Findings of fact
Findings of fact
We have already found the following facts:
On 12 July 2018, the Bank issued its half year update, which included a statement that its Pillar 2A requirement of 1.7% was “currently under review with the PRA” and the Bank “anticipated receiving capital relief from the PRA as part of the Pillar 2A Offset”.
On 10 September 2018, the Bank received the PSM letter, which stated that the PRA was “somewhat frustrated” that the Bank had referred publicly to the discussions on the Pillar 2A offset and said “we would not wish to see a repeat” of this type of public disclosure, see §132.
The PSM letter also said that, as the Bank was remediating the classification of commercial risk weights, and this “will likely increase the Pillar 1 risk weighted assets”, the PRA was “uncertain about the materiality of any prospective adjustment to [the Bank’s] capital position”. It continued:
“Until this matter is satisfactorily resolved, and we have received reassurance that Metro is holding sufficient Pillar 1 capital against its commercial assets, we will not apply Policy Statement 22/17 which allows the offsetting of certain Pillar 2a variable add-ons.”.
At the meeting with the PRA on 12 September 2018, Mr Salmon agreed to a discussion about the offset once the mistake had been corrected, noting that the PRA would need to understand how the mistake had occurred and to be assured there was no read-across to other reporting aspects, see §137.
In the October 2018 Board meeting, the Bank noted and took as read the 2019 budget estimate, which had included the benefit of the Pillar 2A offset of £50m as being actioned “by the end of Q1 2019”, see §223.
On 8 January 2019, Ms Gillan emailed the PRA to arrange a meeting to discuss the outcomes of the Deloitte work on the RWA issue, and added “we hope this will then allow us to revisit earlier conversations with Supervision about application of the Pillar 2A off-set approach”, see §250.
Mr Arden accepted in cross-examination that he “didn’t believe at any stage that there was a promise” by the PRA that once the RWA issue had been remediated, the Bank would allow a Pillar 2A offset, and he also said that it “was not going to be on the table until [the Bank] had got the RWAs right”. Mr Donaldson similarly accepted that discussions about the Pillar 2A offset could not begin until after the remediation of the RWAs.
On the basis of all the above, we find as further facts that:
the PRA did not promise that the Bank would obtain the Pillar 2A offset; and
the PRA would not consider whether or not to allow the offset until after the RWA issue had been remediated.
In relation to quantum, Mr Donaldson said in his witness statement that if the Bank had obtained the offset, it “would have reduced its overall capital by over £100 million; a reduction of an equivalent of well over £1 billion of RWAs”. However, under cross- examination he was unable to explain the basis for that figure. In re-examination, his attention was drawn to the £50m in the 2019 Budget paper, and asked whether this helped him with the value of the proposed Pillar 2A offset. He responded:
“I think, therefore , it is the 100 plus million that we had in the work that we had done, and it must be offsetting the overs and unders with the worst case that we considered we would get post the Deloitte work”
We understand him to mean that he thought the £50m in the 2019 Budget paper was a net figure after the RWA capital adjustment of some £40-50m had been deducted from his £100m estimate. However, that is not what the paper says. We prefer to rely on the contemporaneous evidence, and find as a fact that at the relevant time, the Bank’s estimate of the effect of a Pillar 2A adjustment was £50m.
