HT-2020-000448 - [2024] EWHC 1185 (TCC)
Technology and Construction Court

HT-2020-000448 - [2024] EWHC 1185 (TCC)

Fecha: 17-May-2024

R0 Maintenance Costs – Item 8 of the Updated Schedule of Loss

R0 Maintenance Costs – Item 8 of the Updated Schedule of Loss

492.

DBS pleads that it has been required to engage in a number of changes and updates to R0 to improve the security and reliability of data exchanged with R1. The Updated Schedule of Loss identifies a number of projects, and adds that, due to the age of the system, all necessary changes to R0 have been costly to implement. The pleaded sum is ‘estimated’ at £2,843,990.

493.

Mr Hain explains that the costs include (a) CGI claimed costs in the sum of £1,829,974 (b) the replacement of MS Access and Deployed of F5 costs in the sum of £193,000 (c) internal resources in the sum of £230,938 and (d) internal resources relating to security in the sum of £590,078.81. Mr Hain makes various adjustments to the sums claimed.

494.

There is no basis to link, causally, the CGI costs or the replacement of MS Access and Deployed of F5 costs to the period of delay for which a claim is valid.

495.

Mr Hain notes that claimed sums at (c) and (d) relate to a period from April 2017 to March 2022. The claim at (c) is based upon the assumption that the work required equated to 1 FTE SEO and 0.4 FTE EO. The claim at (d) relates, in the majority, to ‘Digital (1 x Contract resource 1 day per week)’ and ‘DSARs (1 x 0.5 AO per week)’. He calculates an adjustment for the 2017-2018 year to excise the costs up to 28 November 2018 which is the date (no doubt on instructions) he said was the date R1 Disclosure was due to go live on. The remaining elements for (c) and (d) for that year are £39,481 and £56,855. A proportion of these sums, therefore, relate to the period from 28 November 2017 to 5 February 2018. The sums are far below the sums that would have been recovered by way of Delay Payments (had DBS complied with Clause 6), and so (even if appliable) no claim for proven additional damages exists.

496.

This claim fails.