HT-2025-000036 - [2025] EWHC 2707 (TCC)
Technology and Construction Court

HT-2025-000036 - [2025] EWHC 2707 (TCC)

Fecha: 21-Oct-2025

Where pursuant to subsection (2) the payee gives a notice complying with section 110 A (3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postpone

(3)

Where pursuant to subsection (2) the payee gives a notice complying with section 110A (3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given.