Mr Britton’s First Analysis
Mr Britton’s First Analysis
Mr Britton (in his First Report) adopted a ‘prospective’ analysis. This method chiefly relied upon the Microsoft Project plans produced by TCS during 2016 and 2017 – beginning in 20 January 2016, up to 13 July 2017 – to identify and track changes over time to the forecast Go-Live date for R1-B&B.
The starting point for his analysis was the existence, therefore, of a move to the Go-Live date in a particular contemporaneous plan. That move would generally be backward (i.e. later), but sometimes forward. Mr Britton then sought to examine the detail of the plans to determine what he considered had changed since the earlier plan to cause movement to the projected Go-Live date. An extract from his analysis, as summarized and commented upon in the Joint Report with Dr Hunt is set out below to illustrate the basis of the analysis:

Mr Britton regarded these resets to the projected Go-Live date from time to time as being a ‘proxy’ for actual critical delay (including ‘negative’ critical delay, if the date came forward) to the R1 Project.
The effect of the analysis is that Mr Britton did not consider whether a forecast event which pushed the forecast delay back in one plan in fact became an event which caused actual critical delay to completion in due course. Mr Britton accepted this in terms (Day 16/74):
Q. You're really asking -- seeking to ask and answer
the question, from the plan: what appears to have caused
1 the planner to change the Go-Live date?
A. Yes.
Q. We go on, we can see a bit further down, you say:
"I have then reported that as the reason for
the date slipping or (in several instances) moving
forward."
A. Yes.
Q. So that's what you do and you say: this is the -- this
is the reason for the change -- the date change?
A. Yes.
Q. And, at least in this analysis, you don't at any stage
seek to consider whether the forecast events actually
occurred as planned?
A. No.
Whilst Mr Britton also accepted that he did not, having identified what prospective delay was perceived to be likely to occur in the future, carry out any cross-check against what actually happened, he thought this was a theoretical problem in this case (Day 16/123):
Q. Yes. So you could test – you could cross-check the information in the Microsoft Project plan by reference to, for example, and as-built analysis, which would tell you whether what was projected comes to pass, if you’re doing it retrospectively?
A. Yes.
Q. But that’s not what you do in your first report, is it?
A. No, I don’t do that exhaustively. I won’t say I won’t do it. I’d have to have a look.
Q. Well, you don’t do it at all in your first report, do you? It’s not exhaustively; you don’t do it at all?
A. I would -- I don’t know. I can’t say I never do it, but I -- you know, as a general rule, no, I don’t.
Q. What, in your first report?
A. In my first report.
Q. No.
And would you accept that if one was interested in
finding out to what extent a project was actually
delayed and the things that actually caused delay to
the project, it would be appropriate to look back to see
what actually happened and not simply confine yourself
to that which was projected to happen?
A. But at the end, I am looking at what actually happened.
And also I think this is a very theoretical objection,
because if you look at the events which cause delay,
many of them are in the past and -- with respect to
the plans, and when you follow up what did actually
happen, they did happen and delayed even further.
Mr Britton explained this further in re-examination, where he said that (Day 19/128):
…The -- what I'm really
trying to say in that answer is that I think Mr Croall's
objection was that, you know, if you're looking forward,
it might never have happened, but if you go through
the sequence of plans, you can see that all of
the delays that affect the timeline, that cause
the Go-Live date to be pushed out, you can see, in
retrospect, that they did happen and they were actually
worse than that. So it's not a fair criticism to say,
"Well, it might not have been -- it might not have
happened that way"; it did happen that way, ultimately.
They didn't appear as the critical path later on because
other things had delayed even further, but, you know,
those delays did happen.
The difficulty of this approach as a matter of objective delay analysis is that its efficacy as an approach itself depends on the very conclusion Mr Britton arrives at, namely that infrastructure delays are constantly on the critical path. Mr Britton does not therefore regard it as particularly important (in the context of his report which allocates all infrastructure delay to HPE (and/or DBS)) to distinguish with precision what the period or cause of critical delay actually was.