- Heading
- Introduction
- The jurisdiction of the Tribunal
- The burden and standard of proof
- The PRA and capital requirements
- The Bank’s lending
- CRE loans
- CLIP loans
- PBTL loans
- COREP reporting
- The Authority
- Listing Rule 1.3.3R
- The MAR
- The evidence
- Approach to the evidence
- Mr Arden
- Mr Donaldson
- Ms Gillan
- Ms Roberts
- Mr Somers and Mr Dransfield
- Mr Sutherland
- Mr Lane
- Mr Brierley
- Individuals who were not called as witnesses
- Findings of fact
- The early years
- Linklaters
- Key personnel during the period from March 2018
- Relationship with the PRA and the Authority
- 2016 and 2017
- The COREP audit and the CRE loans
- Mr Arden, the Board and the committees
- KPMG appointed
- April to June 2018
- July 2018
- The 2018 capital raise and half year results
- August 2018: PBTL and CLIP
- Communicating with the PRA
- KPMG decision trees
- PBTL classification
- Annual Review of Commercial Lending
- September Audit Committee
- September NEDs meeting
- September Board meeting
- Engagement of Deloitte
- Internal work in support
- Communications with the PRA
- Meeting with Linklaters
- Disclosure Committee meeting
- Mr Somers’ email
- Meetings with Mr Hill and Mr Bernau
- The October CRPAC meeting
- RWA Report
- Business and Commercial Lending
- The October Audit Committee meeting
- The Q3 Update
- Accounting, reporting and control report
- The October ROC meeting
- Chief Risk Officer’s Report
- The RWA Report
- Business and Commercial Lending Review
- The October Board meeting
- Linklaters Governance Update
- Audit Committee Update
- The Q3 Update
- 2019 Budget Paper
- Whether the RWA issue was discussed
- Chief Risk Officer’s Report
- Response to PSM Letter
- The Q3 Update and analyst calls
- Deloitte’s reports
- Discussions with Linklaters
- Discussions with the PRA and the January announcement
- Subsequently
- The PRA
- The Authority
- Mr Donaldson’s and Mr Arden’s careers
- The common ground
- The Parties’ cases
- The Authority’s case
- The Applicants’ case
- ISSUE ONE: WHETHER THE BANK BREACHED LR 1.3.3R
- The PRA and the COREP Returns
- Findings of fact
- The Applicants’ position
- The Tribunal’s view
- The PRA and confidentiality
- Findings of fact
- The Applicants’ position
- The Authority’s position
- The Tribunal’s view
- Mr Lane’s advice
- Findings of fact not in dispute
- Who was at the meeting
- How long was the meeting
- Linklaters’ practice when giving advice
- Knowledge of the impending Q3 Update
- What was said by Mr Arden at the meeting
- Confidential matter?
- The Tribunal’s finding
- The purpose of the meeting
- Reasonable to rely?
- Overall conclusion on legal advice
- No breach if uncertain and under investigation?
- Mr Jaffey’s submissions
- Mr Stanley’s submissions
- The Tribunal’s view
- No material breach if unknown
- The knowledge issue
- Key findings already made
- The Authority’s overall position on the knowledge issue
- The Applicants’ overall position on the knowledge issue
- Rules on classification
- Data issues
- Nature of the data issues
- Extent of the data issues
- Effect on materiality
- SME supporting factor
- Residential property
- Conclusion on data issues
- The mitigants overall
- The AIRB application
- Pillar 2A Offset
- Submissions
- Findings of fact
- Conclusion on Pillar 2A offset
- Phasing in
- PRA discretion
- Taking all the above into account
- Overall conclusion on the Knowledge Issue
- The PBTL Loans
- Findings of fact
- Submissions and the Tribunal’s view
- Whether the alternatives were unreasonable
- The Applicants’ position
- The Authority’s submissions
- The Tribunal’s view
- Reliance on the board and the Committees
- Findings of fact
- September
- October Audit Committee
- October ROC meeting
- October Board meeting
- The position of the parties
- The Tribunal’s view
- The Audit Committee
- The Board
- Reliance on Ms James
- Findings of fact
- Submissions
- Discussion
- Overall conclusion on Issue one
- The legal principles
- The statutory provisions
- Burton v Bevan
- Scandex
- Capital Alternatives
- Avacade
- Ferreira
- Submissions on Ferreira
- The words of the provision
- The ratio of Ferreira
- The corporate veil
- Forster: meaning of “knowingly concerned”
- Forster: reliance on legal advice
- The Applicants’ submissions
- The Authority’s submissions
- The Tribunal’s view
- The principles summarised and the issues remaining
- Mr Arden
- Mr Donaldson
- The position of the parties
- The Tribunal’s view
- ISSUE THREE: PENALTIES
- The Tribunal’s approach
- The DEPP
- The Authority’s position
- The Applicants’ position
- The Tribunal’s view
- The penalty framework
- Applying the Steps
- Step 2(1)-(3): Earnings
- The Tribunal’s view
- Step 2(4)-(7): Seriousness
- Step 3: Mitigation
- DEPP
- Submissions and discussion
- Co-operation
- Remediation
- Compliance with the PRA’s requirements
- Communications with the Authority
- No negative factors
- Other consequences
- Difference between the Applicants?
- Conclusions
![[2025] UKUT 00185 (TCC)](https://backend.juristeca.com/files/emisores/logo_ICfrj4g.png)