What was said by Mr Arden at the meeting
What was said by Mr Arden at the meeting
As set out at §§297-300, we have already found that Mr Lane was told by Mr Arden:
there were “regulatory interpretation issues” about the classification;
this had been raised as a “potential issue” by the PRA;
the estimate of £600m was based on sampling; and
the PRA had agreed that no immediate changes were necessary.
However, none of those statements was true at the time they were made. In addition:
Mr Arden told Mr Lane that the Bank was “potentially having to re-weight the CRE loan portfolio”, when the Bank had told the PRA that it was remediating the issue so as to use the correct 100% risk weighting for the CLIP loans; and
Ms Roberts’s email twice refers to the existence of an “ongoing dialogue” with the PRA about the issue, when there was no dialogue: instead, the Bank had simply told the PRA that it was remediating the issue. We make the reasonable inference from the duplicate mention in Ms Roberts’s email that Mr Arden also told Mr Lane that there was an ongoing dialogue.
Ms Roberts also recorded that Mr Arden had told Mr Lane that the Bank had “a problem with the risk weight classification of some commercial assets”, and Mr Lane recalls that Mr Arden “explained the general nature of the issues”. When Mr Arden was asked in cross-examination whether he had also told Mr Lane that it was certain that an adjustment would be required, he repeatedly said “I don’t recall”; he would only confirm that he had talked about “the regulation interpretation issues and the data quality issues”. We make the reasonable inference that Mr Arden did not tell Mr Lane that the Bank had misapplied the rules requiring that the CLIP loans be risk weighted at 100% and that in consequence an adjustment would be required.
Mr Lane’s evidence was that:
“The impression I received from David Arden was that there was a high level of uncertainty regarding whether an adjustment would be required. Also, if there was to be an adjustment, the amount could be highly variable due to underlying data and regulatory interpretation issues. Further work was needed to be done with Deloitte along with further interactions with the PRA.”
He also said that:
“David Arden indicated that he didn’t feel that the issue would necessarily be material in terms of impacting Metro Bank’s growth ambitions and future financial performance. He indicated he thought that even in a worst-case outcome Metro Bank would remain well capitalised, in excess of its minimum regulatory capital requirements.”
Mr Arden responded to this evidence in his second witness statement, saying:
“I stated that I did not believe the RWA issue would be material in the context of the Bank's future strategy…However, I did not think the RWA issue was an irrelevant issue for the Bank…If I thought it was immaterial I would not have sought the advice of Linklaters.”
Mr Arden thus confirmed Mr Lane’s recollection that he had said the RWA adjustment would not be material. He did not deny that he had told Mr Lane that “further work was needed to be done with Deloitte along with further interactions with the PRA” before the Bank could know the position.
We find as a fact that as the result of the information provided by Mr Arden in the course of the meeting, Mr Lane had the incorrect impression that:
there was a high level of uncertainty as to whether an adjustment would be required;
if there was to be an adjustment, the amount could be highly variable;
this was due to underlying data and regulatory interpretation issues;
even in the worst case the outcome was not necessarily material; and
the position would not be clear until Deloitte had done further work and there had been further interactions with the PRA.