Mr Britton accepted, in the passage above, that earlier delays identified as the cause of (forecast) critical delay may not ultimately have transpired to be either on the critical path or, indeed, to have caused delay at all. A good example of this was where a particular part of the planned solution was de-scoped from the project altogether so that the forecast delay attributable to the development of that part of the solution never became a reality. Moreover, he accepted that his analysis does not allow actual delay to be apportioned between particular infrastructure related activities on his critical path (Day 16/117):
Q. But let us be clear. If the court wanted to know how much any given event caused by way of delay, they couldn’t derive any assistance from your report because you don’t seek to apportion delay to any given feature or any given event; that’s right, isn’t it?
A. Between infrastructure features, no, that’s right.
MR JUSTICE CONSTABLE: But because all of your analysis is through infrastructure, that means there isn’t really a caveat, in fact, to your answer?
A. I think if you were to want to -- to want to come to a conclusion that said X days were delayed -- there was X days delay due to CJX/PSN and there was Y days due to content inspection, then it would be quite challenging to do that. You could maybe do it by looking further into and looking at the different delays, but there would be no easy – there’s no easy off-the-shelf answer.
It is true that in a universe where (a) all delays are infrastructure delays, and (b) all infrastructure delays are Authority Cause, this would not necessarily be a problem. It was, it seems, for this reason that Mr Britton did not perceive his approach as problematical (Day 16/129):
MR JUSTICE CONSTABLE: And how much does your view on the absence of a problem in this project relate to your view that, from your analysis, the critical path runs through effectively the same thing, as far as you’re concerned, ie the fault of one party, and distinguishing with greater precision within that isn’t necessary for you to draw a particular conclusion? Are those two linked?
A. I -- I think, I’m not sure whether this would have been sufficient if we’d had to, as I say -- if the responsibility passed from one party to another. I think you would need to refine it in some way. But I think it’s still important to take account of how the projected delays influenced the decisions made at the time. So I don’t know if I have an answer as to how you would do it if -- if it was more complex.
Where, however, the universe is one in which the very purpose of the exercise, without starting with the answer, is to determine what activities were the real cause of actual delay, rather than potential causes of forecast delay, and what the actual delay period attributable to a particular activity was as things transpired, this is in my judgment a significant problem with Mr Britton’s analysis.
A large part of the rationale advanced by Mr Britton for this approach depended upon his assumption that once a forecast delay was embedded into the programme, it effectively became a cause of delay because other work was undertaken in the context of the new timeline. Thus, in his Third Report, Mr Britton expressed the view that:
‘On an IT project, activities that are not on the critical path will tend to extend to fill the time available and activities that are one the critical path will tend to be compressed and overlapped or a completely new strategy will be devised if the project is late. Dependencies are fluid and can often be waived or postponed…Teams can be asked to work additional hours over limited numbers of weeks to speed up delivery if required. Unlike a construction project, resources cannot simply be brought on and laid off a project as and when required…..If software is not on the critical path, then ways need to be found to keep these team members productive, by slimming the team down (a route that cannot easily be retraced) or by finding additional work for them to do, such as implementing change requests or non-essential improvements and defect fixes. Changes may be agreed without requesting an extension when one would have been insisted on if the software was critical.’….Once a delay to a milestone has been forecast on an IT project, the software-delivery workstream will work to the new forecast date.’
Whilst the logic of Mr Britton’s evidence is comprehensible in general terms (although it must be said that the distinction with the construction industry he observes is not necessarily correct given that, depending on the labour market, very similar resourcing issues may also, in construction projects, give rise to a reluctance to let workers go), it is ultimately a question of fact as to whether this happened. In essence, the conduct described is a type of ‘pacing’, in which the duration of the non-critical activity is prolonged deliberately in the face of delays caused to a critical activity. It is likely to be the product of a conscious management decision to achieve a particular advantage.
