October ROC meeting
October ROC meeting
The ROC meeting was the first since July. The committee was provided with:
the Chief Risk Officer’s Report, the summary page of which contained a brief reference to the fact that “standardised RWAs continue to be above threshold”, while the more detailed slide unhelpfully conflated the reference to the historic issue of reweighting CRE assets with the new CLIP loan problem. The same slide also stated (again, our emphasis) that “this metric could increase by around 10 per cent (circa 40 million of capital) upon completion of the asset classification project”, but without more explanation. Although there was a discussion at the meeting about other elements of the report, there are no minuted comments about this item, see §§204-206;
the RWA Report, which included slides which said that RWAs were expected to increase by an estimated £642m including £574m relating to CLIP loans, and that “any further adjustments to calculations are not expected to be material”. However, the minutes record that the Committee was also told that “the commercial business was now largely correctly risk weighted” and that the wrong risk weighting “had been driven by a lack of clarity and conflicting rules in the regulatory publications”. Neither of those statements was correct, see §§210-211; and
the report on business and commercial lending as previously circulated to the CRPAC, see §186. The Executive Summary said (our emphasis) that the Bank had “experienced some issues with asset classification for regulatory reporting of RWAs”; that this was “not unique to Metro Bank” and would be “resolved over a two-year period”. Although the minutes show that commercial lending was discussed, there was no mention of RWAs.
- Heading
- Introduction
- The jurisdiction of the Tribunal
- The burden and standard of proof
- The PRA and capital requirements
- The Bank’s lending
- CRE loans
- CLIP loans
- PBTL loans
- COREP reporting
- The Authority
- Listing Rule 1.3.3R
- The MAR
- The evidence
- Approach to the evidence
- Mr Arden
- Mr Donaldson
- Ms Gillan
- Ms Roberts
- Mr Somers and Mr Dransfield
- Mr Sutherland
- Mr Lane
- Mr Brierley
- Individuals who were not called as witnesses
- Findings of fact
- The early years
- Linklaters
- Key personnel during the period from March 2018
- Relationship with the PRA and the Authority
- 2016 and 2017
- The COREP audit and the CRE loans
- Mr Arden, the Board and the committees
- KPMG appointed
- April to June 2018
- July 2018
- The 2018 capital raise and half year results
- August 2018: PBTL and CLIP
- Communicating with the PRA
- KPMG decision trees
- PBTL classification
- Annual Review of Commercial Lending
- September Audit Committee
- September NEDs meeting
- September Board meeting
- Engagement of Deloitte
- Internal work in support
- Communications with the PRA
- Meeting with Linklaters
- Disclosure Committee meeting
- Mr Somers’ email
- Meetings with Mr Hill and Mr Bernau
- The October CRPAC meeting
- RWA Report
- Business and Commercial Lending
- The October Audit Committee meeting
- The Q3 Update
- Accounting, reporting and control report
- The October ROC meeting
- Chief Risk Officer’s Report
- The RWA Report
- Business and Commercial Lending Review
- The October Board meeting
- Linklaters Governance Update
- Audit Committee Update
- The Q3 Update
- 2019 Budget Paper
- Whether the RWA issue was discussed
- Chief Risk Officer’s Report
- Response to PSM Letter
- The Q3 Update and analyst calls
- Deloitte’s reports
- Discussions with Linklaters
- Discussions with the PRA and the January announcement
- Subsequently
- The PRA
- The Authority
- Mr Donaldson’s and Mr Arden’s careers
- The common ground
- The Parties’ cases
- The Authority’s case
- The Applicants’ case
- ISSUE ONE: WHETHER THE BANK BREACHED LR 1.3.3R
- The PRA and the COREP Returns
- Findings of fact
- The Applicants’ position
- The Tribunal’s view
- The PRA and confidentiality
- Findings of fact
- The Applicants’ position
- The Authority’s position
- The Tribunal’s view
- Mr Lane’s advice
- Findings of fact not in dispute
- Who was at the meeting
- How long was the meeting
- Linklaters’ practice when giving advice
- Knowledge of the impending Q3 Update
- What was said by Mr Arden at the meeting
- Confidential matter?
- The Tribunal’s finding
- The purpose of the meeting
- Reasonable to rely?
- Overall conclusion on legal advice
- No breach if uncertain and under investigation?
- Mr Jaffey’s submissions
- Mr Stanley’s submissions
- The Tribunal’s view
- No material breach if unknown
- The knowledge issue
- Key findings already made
- The Authority’s overall position on the knowledge issue
- The Applicants’ overall position on the knowledge issue
- Rules on classification
- Data issues
- Nature of the data issues
- Extent of the data issues
- Effect on materiality
- SME supporting factor
- Residential property
- Conclusion on data issues
- The mitigants overall
- The AIRB application
- Pillar 2A Offset
- Submissions
- Findings of fact
- Conclusion on Pillar 2A offset
- Phasing in
- PRA discretion
- Taking all the above into account
- Overall conclusion on the Knowledge Issue
- The PBTL Loans
- Findings of fact
- Submissions and the Tribunal’s view
- Whether the alternatives were unreasonable
- The Applicants’ position
- The Authority’s submissions
- The Tribunal’s view
- Reliance on the board and the Committees
- Findings of fact
- September
- October Audit Committee
- October ROC meeting
- October Board meeting
- The position of the parties
- The Tribunal’s view
- The Audit Committee
- The Board
- Reliance on Ms James
- Findings of fact
- Submissions
- Discussion
- Overall conclusion on Issue one
- The legal principles
- The statutory provisions
- Burton v Bevan
- Scandex
- Capital Alternatives
- Avacade
- Ferreira
- Submissions on Ferreira
- The words of the provision
- The ratio of Ferreira
- The corporate veil
- Forster: meaning of “knowingly concerned”
- Forster: reliance on legal advice
- The Applicants’ submissions
- The Authority’s submissions
- The Tribunal’s view
- The principles summarised and the issues remaining
- Mr Arden
- Mr Donaldson
- The position of the parties
- The Tribunal’s view
- ISSUE THREE: PENALTIES
- The Tribunal’s approach
- The DEPP
- The Authority’s position
- The Applicants’ position
- The Tribunal’s view
- The penalty framework
- Applying the Steps
- Step 2(1)-(3): Earnings
- The Tribunal’s view
- Step 2(4)-(7): Seriousness
- Step 3: Mitigation
- DEPP
- Submissions and discussion
- Co-operation
- Remediation
- Compliance with the PRA’s requirements
- Communications with the Authority
- No negative factors
- Other consequences
- Difference between the Applicants?
- Conclusions
![[2025] UKUT 00185 (TCC)](https://backend.juristeca.com/files/emisores/logo_ICfrj4g.png)