- Heading
- Introduction
- The jurisdiction of the Tribunal
- The burden and standard of proof
- The PRA and capital requirements
- The Bank’s lending
- CRE loans
- CLIP loans
- PBTL loans
- COREP reporting
- The Authority
- Listing Rule 1.3.3R
- The MAR
- The evidence
- Approach to the evidence
- Mr Arden
- Mr Donaldson
- Ms Gillan
- Ms Roberts
- Mr Somers and Mr Dransfield
- Mr Sutherland
- Mr Lane
- Mr Brierley
- Individuals who were not called as witnesses
- Findings of fact
- The early years
- Linklaters
- Key personnel during the period from March 2018
- Relationship with the PRA and the Authority
- 2016 and 2017
- The COREP audit and the CRE loans
- Mr Arden, the Board and the committees
- KPMG appointed
- April to June 2018
- July 2018
- The 2018 capital raise and half year results
- August 2018: PBTL and CLIP
- Communicating with the PRA
- KPMG decision trees
- PBTL classification
- Annual Review of Commercial Lending
- September Audit Committee
- September NEDs meeting
- September Board meeting
- Engagement of Deloitte
- Internal work in support
- Communications with the PRA
- Meeting with Linklaters
- Disclosure Committee meeting
- Mr Somers’ email
- Meetings with Mr Hill and Mr Bernau
- The October CRPAC meeting
- RWA Report
- Business and Commercial Lending
- The October Audit Committee meeting
- The Q3 Update
- Accounting, reporting and control report
- The October ROC meeting
- Chief Risk Officer’s Report
- The RWA Report
- Business and Commercial Lending Review
- The October Board meeting
- Linklaters Governance Update
- Audit Committee Update
- The Q3 Update
- 2019 Budget Paper
- Whether the RWA issue was discussed
- Chief Risk Officer’s Report
- Response to PSM Letter
- The Q3 Update and analyst calls
- Deloitte’s reports
- Discussions with Linklaters
- Discussions with the PRA and the January announcement
- Subsequently
- The PRA
- The Authority
- Mr Donaldson’s and Mr Arden’s careers
- The common ground
- The Parties’ cases
- The Authority’s case
- The Applicants’ case
- ISSUE ONE: WHETHER THE BANK BREACHED LR 1.3.3R
- The PRA and the COREP Returns
- Findings of fact
- The Applicants’ position
- The Tribunal’s view
- The PRA and confidentiality
- Findings of fact
- The Applicants’ position
- The Authority’s position
- The Tribunal’s view
- Mr Lane’s advice
- Findings of fact not in dispute
- Who was at the meeting
- How long was the meeting
- Linklaters’ practice when giving advice
- Knowledge of the impending Q3 Update
- What was said by Mr Arden at the meeting
- Confidential matter?
- The Tribunal’s finding
- The purpose of the meeting
- Reasonable to rely?
- Overall conclusion on legal advice
- No breach if uncertain and under investigation?
- Mr Jaffey’s submissions
- Mr Stanley’s submissions
- The Tribunal’s view
- No material breach if unknown
- The knowledge issue
- Key findings already made
- The Authority’s overall position on the knowledge issue
- The Applicants’ overall position on the knowledge issue
- Rules on classification
- Data issues
- Nature of the data issues
- Extent of the data issues
- Effect on materiality
- SME supporting factor
- Residential property
- Conclusion on data issues
- The mitigants overall
- The AIRB application
- Pillar 2A Offset
- Submissions
- Findings of fact
- Conclusion on Pillar 2A offset
- Phasing in
- PRA discretion
- Taking all the above into account
- Overall conclusion on the Knowledge Issue
- The PBTL Loans
- Findings of fact
- Submissions and the Tribunal’s view
- Whether the alternatives were unreasonable
- The Applicants’ position
- The Authority’s submissions
- The Tribunal’s view
- Reliance on the board and the Committees
- Findings of fact
- September
- October Audit Committee
- October ROC meeting
- October Board meeting
- The position of the parties
- The Tribunal’s view
- The Audit Committee
- The Board
- Reliance on Ms James
- Findings of fact
- Submissions
- Discussion
- Overall conclusion on Issue one
- The legal principles
- The statutory provisions
- Burton v Bevan
- Scandex
- Capital Alternatives
- Avacade
- Ferreira
- Submissions on Ferreira
- The words of the provision
- The ratio of Ferreira
- The corporate veil
- Forster: meaning of “knowingly concerned”
- Forster: reliance on legal advice
- The Applicants’ submissions
- The Authority’s submissions
- The Tribunal’s view
- The principles summarised and the issues remaining
- Mr Arden
- Mr Donaldson
- The position of the parties
- The Tribunal’s view
- ISSUE THREE: PENALTIES
- The Tribunal’s approach
- The DEPP
- The Authority’s position
- The Applicants’ position
- The Tribunal’s view
- The penalty framework
- Applying the Steps
- Step 2(1)-(3): Earnings
- The Tribunal’s view
- Step 2(4)-(7): Seriousness
- Step 3: Mitigation
- DEPP
- Submissions and discussion
- Co-operation
- Remediation
- Compliance with the PRA’s requirements
- Communications with the Authority
- No negative factors
- Other consequences
- Difference between the Applicants?
- Conclusions
![[2025] UKUT 00185 (TCC)](https://backend.juristeca.com/files/emisores/logo_ICfrj4g.png)