Dr Hunt’s evidence on the topic, in her second report, was as follows:
‘While I have not been able to assess TCS’s progress in development and testing in detail, because of the lack of a development tracking tool, I have seen no evidence to suggest that TCS’s development and testing team were in effect ‘pacing’ their activity while waiting for other critical activities to complete. On the contrary there is evidence that TCS did not have sufficient resource to carry out the necessary work in 2016, for example:
• DBS expressed concerns at the lack of test resource, completeness of test plans and a lack of a release manager in March 2016
• TCS’s proposal to re-sequence test phases in May 2016 was accompanied by a proposal to significantly increase on-shore testing resource
• TCS did not have sufficient resource to test and support both Barring & Basics and Disclosure in June 2016
• Suggestions that TCS should implement changes to the portals for usability reasons caused concern about build impact in TCS’s build team’
In response to this, Mr Britton identified (at paragraph 40h of the Joint Statement dated 25 August) generic behaviour (such as the agreement to RFCs (Requests for Change) or the spreading of UAT2 (User Acceptance Testing) over three cycles, without requesting extensions, and the absence of pressure on the BPO (Business Process Outsourcing) UAT team to speed up despite overrunning by months). However, it remains the case that none of the TCS witnesses gave any direct evidence to support the existence of a decision to slow activities down to pace against infrastructure delays. There were no documents in which such a strategy was either discussed at management level, or through which instructions to ‘pace’ were given to the teams. In cross-examination, Mr Britton also accepted that these were not really examples of ‘pacing’, more ‘keeping the team busy’.
It might be said that the examples provided by Dr Hunt were all dated from a period where little critical delay since the November 2015 reset had occurred (assuming the extent of accrual of delay within Mr Britton’s first analysis, Mr Jardine’s analysis, and the contemporaneous programmes is correct), and therefore they do not relate to the period in which infrastructure delay was undoubtedly occurring (irrespective of the question of criticality). However, her observation about the absence of evidence suggesting any conscious decision to pace activities is, in my judgment, a fair and justified one.
Both parties made submissions as to BPO UAT in the particular context of pacing, or ‘unintentional pacing’ as it was described at one point by Mr Britton.
Mr Jardine explained the importance of BPO UAT to his analysis in cross-examination (Day 24/61):
Q. But essentially, as I understand it, you're choosing BPO UAT largely because it wasn't forecast to last as long as it did?
A. I -- by observation, I look at that and I think that's -- that's the problem. It's back to my core -- my – my core work thought. It was on the original critical path and I would find it strange if the baseline critical path wasn't true what people thought were the core pieces of work at the time. And then it was -- it looks to have been, for whatever reason, only ever forecast to be done it within a week or two, but when it came to it, suddenly it's caught you up and perhaps caught you by surprise, but that has caused it to become critical at the end here.
Mr Britton explained how the same issue affected his decision making in relation to his second analysis (Day17/172):
Q. And obviously the single longest item which is much longer than planned is the slip to BPO UAT?
A. Yes.
Q. As a consequence, in your report at page 40 {C1/4/40} onwards, you spend some time explaining why it is that that workstream need not have taken the amount of time it in fact took?
A. Yes.
Q. Is that a fair way of characterising how you address it?
A. Yes.
Q. And it’s because you conclude that it need not have taken that time that you conclude that you can – unlike the delays that we see to systems monitoring and load balancing, it doesn’t need to be fed into the –
A. The original plan.
Q. -- the original November 2015 plan. Have I understood that right?
A. Yes.
By ‘unintentional pacing’, Mr Britton explained that he meant that the activity did not appear to have been resourced adequately to perform it within the planned timeframe. It was not necessarily an act of deliberately going slowly, rather it was just not picking up speed when it fell behind, because of the existence of critical delays on the infrastructure path(s). Mr Britton characterised BPO UAT as an activity which was allowed to drift because it was not critical, and TCS submit that there was no reason in principle why the initially planned timescales for BPO UAT (being 18-20 working days) could not have been achieved had that been necessary. TCS points out that BPO UAT was never marked as critical on contemporaneous ‘POAP’s (Plans on a Page – effectively summary programmes), consistent with (amongst other things) the evidence of Mr Padannayi’s explanation in cross examination as to why there was no sense of urgency even though the TCS build team (as opposed perhaps to the BPO team) wanted to close BPO UAT (Day4/160):
A. We wanted to finish this test phase, definitely. But what I was referring to earlier was that if you look at holistic view of programme and if you see where this PMS testing -- or BPO UAT was taking longer indeed, but there wasn't -- there was nothing hanging off of it, so to speak, before what is stopping it from going live basically.
