HT-2025-000036 - [2025] EWHC 2707 (TCC)
Technology and Construction Court

HT-2025-000036 - [2025] EWHC 2707 (TCC)

Fecha: 21-Oct-2025

The relevant facts

C. The relevant facts

17.

On 14th September 2022, Gypcraft issued payment application 20 seeking payment of circa £90,000. This sum was arrived at by putting forward a “net valuation” of circa £2m and deducting “previous net payments” of £1.912m. On 6th October 2022, VCL issued a Payment Notice showing a sum due of only about £32,000. This document described the sum of £1.912m as “amount previously due”.

18.

A similar pattern obtained for applications 21 and 22 in October and November 2022. None of the Payment Notices were issued in accordance with the contractual timetable described above.

19.

On 16 January 2023, Gypcraft issued its interim application for payment no. 23. In Application 23, Gypcraft sought payment of the sum of £342,385.52.

20.

On 7 February 2023, VCL purported to issue a payment notice stating that the sum due to Gypcraft was £125,437.77. VCL paid that sum.

21.

The 7 February Document, called in the covering email a “Payment Notice” and stated on its face to be a “Payment Notice”, was not issued on time. It was issued 5 days after the payment notice date. VCL did not serve a separate payless notice.

22.

In October 2024, Gypcraft started an adjudication seeking, as its primary position, the outstanding sum under Application 23 (£216,947.75) as a notified sum.

23.

The Adjudicator found inter alia that:

i)

The 7 February Document was invalid.

ii)

Gypcraft was, therefore, entitled to the outstanding sum of £216,947.75 as a notified sum for Application 23.

iii)

Gypcraft was entitled to interest up to the date of his Decision of £26,045.76 (£24,339.75 + £1,706.01) and continuing at a daily rate of £41.61.