HT-2020-000448 - [2024] EWHC 1185 (TCC)
Technology and Construction Court

HT-2020-000448 - [2024] EWHC 1185 (TCC)

Fecha: 17-May-2024

Introduction

Introduction

164.

The parties’ positions on delay to the R1 Project are polarised, and may broadly be summarised as follows:

(1)

TCS contends the predominant cause of delay to R1-B&B was inadequacy of the technical infrastructure services that DBS procured from HPE: they were immature, unstable and poorly documented; that provisioning, configuring and troubleshooting on infrastructure consistently proceeded at an unpredictable (and thus unplannable) but generally glacial pace. Although its pleaded case maintained that DBS failed to manage HPE adequately so as to resolve these issues, this case was not advanced with any enthusiasm either in examination of witnesses or in submissions. The case essentially rested upon HPE’s failures (either systemic or in execution).

(2)

DBS rejects that difficulties with the technical infrastructure were responsible for any of the critical delay to the R1 Project; rather, it contends the delay was caused by problems with the development and testing by TCS of the application software.

165.

Each party brings a financial claim arising out of the delays. TCS brings a claim for relief from liquidated and unliquidated damages, and its own claim for losses said to arise out of the delay, pursuant to Clause 7 of the Agreement. DBS brings its counterclaim for liquidated damages and unliquidated damages, pursuant to Clause 6 of the Agreement. TCS also contends that the Court can, should it need to, apportion responsibility for delay pursuant to Clause 8. DBS denies that Clause 8 is a pleaded issue, and (in any event) that the clause is relevant, or that any rights under the clause have been triggered in any event. I have dealt with the Clause 8 point, above.

166.

Before considering the parties’ respective contentions as to the causes of delay, I set out the context in which the evidence sits following my determinations as to the meaning of the liability and delay related provisions I have set out above:

(1)

DBS’s claim for liquidated damages is excluded by reason of its failure to have served a Non-conformance Report at all;

(2)

DBS nevertheless has a claim for unliquidated damages (in excess of Delay Damages it would have been entitled to but for its failure to serve a Non-conformance Report) it may prove were caused by Delay as a result of Contractor Default in excess of 6 months;

(3)

Delay is caused by CONTRACTOR Default unless TCS establishes that it is entitled to relief pursuant to Clause 7. TCS is entitled to relief irrespective of compliance with any condition precedent;

(4)

TCS is entitled to relief from Delay Damages and to recover loss and expense to the extent that it can establish that it would have been able to Achieve the Milestone by its Milestone Date but has failed to do so as a result of an AUTHORITY Cause;

(5)

it is therefore necessary for TCS to establish the date by which it would have been able to Achieve the Milestone but for AUTHORITY Cause;

(6)

an AUTHORITY Cause requires establishing a breach by DBS of an express or implied obligation (whether by itself, one of its other contractors, or servants or agents) under the Agreement.