Q. That was –
A. There's no -- this is not a predecessor for any other critical activity in the sense this taking longer was delaying the programme day by day. No, that was not.
I accept that Mr Padannayi’s recollection to the effect that BPO UAT was not perceived as being on the critical path at the time is most probably accurate. However, the chronology produced by DBS at paragraph 185 of its Closing Submissions which is the basis for the following factual findings is also a fair and correct one. It is one which demonstrates in my judgment that TCS’s submission that BPO UAT could have been carried out in the as-planned duration of 18-20 days if necessary is completely without foundation:
As of 15 November 2016, the plan for BPO UAT envisaged the testing of 363 test scenarios at an average rate of 19 scenarios per day, leading to a finish date in December 2016;
By 22 November 2016, TCS had attempted 124 scenarios of which 54 passed, 38 failed and 32 were blocked. Support was sought from the build team to address the issues as of 23 November 2016, but slow progress was being made in addressing the issues. As set out in the email from Amit Kumar Tyagi:
‘As per the update shared yesterday, today We have taken support from build team to analyse all the failed and blocked scenarios in PMS area and identified the one's which needed further clarification, testing, test data creation, or if it is a new requirement.
There was slow progress in execution today due to teams involved in these discussions on previous failed, blocked scenarios and unavailability of test data in the SIT-L environment (since regression and BPO UAT testing is going in parallel and test data creation needs support from testing team).’
Similar problems continued to occur. Some days (e.g. 29 November 2016) no official testing took place because of lack of availability of the Finance team. There was still a large number of blocked and failed scenarios as at 2 December 2016. From Amit Kumar Tyagi:
‘There are total 142 blocked scenarios, the reasons for the blockage of these scenarios is summarised as follows -
Blocked in PMS - 112
Finance unable to close period - 73
Reporting logic incorrect - 15 (5 scenarios have failed which were attempted full test of similar scenarios but the logic seems to be incorrect due to which these have been put as blocked)
Test data creation in progress to retest and confirm - 8
User Training under progress to carry on testing - 2
The remaining 14 include Test Scenarios dependent on other Failed/Blocked Scenarios
Blocked in non-PMS i.e. Contact Centre, BPO, MIS etc - 30
Blocked by RBAC's - 27
Blocked due to other Failed Scenarios - 3
In addition to the blocked scenarios, there are total 87 failed scenarios (29 non-PMS and 58 PMS). The defects have been raised for these and are being discussed/reviewed during daily triage call. The defect summary has been skipped from this status update and will be continued from 05-Dec-16 daily status report.’
[PMS is Payment Management System; MIS is Management Information System; RBAC is Role Based Access Control]
On 9 December 2016, Ms Wagner rejected as unrealistic a plan to complete BPO UAT by the end of December. She asked for a realistic plan that could be delivered. The report also referred to the fact that ‘BPO have struggled… due to lack of resource on our part” and that the “test team have committed to providing us with two additional resource to aid the progress of retesting.’
On 9 January 2017, Mr Bhatia reported internally that BPO UAT had “not gone well and the statistics [had] not been very encouraging so far…”
A status update on 20 February 2017 reported that there were still 87 defects in re-testing which it was hoped would be completed by 6 March 2017, following which there would be a round of regression testing
An internal TCS message on 1 March 2017 referred to the fact that BPO UAT had not been run as efficiently due to inexperience of the TCS BPO UAT team in running tests.
By the end of March (27 March 2017), Mr Foster reported the status as follows
‘Please find below. We have had no update from testing today due to the system being unavailable for nearly all of the day. With regards to Barring testing we are still waiting for the resolution of the outstanding cases from last week. The build team have made a number of updates to this but over the last week everytime an issue is fixed it causes a problem in another area.’

Mr Swain of TCS disagreed with this characterisation of the problem, hinting it seems that it was the approach of the BPO team which was causing the problems:
‘I would disagree with the statement that everytime an issue is fixed it creates more problems. We meet several times a day on various issues, we can discuss and try resolve in an efficient manner if it's such a problem. I have given below an extract of fixes released/tested in last 2-3 weeks…
We understand the criticality of this phase and try to ensure that you get the fixes as soon as possible.’
This exchange does not appear consistent with an activity which is merely being allowed to drift in the knowledge of parallel critical delay on a different workstream. TCS was therefore aware of the problems with BPO UAT and the importance of resolving them.
On 28 March 2017, Ms Mather asked Mr Foster what was needed to meet the exit criteria. In a separate message, she also asked why an unrealistic date of 3 April had been set when it was known that the test team would not be available due to their involvement in month end activities. Mr Foster responded that this was due to ‘various reasons including lack of system availability and resource not being available for unexpected reasons’.
As at mid-June, the following data was presented:


This shows the progression of defect identification and resolution through the first half of 2016.
In the same email chain, Mr Swain stated that there were expected to be no remaining critical defects at the end of that day, implying there were still critical defects as of that date. He said:
‘Our BPO team has made it clear that only critical defects are must-have from business point of view. However in today's checkpoint DBS has said they will review the high defects to ensure that service is not impacted due to these.
We will be left with around 25 high defects as of EOD today. All of these in rejected/retest status.
Currently Safuvan's team is retesting and closing these defects.
In parallel, Debra has asked BPO team to revisit these defects and reduce the severity, as appropriate.’
Notwithstanding the obvious focus and effort, as of 22 June 2017, the position was:

There therefore remained severity 1 and severity 2 defects. Defects overall were still less than 90% fixed: there were 806 defects in total with 89 outstanding.
Exit from BPO UAT in the event only occurred on 9 August 2017.
This chronology suggests, as I find, that the extended duration of BPO UAT was caused in very large part by TCS’s own problems which were being encountered and an absence of resource which would not have been immediately remediable had TCS considered it necessary. It may be that some element of the overall duration was caused by a lack of prioritisation given the other, critical delays at the time. Ultimately, however, I do not consider that the duration of this activity was principally caused by ‘unintentional pacing’. It was caused mainly by the technical issues TCS was grappling with, the (possibly changing) requirements of the BPO commercial team and the unreliability of their availability for testing given the other demands on their time. This is so even though I accept it was probably sub-critical, although only marginally so in the latter months of the R1 B&B project.
It is convenient at this point to consider that one of the principal explanations that Dr Hunt gave for the length of time taken by TCS for development and testing was the need for defect-fixing. In its written Closing, TCS identifies, by reference to aspects of cross-examination, a number of reasons why Dr Hunt has overstated the extent or difficulty of defect fixing.
The starting point is that, on the basis of the contractual analysis, it is necessary for TCS to prove the date by which they would have Achieved the Milestone as a key element of obtaining relief: it is not for DBS to explain the reasons why TCS took the time they did by reference to identifiable problems that TCS faced of its own making.
In relation to Mr Jardine’s Window 3 (from 15 June (when DBS suspended UAT 1) to 10 November 2016 (when DBS recommenced UAT by starting UAT 2)), for example, Mr Jardine’s view was that the critical path remained through the development and testing of the additional software Drops and thereafter into Final SIT 2 and UAT 2, since these were the “core” stages of R1-B&B that the successive POAPs show were being progressed (and were increasingly in delay). Dr Hunt (upon whose analysis Mr Jardine relied) considered that the principal reason for these additional code Drops, and consequential critical delay to the start and progress of Final SIT 2, was the need for TCS to fix and re-test software defects found in earlier SIT and UAT1 prior to its suspension.
Dr Hunt relied on ‘ALM’ (Application Lifecycle Management) data from TCS showing the number and severity of the defects recorded for SIT during 2016. The view expressed in Dr Hunt’s report was that the main driver of continuing SIT during this period was the need for TCS to deliver and test additional drops which were primarily driven by the need for defect fixes. In cross-examination, Dr Hunt fairly conceded that this was an overstatement of the position (Day 21/109):
And so one can't just say, well, this is how long
the test phase was, one needs more metrics to understand
what was primarily driving the ongoing SIT?
A. Yes, I was answering you in the abstract, and I think in
this case, for this window, it's more complicated than
that. We've got a mixture of DBS RFCs, we've got defect
fixes going on, we've got the PMS enhancements, we've
got in the early stages some portal work still going on
and we've also got issues that TCS decided to move from
drop 8 into drop 6 to support OPA, for example. So
there's a whole mixture of different things happening.
So I think to say it's primarily defect fixes is an
overstatement on my case -- on my part.
Whilst Dr Hunt fairly conceded the point was more nuanced than her initial report had indicated, the tenor of her evidence in cross-examination, which I accept, is that there remained, nevertheless, a considerable amount of defect-fixing work ongoing. A large part of the cross-examination focussed on the potential contribution to the workload caused by the impact of RFC related work. Even if, as Dr Hunt conceded, a greater element of the extended duration of testing related to RFC work than fixing defects in the originally planned workscope, there are two fundamental difficulties facing TCS. The first is that, having agreed to carry out RFC work with no adjustment to the Milestone Date pursuant to the Change Control procedure, to the extent that the work did in fact cause delay, it is TCS’s risk, which passed at the point of agreeing the RFC. The second, more important, issue is that even if this were not the case, there is no evidential basis, either in the factual witness evidence or the expert evidence, upon which the Court could possibly come to a reliable conclusion about the appropriate amount of time which reflected RFC defect-fixing work as opposed to original-scope defect-fixing work. Indeed, the absence of such an analysis formed part of one of Mr Lavy’s questions (Day 21/123):
A. What we've got here is very much a mish mash of
different things.
Q. So if you wanted to understand -- if it was important to
understand the difference between the, what I'm going to
call, pre-existing defects, so from the original
contractual scope, and RFC-based defects, one would have
to do rather more analysis than you've done; is that
fair?
Yes, that's fair.
Where it is for TCS to demonstrate the date by which it would otherwise have Achieved the Milestone as part of its case for relief and/or payment, the absence of this analysis is, fundamentally, an obstacle for TCS. This is particularly so in circumstances where the evidence suggests that – even if there are a number of non-TCS related issues causing problems for exiting a particular test phase – there were also TCS-related issues preventing exit caused by TCS or sub-contractors for whom TCS was responsible. In these circumstances, it is not possible for TCS to establish that – even ignoring the non-TCS issues – they would have exited the particular test phase sooner. Take, for example, the exit to Final SIT 2, where the evidence is clear that the Welsh Template Testing issue (a TCS issue) remained a difficulty to TCS alongside other issues through to the end of 2016. There is no evidence (witness or documentary) which suggests that delays in this regard were attributable to any party other than TCS or its sub-contractor, or that the issues would have been resolved sooner than they were in fact but for other problems.
I conclude on the evidence that it is not likely that TCS could in fact have exited testing phases earlier than they did. Mr Britton accepted that if the criteria to exit a test phase were met, it would be sensible for the contractor to exit and then carry on fixing defects, rather than elongating the test phase to fix more defects even though the exit criteria were already met (Day16/148):
MR JUSTICE CONSTABLE: And would you -- I mean, this sounds slightly counterintuitive to me, although I don’t run IT projects. To not exit, when it’s something on a plan, you’ve got your client there, why wouldn’t you exit? And then obviously you may -- you may want something for your testers to do so they carry on fixing defects, but if they’ve got to the point at which they’re allowed to exit, given the remaining number of defects, why on earth wouldn’t you do that so you’ve just ticked that box and the client can’t complain?
A. Yeah. No, you could do that and I think that would be a sensible thing to do. But -- so you might exit and then just carry on fixing defects. So, yes, perhaps it’s not the best example in the world.
This is particularly so, in my judgment, in the context of an Agreement where the right to relief was dependent upon establishing when TCS would otherwise have Achieved the Milestone. It is not obvious why going slower than planned and/or than the pace at which TCS would otherwise have been able to proceed along the software-development workstream and/or not exiting test phases as soon as possible would be, in any way, a sensible strategy. It certainly cannot be assumed that this is what TCS would have done, given that it seems entirely counterproductive to its interests knowing that it would be necessary to seek relief when the Milestone was not Achieved. Mr Britton fairly accepted in evidence that any conscious decision to work in this way would be reported up the line or down the line (Day 16/157); and that if it chose to do so, it would be at risk:
Q. So, if they were doing so, they would appreciate they were doing it on risk, so to speak?
A. I think so. They would take a -- they would take a balanced judgment based on risk, if there’s that much logic to it.
Q. And one of those risks is that they will end up being the cause of a delay to the project, isn’t it?
A. Yes, there is -- there is that risk.
Another risk, of course, is that it may make it difficult for TCS to establish when it would (on its sub-critical path, assuming this is where its activities lay) have Achieved the Milestone but for AUTHORITY Cause. This difficulty is highlighted by consideration of BPO UAT above. I have accepted that it was probably not on the critical path (although it probably would only have been marginally sub-critical), but I have also rejected TCS’s ‘all or nothing’ case that BPO UAT would have been carried out in the planned duration if TCS had wanted as completely unrealistic. This presents an insuperable difficulty for TCS’s pleaded case that, but for the infrastructure delays, it would have Achieved the Milestone as planned (subject to 18 days delay).
Returning to Mr Britton’s analysis, I consider that insofar as his conclusions regarding criticality are driven, as they seem to be, by his assumption that the software development and testing workstream was being intentionally or unintentionally paced to any material degree, these conclusions are unreliable. Moreover, even in circumstances where the Agreement was silent as to the type of delay analysis required, it is improbable that the sort of prospective analysis undertaken by Mr Britton would be of much assistance to any tribunal wishing to understand what the actual periods and causes of critical delay on a project were, after the event. As set out above, Clause 7 requires a backward-looking analysis which identifies the actual reasons TCS failed to Achieve the Milestone in question. It is clear that Mr Britton’s first, prospective, analysis does not adopt a recognisable and logical method by which this could be established with any reliability. The mere fact that, as is undoubtedly true, infrastructure delays were within contemporaneous documents perceived at various times by various parties including DBS to be causes of critical delay does not detract from this conclusion as to the appropriateness of Mr Britton’s approach to delay analysis.
A further difficulty with Mr Britton’s analysis in the specific context of this case is that he only considered matters which were shown to be on the critical path on any given plan, and did not analyse delays to activities on the sub-critical path. Mr Britton accepted this (Day 16/75 line 15). In circumstances where TCS is also required pursuant to Clause 7 to demonstrate the date by which it would have Achieved the relevant Milestone but for AUTHORITY Cause, this is a fundamental problem. That Mr Britton presented no analysis which sought to establish this (in circumstances where by definition software development was, on his evidence, always on a sub-critical path) was demonstrated by the fact that the answer to this key question was advanced in Closing by TCS by reference to, in effect, an analysis presented by Mr Lavy through a ‘correction’ of Mr Jardine’s evidence rather than by reference to any evidence from Mr Britton.
- Heading
- CONTENTS
- IntroductiON
- The Factual Witnesses
- Expert Evidence
- Programming Experts
- Forensic Accounts
- The Parties Submissions
- Principles Applicable to Issues of Construction
- The Defendant’s Obligations and Responsibilities
- Clause 15
- Clause 9.5 which states
- Clause 14.5 of Schedule 2-6 which states
- The Delay and Notice Provisions
- Clause 7
- Conditions Precedent: Clauses 5 and 6
- Conditions Precedent: the authorities
- Clause 5.6
- Clause 6
- Clause 8
- Limitations of Liability
- A single or multiple caps?
