HT-2020-000448 - [2024] EWHC 1185 (TCC)
Technology and Construction Court

HT-2020-000448 - [2024] EWHC 1185 (TCC)

Fecha: 17-May-2024

The Charges Variation Dispute Introduction

I.

The Charges Variation Dispute

Introduction

768.

TCS’s fees for providing the operational services under the Agreement were principally in the form of Volume Based Service Charges. These were per-transaction charges payable in respect of each disclosure application processed by TCS during each Service Year. The scheme of charges, which is set out in paragraph 2.3 of Schedule 2-3 to the Agreement, specified a unit charge for each type of disclosure application (Basics, Standard, Enhanced and Update) for each Service Year as follows:

769.

The parties also agreed a mechanism to vary those charges for the following service year based on the number of transactions in the prior service year (‘the Charges Variation Clause’): Section 2.8 Schedule 2-3. The relevant provisions are:

‘2.8.4 If the Actual Transaction Percentage exceeds 110% (one hundred and ten percent) then the Transaction Charges for the subsequent Service Year may, at the Authority’s option, be reduced such that in the subsequent Service Year, the reduced Transaction Charges multiplied by the Predicted Transaction Volumes would give an under-recovery of Forecast Revenue in that Service Year equivalent (within 2%) to the over-recovery of the Forecast Revenue in excess of the 110% cap in the prior Service Year. The revised Transaction Charges shall apply from 1st April of the relevant year.

2.8.5

If the Actual Transaction Percentage is lower than 85% eighty five percent) but greater than 75% (seventy five percent) then the Transaction Charges for the subsequent Service Year shall be increased such that in the subsequent Service Year, the increased Transaction Charges multiplied by the Predicted Transaction Volumes would give an over-recovery of Forecast Revenue in that Service Year equivalent (within 2%) to the under-recovery of the Forecast Revenue in excess of the 85% cap in the prior Service Year. The revised Transaction Charges shall apply from 1st April of the relevant year. For illustration purposes only if the Actual Transaction Percentage equals 82% then the increase in Transaction Charges for the subsequent Service Year shall be such that the over recovery in the subsequent Service Year is equivalent to 3%, the difference between 82% and 85%.’

770.

There was a slightly different procedure relating to the final service year: Sub-Section 2.8.8:

2.8.8 At the end of the Service Year 4 a minimum Transaction Volume shall be agreed for Service Year 5, on which the Volume Based Service Charge shall be calculated. This minimum Transaction Volume shall be 85% of the current Predicted Transaction Volume prevailing after any variation to the Predicted Transaction Volume made at the end of Service Year 4.’

771.

Relevant terms within these clauses are defined as follows:

(1)

Forecast Revenue” is defined as “the revenue earned by the CONTRACTOR as stated in the Financial Model, cell Y21 in the summary worksheet

(2)

“Predicted Transaction Volume” is defined as “the entries within the Financial Model for each of the Basic Disclosure, Standard Disclosure, Enhanced Disclosure, Updated Service Applications and Update Service Renewals’.

772.

The FM is referenced at Clause 20 of the Agreement, headed ‘Financial Model’. It states simply:

‘The provisions of schedule 2.3 (The Charges and Charges Variation Procedure) shall apply in relation to the Financial Model and the parties shall comply with their respective obligations under schedule 2-3 (The Charges and Charges Variation Procedure) in this regard.’

773.

It is also relevant that Clause 2.3.3 of Schedule 2-3 states;

‘2.3.3 The Volume Based Service Charges shall be calculated each Month as follows:

2.3.3.1 for each type of Transaction, the actual volume of transactions in the Month shall be multiplied by the Transaction Charges in Table 1 or Table 2 above (as applicable), subject to any variation to the Transaction Charges arising from the provisions in paragraph 2.8, Charges Variation, of this Schedule 2-3.

2.3.3.2 the total Transaction Charges for each type of Transaction are then summed to give the monthly Transaction Charge.’

774.

The parties disagree in two respects about the proper construction of these provisions, and, as the case was closed, one remaining factual dispute. These issues are relevant to the proper calculations to be carried out pursuant to the Charges Variation Clause. The three remaining issues are (numbered as per the parties’ submissions prior to Issue 3 falling away):

Issue 1: How the amount of an ‘over-recovery of the Forecast Revenue’ (Clause 2.8.4) or ‘under-recovery of the Forecast Revenue’ (Clause 2.8.5) is to be measured. This is an issue of construction.

Issue 2: Whether the Predicted Volumes for Basics in Service Year 4 were 1,000,000 (TCS’s case) or 320,374 (DBS’s case). This is an issue of fact.

Issue 4: How Clause 2.8.8 of Schedule 2-3 applied to Volume Based Service Charges in Service Year 5. This is an issue of construction.

775.

The forensic accountant experts have agreed the results, depending upon the resolution of the points of contractual and factual difference, as set out in the following table:

Issue 1

Issue 2

Issue 4

Under/(Over) Payment

SY4&5 ATC

1m v 320k

85% floor v fixed

TCS

TCS

TCS

15,164,816

DBS

4,467,391

DBS

TCS

14,373,890

DBS

4,711,157

DBS

TCS

TCS

6,976,737

DBS

(2,024,573)

DBS

TCS

5,132,634

DBS

(2,329,641)

776.

Thus it can be seen that the result of the Court deciding each sub-issue in accordance with TCS’s case is that TCS would have been underpaid by £15,164,816. If each issue were determined in accordance with DBS’s case, DBS has overpaid TCS by £2,329,641.

777.

I will deal with Issues 1 and 4 (the issues of construction) first.