F. Payment Notices and Pay Less Notices
F. Payment Notices and Pay Less Notices
VCL submit on this aspect that the document which they issued on 7th February 2023 in response to application 23 was in fact a Pay Less Notice such that, in accordance with clause 4.7.5.1, the payment to be made on or before the final date for payment would not be less than the amount stated in it as due.
This is an ambitious submission. The covering email referred in the subject box, in two places, to “PN 23”. The body of the email twice referenced the provision of a “Payment Notice”. The attached document was headed “Payment Notice” and stated that “the basis on which the sum stated in this Payment Notice has been calculated is set out in the attached breakdown”.
Applying the helpful summary of the approach to contractual notices set out at para 47 of Advance JV v Enisca Ltd [2022] EWHC 1152 (TCC), 202 Con. L.R. 219, I have no doubt that this document was what it said it was: a Payment Notice. Any other reading of the document would be entirely artificial.
Furthermore, it would, in my view, entirely undermine the Act and the Sub-Contract if what the parties clearly intended at the time to be a Payment Notice could somehow retrospectively be converted into a Pay Less Notice. As Coulson J (as he then was) observed in Grove Developments Limited v S&T (UK) Limited [2018] BLR 173 at [29]:
“In my view, that general guidance applies equally to a payment notice and a pay less notice. Each has to make plain that it is, respectively, a payment notice or a pay less notice. Each has to clearly set out the sum which is said to be due and/or to be deducted, and the basis on which that sum is calculated. Beyond that, the question of whether or not it is a valid notice in accordance with the contract is a matter of fact and degree.”
- Heading
- Adrian Williamson KC
- The Subcontract fails to adequately identify a relevant “Interim Valuation Date” for Payment Cycle #23, meaning that clause 4 must be substantially re-written by Part II of the Scheme. The necessary m
- There was a course of conduct between the parties under which a convention arose that Gypcraft would accept VCL’s Payment Notice #23 out of time. This involves looking how the parties treated the othe
- Lastly, if VCL’s Payment Notice #23 was out of time to serve as a payment notice, it was (indisputably) nevertheless in time to serve as a Pay Less Notice. It contained all the relevant information to
- 110APayment notices: contractual requirements
- This section applies in a case where, in relation to any payment provided for by a construction contract— (a)the contract requires the payer or a specified person to give the payee a notice complying with section 110 A (2) not later than five days af
- Subject to subsection (4), the payee may give to the payer a notice complying with section 110 A (3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the
- Where pursuant to subsection (2) the payee gives a notice complying with section 110 A (3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postpone
- If— (a)the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person o
- that notification is to be regarded as a notice complying with section 110A (3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection)”
- B. Procedural matters
- The relevant facts
- D. The Interim Valuation Date
- E. Estoppel
- F. Payment Notices and Pay Less Notices
- Conclusions
![HT-2025-000036 - [2025] EWHC 2707 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)