- The Delay Damages cap under Clause 52.2.5
- Is TCS’s claim for loss of anticipated costs savings excluded by Clause 52?
- Compliance with Clause 5.3, Agreement and Estoppel Introduction
- Express Agreement
- Estoppel
- Introduction
- R1 B&B Delays
- Mr Britton’s First Analysis
- Mr Britton’s Second Analysis
- Conclusion on Mr Britton’s Analyses
- TCS’s submission based upon Mr Jardine’s analysis
- Responsibilities for Delay on the ‘Infrastructure’ Critical Path
- R1-D
- Compliance with Notice Provisions
- Analysis of Delays
- Up to August 2017
- From August 2017 to 19 September 2018
- Analysis
- Failed to confirm its desired functional scope of R1 Disclosure in relation to the Customer-to-Business portal and Accountable Officer’s Update Service functionality. Such confirmation was a prerequis
- Failed to make available an end-to-end test environment for the Interactive Voice Response system
- Failed to agree upon a data migration approach, without which the Claimant could not complete the build of a data migration environment so that anonymised data could be made available for testing
- Failed to ensure that relevant external stakeholders were available to participate in Final Systems Integration Testing
- Partial Termination
- TCS’s Claims
- Non-Manpower Costs
- Anticipated Cost Savings
- Summary of TCS’s Delay Claim Recovery
- DBS’s Claims
- Delay Payments
- R1-B&B Delay
- Disclosure Scotland Extension Costs – Item 1 of the Updated Schedule of Loss
- Loss of Anticipated Savings – Item 3 of the Updated Schedule of Loss
- R1-D Delay
- R0 Licence Costs – Item 4 of the Updated Schedule of Loss
- R0 Hosting and Infrastructure Costs - Item 5 of the Updated Schedule of Loss
- R0 Technology Refresh – Item 6 of the Updated Schedule of Loss
- R0 N-1 Sustainment Costs – Item 7 of the Updated Schedule of Loss
- R0 Maintenance Costs – Item 8 of the Updated Schedule of Loss
- Savings
- Introduction
- Quality-related Obligations
- Good Industry Practice and Defects
- Digital by Default Standards
- Section 71
- The Basics Portal
- Section 73
- The Barring Portal
- Section 75
- Section 76
- Barring Portal: Loss of productivity - Item 11 of the Updated Schedule of Loss
- LPF Portal
- Siebel Useability Issues
- Redaction
- Document naming, bundle creation and performance
- Adobe Licence (Item 20)
- Document Storage (Item 21)
- Other B1 Barring Quality Issues
- Scan on Demand
- Special Characters
- Letters
- Item 24 : Loss of Efficiency Claims arising out of R1 Barring Quality/Useability Issues
- N-1 Sustainment Costs
- Causation and Loss
- Exit/Service Transfer
- Identification of all services (3.2.2)
- Knowledge Transfer (3.2.6 and 3.2.7)
- Section 95
- Providing all documentation to a replacement contractor (3.2.1 and 3.2.10)
- The identification of all leases, maintenance agreement and support agreements in connection with the provision of the services (3.2.3)
- Providing any other information or assistance reasonably required by a replacement contractor (3.2.14)
- Causation and Loss
- The Security Incidents
- The Charges Variation Dispute Introduction
- Issue 1: How the amount of an ‘over-recovery of the Forecast Revenue’ (Clause 2.8.4) or ‘under-recovery of the Forecast Revenue’ (Clause 2.8.5) is to be measured
- Section 104
- Issue 4: How Clause 2.8.5 of Schedule 2-3 applied to Volume Based Service Charges in Service Year 5
- Issue 2: Whether the Predicted Volumes for Basics in Service Year 4 were 1,000,000 (TCS’s case) or 320,374 (DBS’s case)
- Conclusion on Volume Based Service Charge
- Conclusions
![HT-2020-000448 - [2024] EWHC 1185 (TCC)](https://backend.juristeca.com/files/emisores/logo_yJUntHA.png)