone
- If— (a)the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person o
- that notification is to be regarded as a notice complying with section 110A (3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection)”
- B. Procedural matters
- The relevant facts
- D. The Interim Valuation Date
- E. Estoppel
- F. Payment Notices and Pay Less Notices
- Conclusions
![HT-2025-000036 - [2025] EWHC 2707 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)