HT-2025-000036 - [2025] EWHC 2707 (TCC)
Technology and Construction Court

HT-2025-000036 - [2025] EWHC 2707 (TCC)

Fecha: 21-Oct-2025

Adrian Williamson KC

Adrian Williamson KC:

Introduction

1.

In these Part 8 proceedings, VCL seek declarations in relation to the proper construction of a contract payment mechanism used by the parties under their subcontract dated 12 November 2020 (“the Subcontract”). Gypcraft resist the grant of these declarations.

2.

These issues arise as follows:

i)

Gypcraft succeeded before an Adjudicator in relation to the proper analysis of Payment Cycle 23 between the parties, which took place over January and February 2023;

ii)

By a Decision made on 12 November 2024, the Adjudicator decided that VCL should to pay Gypcraft £216,947.75 plus interest on the basis that: (a) Gypcraft had served a valid Interim Payment Application 23; (b) VCL had failed to serve either a Payment Notice or a Pay Less Notice in response as required; and (c) therefore Gypcraft’ s Interim Payment Application 23 was payable in the amount applied for, in accordance with section 110B(4) of the Housing Grants, Construction & Regeneration Act 1996 (“ the Act”);

iii)

VCL have paid these sums but contend that the declarations sought, or any of them, will invalidate the Decision, so that this sum will fall to be repaid.

3.

VCL’s case is summarised as follows in Mr Bowling’s skeleton argument: