Barring Portal: Loss of productivity - Item 11 of the Updated Schedule of Loss
Barring Portal: Loss of productivity - Item 11 of the Updated Schedule of Loss
For the reasons set out in in respect of Updated Schedule of Loss item 3, I have concluded that the quantification of DBS’s loss of productivity claim is flawed and the claimed losses irrecoverable. In the circumstances, item 11 also fails.
However, even if the WFPM was a reliable basis for starting to assess a loss of productivity in general terms, there is absolutely no proper attempt by DBS to provide a sound evidential link between the specific useability breaches established in respect of the Barring Portal and loss of productivity caused to DBS staff. DBS merely takes an overall sum as the aggregated effect of all Barring related complaints, and suggest in it Written Closing Submissions that it be reduced it by 50% to account for inefficiencies ‘caused by performance issues and other matters which do not form part of DBS’s claim’. DBS allocate 40% to the portal issues and 60% to other barring claims on the basis of the evidence of Ms Clare Graves, who whilst accepting that ‘I am not in a position to comment directly (from any personal knowledge) about the impact’ states ‘following consultation with my colleagues, I believe it is fair to estimate that about 40% of the 78.75 excess staff are needed because of Barring Portal Problems’.
There is no credible evidential basis for the suggested percentage reduction of 50% at all: DBS’s own witness evidence does not engage with the question of assessing the performance issues for which DBS itself was responsible or other matters which do not form part of DBS’s claim. Other than Ms Graves’s belief that it is a ‘fair estimate’ on the basis of her discussion with others, there is no explanation as to how the 40/60 percentage has been arrived at so as to allow even the most superficial interrogation. I also note that whilst Ms Graves said (in February 2023) that ‘when the Barring Portal is replaced (in the coming months), it will be easier for us to form a more certain view about this and look at the impact on the workforce by reference to current statistics and models’, DBS did not in fact seek to update its evidence for trial on the basis of the efficiencies in fact gained by the introduction of their new portal.
DBS’s approach cannot be equated with the Court ‘making the best estimate possible’ urged upon the Court by DBS, who relies upon the judgment of Toulson LJ (as he then was) in Parabola Investments Ltd v Browallia Cal Ltd [2010] EWCA Civ 486, [2011] QB 477 per Toulson LJ (as he then was) at [22] – [23]:
‘22. There is a central flaw in the appellants' submissions. Some claims for consequential loss are capable of being established with precision (for example, expenses incurred prior to the date of trial). Other forms of consequential loss are not capable of similarly precise calculation because they involve the attempted measurement of things which would or might have happened (or might not have happened) but for the defendant's wrongful conduct, as distinct from things which have happened. In such a situation the law does not require a claimant to perform the impossible, nor does it apply the balance of probability test to the measurement of the loss.
The claimant has first to establish an actionable head of loss. This may in some circumstances consist of the loss of a chance, for example, Chaplin v Hicks [1911] 2 KB 786 and Allied Maples Group Limited v Simmons and Simmons [1995] 1 WLR 1602, but we are not concerned with that situation in the present case, because the judge found that, but for Mr Bomford's fraud, on a balance of probability Tangent would have traded profitably at stage 1, and would have traded more profitably with a larger fund at stage 2. The next task is to quantify the loss. Where that involves a hypothetical exercise, the court does not apply the same balance of probability approach as it would to the proof of past facts. Rather, it estimates the loss by making the best attempt it can to evaluate the chances, great or small (unless those chances amount to no more than remote speculation), taking all significant factors into account. (See Davis v Taylor [1974] AC 207, 212 (Lord Reid) and Gregg v Scott [2005] 2 AC 176, para 17 (Lord Nicholls) and paras 67-69 (Lord Hoffmann)).’
DBS is correct that the loss of anticipated savings claim is by definition a hypothetical exercise, and this places the claim in a different category to global delay or disruption claims which are claims which seek to measure the effect of something which in fact happened in the past, and to which a standard balance of probabilities causation test applies. However, the ability for the Court, once an actionable head of loss is established which head involves a hypothetical exercise, to disapply the usual balance of probabilities approach to evaluate chances is not to be equated with asking the Court effectively to guess or make arbitrary and unsubstantiated percentage adjustments to claimed amounts in order to take account of matters which need to be excluded from a globally calculated sum. There must be an evidential basis justifying the figures used and the Court must be astute to considering critically whether the method of assessment advanced really is the ‘best’ estimate available. If there are different and more obviously evidentially rigorous approaches to assessing of loss which the claiming party has not advanced, the Court may simply conclude that it is not in a position to assess the ‘best’ estimate.
In the present case, the causal link between the breaches established and lost inefficiencies was, in relation to this part of the DBS’s case, principally the lack of take up of the digital system by applicant. It would have been entirely possible to present an evidence-based quantum analysis that (for example) identified the number of applications which would have been handled digitally, had the take-up target been met, and the number of digital applications in fact made, both based upon the actual numbers of applications made. The delta is the number (on DBS’s case) which would have caused, in each case, additional work for DBS which would not otherwise have been required (the multiplier). Analysis would have been able to establish, on the basis of factual evidence of what actually happened, an approximate difference in the amount of time, and therefore cost, between handling an application on paper versus digitally (the multiplicand). The multiplier applied to the multiplicand would have been a rational and reasonably robust approximation of the hypothetical loss. In circumstances where, as I have found, there were other reasons not due to TCS which caused the take up to be lower than targeted, it may be that the multiplier would be adjusted downwards on the basis of a percentage adjustment to estimate the effect of the difference causes, but this sort of adjustment would be applied to a significantly more evidentially rigorous starting point. It is this type of ‘best estimate’ which Toulson LJ was observing is permissible in assessments of the hypothetical.
I do not consider that, even if the WFPM was itself a reliable document, and allowing for the type of approach permitted in the context of a claim which is assessing a hypothetical situation, the Court is able to conclude that the anticipated loss of savings claim advanced by DBS represents the best estimate of the losses which would actually have been caused to it by the established breaches.
- Heading
- CONTENTS
- IntroductiON
- The Factual Witnesses
- Expert Evidence
- Programming Experts
- Forensic Accounts
- The Parties Submissions
- Principles Applicable to Issues of Construction
- The Defendant’s Obligations and Responsibilities
- Clause 15
- Clause 9.5 which states
- Clause 14.5 of Schedule 2-6 which states
- The Delay and Notice Provisions
- Clause 7
- Conditions Precedent: Clauses 5 and 6
- Conditions Precedent: the authorities
- Clause 5.6
- Clause 6
- Clause 8
- Limitations of Liability
- A single or multiple caps?
- The Delay Damages cap under Clause 52.2.5
- Is TCS’s claim for loss of anticipated costs savings excluded by Clause 52?
- Compliance with Clause 5.3, Agreement and Estoppel Introduction
- Express Agreement
- Estoppel
- Introduction
- R1 B&B Delays
- Mr Britton’s First Analysis
- Mr Britton’s Second Analysis
- Conclusion on Mr Britton’s Analyses
- TCS’s submission based upon Mr Jardine’s analysis
- Responsibilities for Delay on the ‘Infrastructure’ Critical Path
- R1-D
- Compliance with Notice Provisions
- Analysis of Delays
- Up to August 2017
- From August 2017 to 19 September 2018
- Analysis
- Failed to confirm its desired functional scope of R1 Disclosure in relation to the Customer-to-Business portal and Accountable Officer’s Update Service functionality. Such confirmation was a prerequis
- Failed to make available an end-to-end test environment for the Interactive Voice Response system
- Failed to agree upon a data migration approach, without which the Claimant could not complete the build of a data migration environment so that anonymised data could be made available for testing
- Failed to ensure that relevant external stakeholders were available to participate in Final Systems Integration Testing
- Partial Termination
- TCS’s Claims
- Non-Manpower Costs
- Anticipated Cost Savings
- Summary of TCS’s Delay Claim Recovery
- DBS’s Claims
- Delay Payments
- R1-B&B Delay
- Disclosure Scotland Extension Costs – Item 1 of the Updated Schedule of Loss
- Loss of Anticipated Savings – Item 3 of the Updated Schedule of Loss
- R1-D Delay
- R0 Licence Costs – Item 4 of the Updated Schedule of Loss
- R0 Hosting and Infrastructure Costs - Item 5 of the Updated Schedule of Loss
- R0 Technology Refresh – Item 6 of the Updated Schedule of Loss
- R0 N-1 Sustainment Costs – Item 7 of the Updated Schedule of Loss
- R0 Maintenance Costs – Item 8 of the Updated Schedule of Loss
- Savings
- Introduction
- Quality-related Obligations
- Good Industry Practice and Defects
- Digital by Default Standards
- Section 71
- The Basics Portal
- Section 73
- The Barring Portal
- Section 75
- Section 76
- Barring Portal: Loss of productivity - Item 11 of the Updated Schedule of Loss
- LPF Portal
- Siebel Useability Issues
- Redaction
- Document naming, bundle creation and performance
- Adobe Licence (Item 20)
- Document Storage (Item 21)
- Other B1 Barring Quality Issues
- Scan on Demand
- Special Characters
- Letters
- Item 24 : Loss of Efficiency Claims arising out of R1 Barring Quality/Useability Issues
- N-1 Sustainment Costs
- Causation and Loss
- Exit/Service Transfer
- Identification of all services (3.2.2)
- Knowledge Transfer (3.2.6 and 3.2.7)
- Section 95
- Providing all documentation to a replacement contractor (3.2.1 and 3.2.10)
- The identification of all leases, maintenance agreement and support agreements in connection with the provision of the services (3.2.3)
- Providing any other information or assistance reasonably required by a replacement contractor (3.2.14)
- Causation and Loss
- The Security Incidents
- The Charges Variation Dispute Introduction
- Issue 1: How the amount of an ‘over-recovery of the Forecast Revenue’ (Clause 2.8.4) or ‘under-recovery of the Forecast Revenue’ (Clause 2.8.5) is to be measured
- Section 104
- Issue 4: How Clause 2.8.5 of Schedule 2-3 applied to Volume Based Service Charges in Service Year 5
- Issue 2: Whether the Predicted Volumes for Basics in Service Year 4 were 1,000,000 (TCS’s case) or 320,374 (DBS’s case)
- Conclusion on Volume Based Service Charge
- Conclusions
![HT-2020-000448 - [2024] EWHC 1185 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)